SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 4627

IN THE HIGH COURT OF DELHI AT NEW DELHI
Purushaindra Kumar Kaurav, J.
IDBI Bank Ltd. – Appellant
Versus
Power Finance Corporation Ltd. – Respondent
W.P.(C) 11946 of 2018 & CM APPLs. 46305 of 2018, 47720 of 2022
Decided On : 12-05-2023

Advocates appeared:
Ms. Maninder Acharya, Senior Advocate alongwith Mr. Siddarth Barwa, Mr. Praful Jindal & Mr. Akash Mohan Srivastav, Advocates, for the Petitioner.
Mr.Sanjay Jain, ASG with Ms. Pallavi Kumar & Mr.Pranav Tanwar, Advocates, for the Respondent-1.
Mr. Abhinav Mishra, Mr. Nivebita Chauhan, Ms. Jagriti Dosi & Ms. Komal Singh, Advocates, for the Respondent-2.
Mr.Venkatesh, Mr. Siddharth Joshi, Mr. Abhishek Nangia & Ms.Soumya Sharma, Advocates, for the Respondent-3.

The relief under Article 226 of the Constitution of India is discretionary, and the court may decline to entertain a petition if it involves disputed questions of fact, contractual origins of the dispute, and has no public law element.

Headnote:

BGs - Contractual Dispute - Private Law - Fraud - Maintainability of Writ Petition

Fact of the Case:

The petitioner, IDBI Bank Ltd., filed a petition challenging the invocation of bank guarantees (BGs) by respondent no.1. The BGs were issued for retention monies as per Definitive Agreements. The petitioner alleged fraudulent assignment of BGs and sought relief against the fraudulent acts committed by the parties invoking the BGs. The respondents contended that the invocation of the BGs was within the law and that the petitioner had no locus in the contractual matter.

Finding of the Court:

The court found that the dispute had contractual origins, involved disputed questions of fact, and had no public law element. The court declined to entertain the petition, stating that the relief under Article 226 of the Constitution of India is discretionary and that the petitioner had an alternative remedy to pursue.

Issues: Disputed questions of fact, contractual origins of the dispute, and the absence of a public law element.

Ratio Decidendi: The relief under Article 226 of the Constitution of India is discretionary, and the court may decline to entertain a petition if it involves disputed questions of fact, contractual origins of the dispute, and has no public law element.

Final Decision: The court dismissed the writ petition and directed the maintenance of status quo with respect to the BGs for four weeks to enable the petitioner to pursue appropriate remedies.

JUDGMENT

1. The present petition is filed under Article 226 of the Constitution of India by IDBI Bank Ltd., praying inter alia-(1) quashing of the invocation notice dated 15.10.2018 issued by the respondent no.1, wherein certain bank guarantees furnished by the petitioner have been invoked; and (2) a direction to the respondents to return the bank guarantees furnished by the petitioner.

2. The facts material to the present dispute are that in the year 2011, Uttar Pradesh Power Transmission Corporation Limited declared one Isolux Corsan Concesiones S.A. (hereinafter `Isolux') as the successful bidder for a project that, inter alia, was for providing transmission services to various long-term transmission customers in the State of Uttar Pradesh (hereinafter `said project'). Isolux, along with another company, formed respondent no.3 (a joint venture company) for the purposes of executing the said Project. The respondent no.3 in turn engaged the respondent no.2 for executing the said project.

3. On 10.02.2012, in order to define the terms of the work, three agreements were entered into between the respondent nos.2 and 3, viz., Civil Works Agreement, Supply Agreement and Services Agreement (hereinafter `Definitive Agreements'). The Definitive Agreements provided that the respondent no.3 was entitled to withhold as "retentions" part of the payments from the periodic payments after 30 days from the issuance of Taking Over Certificate/Service Completion Certificate/Supply Completion Certificate and the balance after expiry of the Defect Liability Period.

4. On 25.02.2014, all the Definitive Agreements were amended so as to provide that the retention amount would be released by the respondent no.3, if the respondent no.2, furnishes bank guarantee (hereinafter `BGs') for an amount equivalent to the retention amount in favour of the respondent no.3. On the other side of things, the respondent no.3 and the respondent no.1, along with some other parties, had entered into a Common Term Loan Agreement (hereinafter `term loan agreement') on 28.02.2014 for a total amount of Rs.3,713.25 crore.

5. Subsequently, the petitioner from 30.12.2014 to 30.10.2015 issued seven BGs at the instance of the respondent no.2 for a total amount of Rs.58.5 crore, in which the respondent no.3 was the beneficiary who thereafter assigned the BGs in favour of the respondent no.1, with the consent of the petitioner.

6. On 10.10.2018, the respondent no.1 issued a notice to respondent no.3 recalling the loan facility availed by the respondent no.3 under the term loan agreement and demanded that the respondent no.3 forthwith pays the outstanding amount. Thereafter, on 15.10.2018, the respondent no.1 sent an invocation notice to the petitioner invoking the BGs and calling upon the petitioner to pay forthwith the amounts so mentioned in the BGs. The petitioner being aggrieved by the invocation notice, filed the instant petition challenging the same.

7. Ms. Maninder Acharya, the learned senior counsel for the petitioner made the following broad submissions - firstly, that the BGs were in lieu of the retention monies as provided for in the Definitive Agreements, which in turn provided that the retention monies were to be released after the completion of the work. As the work has been completed, the petitioner is therefore discharged from its obligations under the BGs. She specifically places reliance on Clauses 2 and 3 of the BGs.

8. Secondly, after taking this court through Clause 3 of the BGs, the invocation notice and loan recall notice of the respondent no.1, learned senior counsel has contended that the BGs were issued for a specific purpose, that is, for the retention monies as provided for in the Definitive Agreements; and since the basis of the invocation of the BGs is failure of respondent no.3 to honour its obligations under the term loan agreement, the same is bad in law, as being contrary to the terms of the BGs itself.

9. Thirdly, the petitioner's agre

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top