IN THE HIGH COURT OF DELHI AT NEW DELHI
Manmohan, Mini Pushkarna, JJ.
Steel Authority of India Ltd. – Appellant
Versus
M/s Larsen And Toubro Ltd. & Anr. – Respondents
FAO(OS) (COMM) 138 of 2021 & CM Appls. 39516 of 2021 & 39517 of 2021
Decided On : 24-07-2023
Arbitration Act - Withholding of Amount - Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 - [Section 37(1)(c) of the Arbitration Act, 1996 read with Section 13 of the Commercial Courts Act, 2015] - [Section 34 of the Arbitration Act] - [Clause 9.3.7 of the contract dated 16.03.2009] - [Clause 1.1 of Appendix 4 of the contract] - The court discussed the finding of the learned Single Judge on the withholding of amount by the appellant and its entitlement to recover the shortfall of CENVAT and VAT credit from the respondent. The court also examined the prohibition of grant of any price variation under the contract and upheld the interpretation of the contract as given by the Arbitral Tribunal.
Fact of the Case:
The appellant filed an appeal challenging the impugned judgment dismissing its petition under Section 34 of the Arbitration Act. The appellant raised objections regarding the withholding of amount by it and its entitlement to recover the shortfall of CENVAT and VAT credit from the respondent, as well as the prohibition of grant of any price variation under the contract.
Finding of the Court:
The court found no infirmity in the finding of the Arbitral Tribunal that the respondent was not liable to make any payment under the BOCW Act. The court also found no merit in the appellant's contention regarding its entitlement to deduct the sum payable by the respondent on account of CENVAT and VAT on works contract. Additionally, the court found that the interpretation of the contract as given by the Arbitral Tribunal was plausible and upheld the same.
Issues: Withholding of amount by the appellant, entitlement to recover the shortfall of CENVAT and VAT credit from the respondent, prohibition of grant of any price variation under the contract.
Ratio Decidendi: The court upheld the findings of the Arbitral Tribunal and the learned Single Judge, emphasizing that there was no infirmity in the concurrent findings and that the interpretation of the contract as given by the Arbitral Tribunal was to be accepted if plausible.
Final Decision: The appeal was dismissed along with pending applications.
JUDGMENT
Mini Pushkarna, J.: (Oral)
1. The present appeal has been filed under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 ("Arbitration Act") read with Section 13 of the Commercial Courts Act, 2015 challenging the impugned judgment dated 17th August, 2021 passed by the learned Single Judge in O.M.P. (COMM) No. 506/2020. By way of the impugned judgment, the learned Single Judge has dismissed the petition of appellant herein under Section 34 of the Arbitration Act.
2. The first objection raised on behalf of appellant is with respect to finding of the learned Single Judge wherein, the objection of appellant pertaining to withholding of amount by it of sum of Rs. 2,49,74,638/- from the amounts claimed by respondent, was rejected. Mr. Parag Tripathi, learned senior Advocate appearing on behalf of appellant has strenuously argued that the learned Single Judge failed to consider that the aforesaid amount was rightly withheld by appellant since respondent was obliged to comply with the requirements under The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 ("BOCW Act"). It is further contended that while the learned Arbitrator held that respondent herein was not liable to make any payment under the BOCW Act, the learned Single Judge has erred in not giving any finding as to whether the decision of the learned Arbitrator in this regard was correct. It is contended that the learned Single Judge did not examine the said question and upheld the award on that account on some different reasoning by holding that appellant herein had not incurred any liability or made any payment towards alleged dues under the BOCW Act. It is, thus, contended that finding of the learned Single Judge on this account is liable to be set aside.
3. It is next contended on behalf of appellant that the learned Single Judge failed to consider that in terms of Clause 9.3.7 of the contract dated 16.03.2009 between the parties, appellant was to receive the necessary and correct documents to enable it to realise Central Value Added Tax (CENVAT) and Value Added Tax (VAT) credit payment from the appropriate authority, and the shortfall, if any, was to be realised by appellant from respondent. Respondent had supplied documents for realisation of Rs. 8,36,36,168/- only towards CENVAT and VAT credit from the appropriate authority, therefore, appellant was entitled to recover the shortfall of the remaining guaranteed CENVAT and VAT credit from respondent.
4. The third contention raised on behalf of appellant is with respect to finding of the learned Single Judge whereby the submission of appellant that the agreement between the parties prohibited grant of any price variation, was rejected as being without any merit. Learned senior counsel for appellant has relied upon Clause 1.1 of Appendix 4 of the contract in order to contend that no price adjustment ought to have been allowed. However, the learned Single Judge failed to consider the criteria laid down for grant of price variation under the contract.
5. Per contra, learned counsel appearing for respondent has justified the impugned judgment passed by the learned Single Judge.
6. We have heard learned counsel for the parties and have perused the record.
7. The first contention raised on behalf of appellant pertains to the finding that respondent herein was not liable for any payment under the BOCW Act. While dealing with the said aspect, the learned Arbitral Tribunal had held as follows:-
"23. The Respondent has argued that in accordance with the clause 39 of the Special Conditions of Contract (SCC) the claimant is responsible for the implementation of all statutory rules and regulations including the Building and Other Conditions of the Contract Act, 1966 (BOCW Act), if applicable, and the claimant was required to quote the price accordingly. The Respondent has withheld an amount of Rs.2,49,74,638/- on this account. In response the claimant stat
The interpretation of the contract as given by the Arbitral Tribunal is to be accepted if plausible, and the court should be slow in interfering with concurrent findings unless there is apparent perv....
The main legal point established in the judgment is the interpretation and application of the Contract Agreement, CENVAT and VAT provisions, and the terms of price adjustment under the Agreement.
An arbitral award cannot be set aside for lacking elaborate reasoning but must provide intelligible bases; deductions for shortfall in MGCC are impermissible without clear contract provisions.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
The court emphasized that arbitrators must operate within the contractual provisions; awards can be overturned if arbitrators act beyond their jurisdiction, particularly regarding deductions not expl....
Penalty and price variation clauses in a contract can coexist and be applied independently without constituting double punishment for delays.
The Arbitral Tribunal's interpretation of reimbursement based on actual costs incurred due to statutory changes is valid, despite disputes over contract terms, reinforcing the principle of contractua....
Point of law: Scope of examination under Section 34 is limited. The decision of the Arbitral Tribunal regarding consideration and interpretation of the Contract is final and this Court cannot supplan....
The main legal point established in the judgment is the interpretation and application of Section 34 of the arbitration and Conciliation act, 1996 to an international commercial arbitration, and the ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.