IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Indian Highways Management Company Limited - Appellant
Versus
Sowil Limited - Respondent
Original Miscellaneous Petition (COMM) No. 376 of 2021, Miscellaneous Application No. 17159, 17160 of 2021
Decided On : 21-12-2021
Arbitration and Conciliation Act - Traffic Surveys - Sections 34, 15, 16, 17, 18, 19, 24 of the MSMED Act - The court discussed the actions of IHMCL in relation to the Contract and the 2018 RFP, the claims made by SOWiL, and the findings of the Arbitral Tribunal. The court analyzed the applicability of the MSMED Act, the obligations of the buyer under Sections 15 and 16, and the dispute resolution mechanism under Section 18. The court held that the provisions of the MSMED Act would override the provisions of the A&C Act to the extent of any repugnancy, and the impugned award was not vitiated by patent illegality or in conflict with the public policy of India.
Fact of the Case:
The case involved a dispute between IHMCL and SOWiL regarding the Contract for conducting traffic surveys on National Highways. IHMCL issued the 2018 RFP, leading to disagreements and claims by SOWiL. The Arbitral Tribunal considered the claims and rendered an award in favor of SOWiL for various sums.
Finding of the Court:
The court dismissed the petition, finding that the impugned award was not vitiated by patent illegality or in conflict with the public policy of India.
Issues: The issues included the applicability of the MSMED Act, the obligations of the buyer under Sections 15 and 16, and the dispute resolution mechanism under Section 18.
Ratio Decidendi: The court held that the provisions of the MSMED Act would override the provisions of the A&C Act to the extent of any repugnancy, and the impugned award was not vitiated by patent illegality or in conflict with the public policy of India.
Final Decision: The petition was dismissed, and all pending applications were disposed of.
JUDGMENT
Vibhu Bakhru, J. - The petitioner (hereafter IHMCL) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning an arbitral award dated 11.10.2021 (hereafter the impugned award) rendered by an Arbitral Tribunal constituted by Justice (Retired) Badar Durrez Ahmed as the Sole Arbitrator (hereafter the Arbitral Tribunal).
2. The Arbitral Tribunal has rendered the impugned award in the context of disputes that have arisen between the parties in relation to a contract dated 28.10.2014 for "Conducting Traffic Surveys on National Highways in Zone-5 (in the States of Odisha, West Bengal and North Eastern States) using Portable Automatic Traffic Counter & Classified (ATCC) Systems" (hereafter the Contract).
Factual Context
3. The respondent (hereafter SOWiL) is a small enterprise under the Micro, Small, Medium Enterprise Development Act, 2006 (hereafter the MSMED Act) and is, inter alia, engaged in the business of providing consultancy services to various organizations for development works, railway works, bridges, structures and tunnelling.
4. IHMCL is a public limited company incorporated under the Companies Act, 1956 and provides services in relation to management of toll collection on National Highways through electronic toll systems; assessment of the volume of traffic; and collection of data through traffic surveys using portable Automatic Traffic Counter-cum-Classifiers (ATCC).
5. The Ministry of Road Transport and Highways (hereafter MORTH) had instructed IHMCL to conduct traffic surveys on the National Highways in India. Accordingly, on 13.05.2015, IHMCL issued a Request for Proposal (hereafter 2014 RFP) inviting bids for conducting traffic surveys using portable ATCC in seven zones on the National Highways in India (hereafter the Project). SOWiL participated in the bid for Zone-5 and was declared as the successful bidder.
6. IHMCL issued a Letter of Award (hereafter LOA) to SOWiL on 13.08.2014. Consequently, on 28.10.2014, the parties entered into the Contract in respect of the aforesaid Project, for a contract value of Rs. 68,03,80,000/-. In terms of the Contract, SOWiL agreed to conduct traffic surveys twice a year for a period of five years, at the specified locations.
7. SOWiL claims that, during the term of the Contract, IHMCL issued another RFP on 08.03.2018 bearing no. IHMCL/Portable-ATCC/March/2018 (hereafter the 2018 RFP) and invited bids on a Price Discovery Mechanism for the balance works being carried out by SOWiL in Zone-5. Thereafter, IHMCL expressed its intention to terminate the Contract in terms of Article 12.2 of the Contract.
8. It is SOWiLs case that IHMCLs proposed invocation of Article 12.2 of the Contract to terminate the Contract during its tenure, for convenience, is a breach of the terms of the Contract. IHMCL countered the same and stated that an exercise of price discovery is not a breach of the Contract. It further contended that the prices under the 2014 RFP were higher and thus, it intended to award the remaining four rounds at a lower rate to save public money.
9. Aggrieved by the same, SOWiL filed a petition before this Court under Section 9 of the A&C Act [being OMP (I) (COMM) 169/2018] and by an order dated 19.04.2018, this Court restrained IHMCL from terminating the Contract. This Court, by an order dated 24.04.2018, further restrained IHMCL from awarding contracts pursuant to the 2018 RFP to any third party in respect of the locations that were awarded to SOWiL.
10. On 10.08.2018, SOWiL filed a petition under Section 11 of the A&C Act [being Arb. P. 593/2018] and this Court, by an order dated 30.10.2018, constituted the Arbitral Tribunal. This Court also disposed of the petition under Section 9 of the A&C Act with the direction that "the petitioner (SOWiL) shall continue to work on the sites that were already allocated to it in terms of the contract between the parties, however, shall be paid in accordance with L-1 rates th
Vedanta Ltd. vs. Shenzen Shandong Nuclear Power Construction Co. Ltd.: (2019) 11 SCC 465
The MSMED Act prevails over A&C Act provisions regarding interest, granting small enterprises specific rights on delayed payments independent of dispute resolution processes.
EM-II filing discretionary for micro/small enterprises beyond 180 days; MSMED reference limitation starts from buyer's post-investigation denial, not supply date; narrow Section 34 scope upholds awar....
If any registration under the MSMED Act is obtained, the same will be prospective and would apply to supply of goods and services subsequent to registration but cannot operate retrospectively. Accord....
The lack of conciliation does not undermine the statutory obligation to make payment under the MSMED Act, emphasizing the importance of adherence to payment timelines by the buyer.
The Court upheld the impugned Award and emphasized the finality of arbitral awards, reinforcing the limited grounds for challenging an award under the Arbitration and Conciliation Act, 1996.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.