SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 1001

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Millennium School - Appellant
Versus
Pawan Dawar - Respondent
Original Miscellaneous Petition (COMM) No. 590 of 2020
Decided On : 10-05-2022

Advocates appeared:
Abhijeet Sinha, Advocate, Archit Singh Gyani, Advocate, Aditya Shukla, Advocate, Amit Aggarwal, Advocate, Pramod Kumar Sharma, Advocate, Prashant Bajaj, Advocate

The main legal point established in the judgment is that the termination of an agreement must be in accordance with the terms of the agreement, and the grounds for termination must be within the agreement.

Headnote:

arbitration and Conciliation act - Termination of Agreement - Clauses 1, 30, 31, 32, 33, 34, 35 - The court found that the termination of the agreement was legal and valid, and the grounds for termination were within the agreement. The court also found that the petitioner was entitled to terminate the agreement during the lock-in period on account of any fundamental breach on the part of the respondent.

Fact of the Case:

The petitioner terminated an agreement with the respondent for transport services, leading to disputes referred to arbitration. The arbitral Tribunal partially accepted the respondent's claims, leading to the petitioner filing a petition under Section 34 of the arbitration and Conciliation act, 1996.

Finding of the Court:

The court found that the termination of the agreement was legal and valid, and the grounds for termination were within the agreement. The court also found that the petitioner was entitled to terminate the agreement during the lock-in period on account of any fundamental breach on the part of the respondent.

Issues: The issues included the validity of the termination of the agreement, deficiency in the services provided by the respondent, and the outstanding payments due.

Ratio Decidendi: The court held that the termination of the agreement was legal and valid, and the grounds for termination were within the agreement. The court also found that the petitioner was entitled to terminate the agreement during the lock-in period on account of any fundamental breach on the part of the respondent.

Final Decision: The court set aside the impugned award to the extent it allowed the respondent's claim for loss of profits and cab charges to the extent of ?12 lakhs.

JUDGMENT

Vibhu Bakhru, J. - The petitioner has filed the present petition under Section 34 of the arbitration and Conciliation act, 1996 (hereinafter the 'a&C act') impugning an arbitral award (hereinafter the 'impugned award') dated 28.02.2020 delivered by an arbitral Tribunal comprising of a Sole arbitrator (hereinafter the 'arbitral Tribunal').

2. The impugned award was rendered in the context of disputes that have arisen between the parties in relation to the agreement dated 01.04.2012.

Factual Context

3. Mr Pawan Dawar (hereinafter 'the respondent') is engaged in the business of providing transport services and carries on his business under the name and style of his proprietorship concern M/s Genesis Enterprises (hereinafter 'GE').

4. On 01.04.2012, the parties entered into an agreement, whereby the respondent agreed to provide transport services to the petitioner. The petitioner owned twenty-two school buses, which the respondent agreed to operate and maintain. The respondent was required to provide conductors, drivers, supervisors, cleaners, full time mechanics and other personnel. In addition, the respondent also agreed to provide additional buses for the purposes of picking up and dropping off the students and the employees of the petitioner.

5. The agreement was for a term of eight years, that is, from 01.04.2012 till 31.03.2020 with the first five years as a lock in period. Further, the respondent agreed to strictly abide by the obligations stipulated in the agreement such as, adhering to the timing for transportation of students; regular maintenance of the buses, maintaining motorable conditions of the buses; complying with the safety guidelines issued by the Supreme Court of India; limiting the number of students transported in each bus to the permissible limit; and, in the event of breakdown of buses, providing alternate vehicles etc.

6. Thereafter, by a communication dated 07.06.2015, the respondent requested the Principal of the petitioner school to release the outstanding payments in terms of the agreement. He further stated that even though, the petitioner was collecting the transportation fee from the students well in advance, however, the petitioner was making payments to him in petty instalments after a delay of a substantial period.

7. The Principal of the petitioner school responded by an e-mail dated 05.08.2015 alleging deficiencies in the services provided by the respondent and further, informed him that the petitioner would be compelled to take strict action if the said deficiencies were not rectified within a period of seven-ten days. Thereafter, by a communication dated 03.09.2015, the petitioner terminated the agreement.

8. aggrieved by the termination of the agreement, the respondent invoked the agreement to refer the disputes to arbitration, in terms of Clause 36 of the agreement. This Court, by an order dated 04.04.2018, passed in O.M.P. (T) (COMM) 55 of 2017 captioned Pawan Dawar v. Millennium School directed the Delhi International arbitration Centre (DIaC) to appoint an arbitrator to adjudicate the disputes between the parties. Thereafter, the arbitral Tribunal entered upon reference on 07.06.2018.

9. Before the arbitral Tribunal, the respondent filed its Statement of Claims. a tabular statement stating the claims made by the respondent are summarised below:-

Claim 1

Outstanding Contractor Fee

Rs. 1,16,16,950/-

Claim 2

Interest payable on the delayed and outstanding contractor fee calculated upto 31.03.2016

Rs.50,65,242/-

Claim 3

Loss of Profits from the remaining period out of the lock- in period i.e. 03.09.2015 till31.03.2017

Rs.93,97,202/-

Claim 4

Contractor fee due and payable with respect to cabs

Rs.65,13,755/-

Claim 5

Interest payable on the delayed and outstanding contractor fee for cabs calculated upto31.03.2016.

Rs.20,98,346/-

Claim 6

Contractor fee due and payable on account of transportation fee with respect to the wards of teachers and accountant MrSatinder Dwivedi

Rs.2,91,758/-

Claim 7

Insurance Premium r

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon Back to top