IN THE HIGH COURT AT CALCUTTA
ARIJIT BANERJEE, OM NARAYAN RAI, JJ.
M/s. Konarak Enterprise - Appellant
Versus
Haldia Development Authority - Respondent
APOT 76 of 2025, AP-COM 229 of 2024, AP-COM 255 of 2024, IA No.GA-COM 1 of 2025, APOT 135 of 2025
Decided On : 25-09-2025
| Table of Content |
|---|
| 1. overview of appeals and basic facts of the case. (Para 1 , 2) |
| 2. arguments presented by konarak against haldia’s claims. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21) |
| 3. court’s analysis on procedural and contextual validity of claims. (Para 32 , 33 , 34 , 35 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 56 , 66 , 67 , 68 , 69 , 70 , 71) |
| 4. key legal standards and definitions regarding arbitral awards. (Para 60 , 62 , 64 , 77) |
| 5. final ruling and dismissal of appeals. (Para 78) |
JUDGMENT :
OM NARAYAN RAI, J.
1. These two appeals under Section 37 of the Arbitration and Conciliation Act, 1996 (hereafter referred to “the said Act of 1996”) assail a common order dated January 17, 2025 passed by an Hon’ble Single Judge of this Court whereby two applications under Section 34 of the said Act of 1996, being AP-COM No. 229 of 2024 filed by Haldia Development Authority (hereinafter referred to as “Haldia”) and AP-COM 255 of 2024 filed by M/s. Konarak Enterprise (hereinafter referred to as “Konarak”) were disposed of. By the order impugned AP-COM No. 229 of 2024 has been allowed in part and AP-COM No. 255 of 2024 has been dismissed.
FACTS OF THE CASE:-
2. Summed up briefly, the undisputed facts of the case, as may be gathered from the material on record, are as follows:-
a) Haldia had floated a Notice Inviting Tender (NIT) for construction of road from Gholpukur to Tekhali Bridge via Amdabad High School at Nandigram (Part- A).
b) Konarak participated in the said tender process and emerged successful, whereafter the work of construction of road from Gholpukur to Tekhali Bridge via Amdabad High School at Nandigram (Part - A) was awarded to Konarak by way of a work order dated February 18, 2009.
c) Certain disputes arose between the parties regarding payments (including refund of security deposit) claimed by Konarak in respect of the work awarded to it by Haldia.
d) As the relevant contract governing the parties (i.e. the work order issued by Haldia in favour of Konarak) and the terms of the NIT provided for resolution of disputes through arbitration, Konarak sought reference of the same to a learned Arbitrator for adjudication. However, as the learned Arbitrator could not be appointed in terms of the arbitration agreement, Konarak approached this Court by filing an application under Section 11 of the said Act of 1996 which was registered as A.P. 235 of 2017.
e) The said application was disposed of by an order dated April 27, 2017 thereby appointing a learned Arbitrator to adjudicate upon the disputes that had cropped up between the parties.
f) Thereafter, Konarak filed its statement of claim before the learned Arbitrator, thereby laying the following three claims: -
i. Refund of security deposit laying in the custody of the respondent along with interest calculated upto 30.10.2016 at the rate of 12%;
ii. Delayed interest on the principal amount of the Final Bill upto 30.10.2016 at the rate of 12%;
iii. Further interests from 01.11.2016 till payment at the rate of 12%; and iv. Costs.
g) The respondent contested the claim by filing its counter statement cum counter-claim thereby denying all the material allegations made in the statement of claim and laying a counter claim of Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand Nine Hundred and Twenty Two) on the ground that Haldia had to get the balance work left unfinished by Konarak, by a third party upon the payment of the said sum of Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand Nine Hundred and Twenty Two).
h) The sole learned Arbitrator disposed of the arbitral proceedings by making and publishing an award on February 29, 2020 thereby partly allowing Konarak’s claim and rejecting the counter-claim filed by Haldia.
i) After receiving the said award, Konarak filed an application under section 33 of the said Act of 1996 seeking rectification of a few mistakes that, according to Konarak, were apparent on t
Associate Builders vs. Delhi Development Authority
Gayatri Balasamy vs. ISG Novasoft Technologies Ltd.
Dyna Technologies Private Limited vs. Crompton Greaves Limited
Under the Arbitration and Conciliation Act, the court can only interfere with an arbitral award on limited grounds; the contractor's claim for security deposit was valid, as the limitation period com....
The court held that the tribunal's award of refund and risk and cost compensation was justified, but the risk and cost amount should be modified to reflect the corrected value of work done.
The court reinforced that under the Arbitration and Conciliation Act, 1996, the scope for judicial interference with arbitral awards is limited, particularly regarding factual findings.
The main legal point established in the judgment is the interpretation of contract terms, breach of contract, and the limited scope of interference with the arbitrator's award based on the violation ....
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
The court upheld the Arbitrator's findings that the rescission of the contract was unjust and delays were primarily attributable to the petitioner, affirming the award under Section 34 of the Arbitra....
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.