SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 931

IN THE HIGH COURT AT CALCUTTA
ARIJIT BANERJEE, OM NARAYAN RAI, JJ.
M/s. Konarak Enterprise - Appellant
Versus
Haldia Development Authority - Respondent
APOT 76 of 2025, AP-COM 229 of 2024, AP-COM 255 of 2024, IA No.GA-COM 1 of 2025, APOT 135 of 2025
Decided On : 25-09-2025

Advocates Appeared:
For the Appellant : Mr. Subhabrata Datta, Adv., Mr. Aranya Saha, Adv.
For the Respondent: Mr. Swarajit Dey, Adv., Mr. Saptarshi Kar, Adv., Ms. Debarati Das, Adv.

Under the Arbitration and Conciliation Act, the court can only interfere with an arbitral award on limited grounds; the contractor's claim for security deposit was valid, as the limitation period commenced at the conclusion of the work.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37, Section 34 - Appeal against arbitral award - The appellant challenged parts of the award related to the non-completion of contracted work and claim for security deposit - The Court emphasized the limited scope of interference under Section 34. (Paras 33, 70)

(B) Interpretation of Clauses - The learned Arbitrator found that the work was not completed by the contractor, justifying Haldia's invocation of the risk and cost principle for additional expenses incurred due to re-awarding unfinished work to another contractor. (Paras 38, 66)

(C) Limitation Period - The Court ruled that the period of limitation for claims commenced post-completion of the work and was adequately extended, leading to the conclusion that the claim for the refund of the security deposit was not barred. (Paras 67, 72)

Facts of the case:
The contractor was awarded work to construct a road, but disputes about payments and completion arose. After arbitration proceedings, Haldia claimed compensation for unfinished work, while the contractor sought the return of the security deposit. The Arbitrator concluded that the contractor did not complete the work and calculated the costs incurred by Haldia for engaging a new contractor. (Paragraphs 1-4)

Findings of Court:
The court upheld the Arbitrator's findings regarding the non-completion of work and the compensation due to Haldia under the contract's provisions. Additionally, the court found no reasons to disturb the award of refunding the remaining security deposit to the contractor after necessary deductions. (Paragraphs 76-77)

Issues: The Court primarily addressed whether the contractor completed the work, entitlement to compensation due to unfinished work, and the applicable limitation period for claims regarding the security deposit. (Paragraphs 35, 49, 66)

Ratio Decidendi: The court reaffirmed that under Section 34, it could only review the legality of the award, not the merits. It found that the Arbitrator's conclusions were well-supported and did not warrant interference, particularly regarding limitations and contract interpretations. (Paragraphs 33, 76)

Result: Appeals dismissed, maintaining the Arbitrator's conclusions and the single judge's order affirming parts of the award.

Table of Content
1. overview of appeals and basic facts of the case. (Para 1 , 2)
2. arguments presented by konarak against haldia’s claims. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21)
3. court’s analysis on procedural and contextual validity of claims. (Para 32 , 33 , 34 , 35 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 56 , 66 , 67 , 68 , 69 , 70 , 71)
4. key legal standards and definitions regarding arbitral awards. (Para 60 , 62 , 64 , 77)
5. final ruling and dismissal of appeals. (Para 78)

JUDGMENT :

OM NARAYAN RAI, J.

1. These two appeals under Section 37 of the Arbitration and Conciliation Act, 1996 (hereafter referred to “the said Act of 1996”) assail a common order dated January 17, 2025 passed by an Hon’ble Single Judge of this Court whereby two applications under Section 34 of the said Act of 1996, being AP-COM No. 229 of 2024 filed by Haldia Development Authority (hereinafter referred to as “Haldia”) and AP-COM 255 of 2024 filed by M/s. Konarak Enterprise (hereinafter referred to as “Konarak”) were disposed of. By the order impugned AP-COM No. 229 of 2024 has been allowed in part and AP-COM No. 255 of 2024 has been dismissed.

FACTS OF THE CASE:-

2. Summed up briefly, the undisputed facts of the case, as may be gathered from the material on record, are as follows:-

a) Haldia had floated a Notice Inviting Tender (NIT) for construction of road from Gholpukur to Tekhali Bridge via Amdabad High School at Nandigram (Part- A).

b) Konarak participated in the said tender process and emerged successful, whereafter the work of construction of road from Gholpukur to Tekhali Bridge via Amdabad High School at Nandigram (Part - A) was awarded to Konarak by way of a work order dated February 18, 2009.

c) Certain disputes arose between the parties regarding payments (including refund of security deposit) claimed by Konarak in respect of the work awarded to it by Haldia.

d) As the relevant contract governing the parties (i.e. the work order issued by Haldia in favour of Konarak) and the terms of the NIT provided for resolution of disputes through arbitration, Konarak sought reference of the same to a learned Arbitrator for adjudication. However, as the learned Arbitrator could not be appointed in terms of the arbitration agreement, Konarak approached this Court by filing an application under Section 11 of the said Act of 1996 which was registered as A.P. 235 of 2017.

e) The said application was disposed of by an order dated April 27, 2017 thereby appointing a learned Arbitrator to adjudicate upon the disputes that had cropped up between the parties.

f) Thereafter, Konarak filed its statement of claim before the learned Arbitrator, thereby laying the following three claims: -

i. Refund of security deposit laying in the custody of the respondent along with interest calculated upto 30.10.2016 at the rate of 12%;

ii. Delayed interest on the principal amount of the Final Bill upto 30.10.2016 at the rate of 12%;

iii. Further interests from 01.11.2016 till payment at the rate of 12%; and iv. Costs.

g) The respondent contested the claim by filing its counter statement cum counter-claim thereby denying all the material allegations made in the statement of claim and laying a counter claim of Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand Nine Hundred and Twenty Two) on the ground that Haldia had to get the balance work left unfinished by Konarak, by a third party upon the payment of the said sum of Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand Nine Hundred and Twenty Two).

h) The sole learned Arbitrator disposed of the arbitral proceedings by making and publishing an award on February 29, 2020 thereby partly allowing Konarak’s claim and rejecting the counter-claim filed by Haldia.

i) After receiving the said award, Konarak filed an application under section 33 of the said Act of 1996 seeking rectification of a few mistakes that, according to Konarak, were apparent on t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top