IN THE HIGH COURT OF DELHI
VIBHU BAKHRU, J.
PCL Suncon - Appellant
Versus
National Highway Authority of India - Respondent
O.M.P.(T). (COMM.). No. 80 of 2020
Decided On : 12-01-2021
Arbitration - Arbitration Proceedings Termination - Arbitration and Conciliation Act, 1996 - Section 32(2)(c)
Fact of the Case:
The petitioner, a Joint Venture, filed a petition challenging the termination of arbitral proceedings under Section 32(2)(c) of the Arbitration and Conciliation Act, 1996. The petitioner claimed that there was a communication gap and was not aware that the arbitrator appointed by it had resigned. The Arbitral Tribunal terminated the proceedings due to the petitioner's failure to nominate another arbitrator in place of the resigned arbitrator.
Finding of the Court:
The court held that the impugned order terminating the arbitral proceedings did not constitute an award and could be challenged under Section 14(2) of the A&C Act. The court set aside the impugned order, subject to the petitioner paying costs of Rs.25,000 to NHAI.
Issues: The main issue was whether the impugned order constituted an award and whether the petitioner's delay in appointing an arbitrator justified the termination of the arbitral proceedings.
Ratio Decidendi: The court clarified that an order terminating the arbitral proceedings under Section 32(2)(c) of the A&C Act is not an award and can be challenged under Section 14(2) of the A&C Act. The court also held that the petitioner's delay warranted costs to be paid to NHAI.
Final Decision: The court set aside the impugned order, subject to the petitioner paying costs of Rs.25,000 to NHAI and directed the Arbitral Tribunal to resume the proceedings and conclude them expeditiously.
JUDGMENT :
1. The petitioner – a Joint Venture constituted by Progressive Construction Limited and SUNCON Construction Berhard, Malaysia – has filed the present petition, inter alia, impugning an order dated 20.04.2020 passed by the two arbitrators terminating the arbitral proceedings under Section 32(2)(c) of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’).
2. The present application is filed under Section 14(1)(a) read with Section 15 of the A&C Act. The petitioner further prays for substitution of the Arbitrator by an independent arbitrator appointed by this Court.
3. The arbitral proceedings were terminated because the arbitrator nominated by the petitioner had resigned and the petitioner had not taken steps to nominate another arbitrator in his place. Consequently, the arbitral proceedings could not proceed and the remaining two arbitrators constituting the Arbitral Tribunal concluded that it was impossible to continue the proceedings and, accordingly, terminated the same. The petitioner claims that there was a communication gap and the petitioner was not aware that the arbitrator appointed by it had resigned. The Arbitral Tribunal had not issued any notice to the petitioner in this regard prior to terminating the arbitral proceedings.
4. The respondent (hereinafter ‘NHAI’) contests the maintainability of the present petition as well as contends that the impugned order cannot be faulted.
5. The aforesaid controversy arises in the following context.
6. NHAI had invited bids for “Four laning and Strengthening of the Existing two lanes between Km. 317 and Km. 65 on NH-2, in State of U.P. and Bihar for construction Package IV-A: Contract Agreement No. GTRIP/5.” Pursuant to the said notice inviting tenders, the petitioner submitted its bid on 15.12.2001 and it was opened on the same day. The petitioner’s bid was accepted and by a letter dated 23.02.2002, the petitioner was awarded the contract for an amount of Rs.3,96,47,78,901/-. A formal agreement between the parties was executed on 28.03.2002. The works were divided into three sections. The first section was to be completed within a period of eighteen months from the date of commencement; the second section was to be completed within a period of twenty four months from the date of commencement; and the third section was to be completed within a period of thirty six months from the date of commencement, that is, by 30.03.2005.
7. The petitioner claims that certain disputes arose between the parties in respect of the said contract. NHAI claims that the petitioner did not complete the works within the stipulated time and therefore, was liable to pay liquidated damages. The petitioner invoked the arbitration clause. It claimed Rs.57,84,00,000/- towards overstay/overhead charges; Rs.2,50,00,000 as refund of the liquidated damages deducted by NHAI; and Rs.40,04,000/- for rehabilitation of Bridge 58/1. The petitioner also claimed waiver of liquidated damages. In addition, the petitioner also claimed interest (pre-suit pendente lite as well as future interest) as well as costs quantified at Rs.10 lacs.
8. The petitioner also filed a petition under Section 9 of the A&C Act (O.M.P. 1019/2013) seeking certain measures of interim protection. The said petition was disposed of by an order dated 09.01.2015 and the recovery of liquidated damages was stayed during the arbitral proceedings.
9. The petitioner nominated Justice E. Padmanabhan (Retd.) as its nominee arbitrator. NHAI appointed Mr. S.R. Pandey as its nominee and both the nominated arbitrators nominated Mr. B. Majumdar as the Presiding Arbitrator. With the appointment of the Presiding Arbitrator on 03.08.2015, the Arbitral Tribunal was constituted. The petitioner filed its statement of claims and NHAI also filed counter claims before the Arbitral Tribunal inter alia claiming Rs.37,15,00,000/- as loss due to short recovery of liquidated damages; Rs.60,55,04,379/- as loss of toll revenue from 20.07.2006 to 17.05.2008;
Gangotri Enterprises Limited v. NTPC Tamil Nadu Energy Company Limited: (2017) 237 DLT 690
Indian Farmers Fertilizer Cooperative Limited v. Bhadra Products: (2018) 2 SCC 534
Satwant Singh Sodhi v. State of Punjab and Ors.: (1999) 3 SCC 487
An order terminating arbitral proceedings under Section 32(2)(c) of the A&C Act is not an award and can be challenged under Section 14(2) of the A&C Act. Delay in appointing an arbitrator may warrant....
An order terminating the arbitral proceedings under Section 32(2)(c) of the Arbitration and Conciliation Act, 1996, is not equivalent to an arbitral award and cannot be challenged under Section 34 of....
The unilateral appointment of an Arbitrator is invalid, and parties retain the right to seek an independent substitute Arbitrator for unresolved counter-claims following termination of arbitral proce....
An order rejecting an amendment to a statement of claim is not an interim award under Section 34 of the Arbitration Act, as it does not determine substantive issues or rights in the arbitration.
An order under Section 32(2)(c) of the Arbitration Act does not constitute an arbitral award and is not subject to challenge under Section 34.
The court affirmed that termination of arbitral proceedings does not permit the appointment of a substitute arbitrator without reviving prior termination, emphasizing procedural adherence in arbitrat....
The challenge for the appointment of Arbitrator under Section 13 of the Act can only be made along with the final award under Section 34.
No power has been invested by Parliament in the Court to remand the matter to the Arbitral Tribunal except to adjourn the proceedings for the limited purpose mentioned in sub-section (4) of Section 3....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.