SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 1804

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Wapcos Limited - Appellant
Versus
C & C Energy Private Limited - Respondent
FAO (Comm) 53 of 2021
Decided On : 20-10-2022

Advocates appeared:
Mr. Varun Sharma, Advocate., for the Appellant; Mr. Arshdeep Singh Khurana & Ms. Tannavi Sharma, Advocates., for the Respondent

The main legal point established is that the interpretation of contractual obligations and the discretion of the Arbitral Tribunal in awarding interest are crucial in determining the enforceability of arbitration awards.

Headnote:

Arbitration and Conciliation Act - Wapcos Limited - Section 34

Fact of the Case:

M/s Wapcos Limited appealed the rejection of its application under Section 34 of the Arbitration and Conciliation Act, impugning the award dated 13.06.2019. The dispute arose from a contract with C&C Energy Pvt. Ltd. for the supervision of a power plant project in Rwanda. The Arbitral Tribunal partially allowed C&C's claims and rejected Wapcos' counter-claims.

Finding of the Court:

The court found that C&C had performed its obligations under the Agreement and was entitled to the agreed consideration. It also upheld the award of interest at the rate of 18% per annum. The court rejected Wapcos' application under Section 34 of the A&C Act.

Issues: The key issues were whether C&C had fulfilled its obligations under the Agreement, the interpretation of payment milestones, and the legality of the interest rate awarded by the Arbitral Tribunal.

Ratio Decidendi: The court held that C&C's obligation was limited to providing manpower as agreed, and it had fulfilled this obligation. The court also upheld the Arbitral Tribunal's discretion in awarding interest at the rate of 18% per annum.

Final Decision: The court dismissed Wapcos' appeal and upheld the rejection of its application under Section 34 of the A&C Act.

JUDGMENT

Vibhu Bakhru, J. - M/s Wapcos Limited (hereinafter 'Wapcos') has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act (hereinafter 'the A&C Act') impugning a common judgement dated 31.07.2020 (hereinafter 'the impugned judgement') passed by the learned Commercial Court, whereby it had rejected the applications filed by Wapcos and M/s C & C Energy Private Limited (hereinafter 'C&C') under Section 34 of the A&C Act. The parties had preferred their respective applications, impugning the award dated 13.06.2019  (hereinafter 'the impugned award') to the extent that they were aggrieved. Wapcos assails the impugned judgement to the limited extent that it rejects its application under Section 34 of the A&C Act [being OMP(Comm) No. 167/2009 captioned M/s WAPCOS Limited vs C & C Energy Private Limited].

Factual Background

2. On 18.09.2012, the Energy Water and Sanitation Authority of Rwanda (EWSA, Rwanda) awarded a contract to Wapcos for 'supervision of engineering-procurement-construction of 15 MW peat-to-power plant in Rwanda' (hereinafter 'the Project').

3. Thereafter, on 21.01.2013, Wapcos and C&C entered into an agreement (hereinafter 'the Agreement'), whereby C&C agreed to assist in the supervision of the Project. The Agreement was for a term of fifteen months from the date of execution of the Agreement, that is, until 20.04.2014. In terms of Article 9 of the Agreement, the remuneration and payment for the services was fixed at ?1,64,43,000/-, excluding all taxes against the provision of manpower for carrying out the tasks.

4. The scope of work to be performed by Wapcos and C&C was contingent upon the work executed by the Engineering Procurement Construction (EPC) Contractor engaged by EWSA, Rwanda. The EPC Contractor delayed in completing its work, rendering Wapcos and C&C unable to complete their work within the stipulated period of time. The parties were only able to complete 50% of the work within the stipulated period of fifteen months.

5. C&C contends that on account of failure of the EPC Contractor to complete its work in time, it sent a letter dated 17.03.2014, requesting for an extension of time for a period of six months or until the completion of the erection of plant by the EPC Contractor. C&C also stated that the financial remuneration for this would be agreed mutually. C&C states that it continued to work and provided seventy-six (76) additional man-days for the work. Thereafter, it withdrew its manpower.

6. C&C raised invoices amounting to ?1,86,44,882/-. Against the said invoices, Wapcos only paid an amount of ?1,16,57,067/-. The remuneration for the additional man-days provided by C&C amounted to ?13,68,684/-, against which Wapcos did not make any payment.

7. Thereafter, disputes arose between Wapcos and C&C regarding the payment of the balance amount. After no result came from trying to resolve the disputes amicably, C&C invoked the agreement to refer the disputes to arbitration, in terms of Article 11.5 of the Agreement. However, the parties failed to agree on the appointment of an arbitrator. Thereafter, C&C, by way of a petition under Section 11 of the A&C Act, approached this Court for appointment of an arbitrator. By an order dated 30.05.2017, this Court referred the parties to the Delhi International Arbitration Centre (DIAC). The Arbitral Tribunal was constituted under the Rules of the DIAC. Arbitration

8. Before the Arbitral Tribunal, C&C filed its Statement of Claims. The claims made by C&C in the Statement of Claims are tabulated below:

Claim No.

Particulars

Amount

1.

Recovery towards services/man-days provided under the contract

Rs.69,87,815/-

2.

Recovery towards the additional man-days provided

Rs.13,68,684/-

3.

Interest on Claim nos. 1 and 2 at the rate of 18% per annum up to 15.08.2017

Rs.15,87,900/-

4.

Pendente lite interest at the rate of 18% per annum

 

5.

Preventive injunction/Preservation of assets

 

6.

Costs

 

 

9. Wapcos filed its Statement of Defence and contested

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top