IN THE HIGH COURT OF DELHI AT NEW DELHI
Najmi Waziri, Vikas Mahajan, JJ.
Indeen Bio Power Ltd. – Appellant
Versus
EFS Facilities Services India Pvt. Ltd.
And – Respondent
FAO(OS) (COMM) 14 of 2021, CM APPL. 15614 of 2021 & CM APPL. 42606 of 2021 & FAO(OS) (COMM) 111 of 2021
Decided On : 07-07-2023
Commercial Courts Act - Impugned Order - Arbitration and Conciliation Act, 1996, Section 34 - Project Development Agreement, Synchronization and Coordination Agreement, Supply Contract Agreement, Service Contract Agreement, Works Contract Agreement - The court discussed the significance of the documents and the controversy surrounding them. The impugned order set aside the Arbitral Award and allowed Indeen to re-agitate its claims before the Arbitral Tribunal.
Fact of the Case:
The case involved a dispute between Indeen Bio Power Limited and M/s EFS Facilities Services (India) Pvt. Ltd. regarding a project for setting up a biomass plant. The Arbitral Award in favor of Indeen was set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Finding of the Court:
The court found that the Arbitral Award had erred in considering documents beyond the 'Entire Agreement Clause' and had violated the principles of natural justice and fair play. The court held that the impugned judgment was justified in setting aside the award.
Issues: The issues revolved around the interpretation and admissibility of various agreements and documents, the authority of the Arbitrator to consider certain evidence, and the application of the 'Entire Agreement Clause'.
Ratio Decidendi: The court's decision was based on the violation of the 'Entire Agreement Clause', the principles of natural justice, and the fair play. The court emphasized the importance of adhering to the terms of the contract and trade usages in arbitration proceedings.
Final Decision: The appeal was dismissed as the court found no reason to interfere with the impugned judgment.
JUDGMENT
Najmi Waziri, J. In FAO(OS) (COMM) 14/2021 and FAO(OS) (COMM) 111/2021, Indeen Bio Power Limited (`Indeen') has impugned under section 13(1) of the Commercial Courts Act, 2015 (`CCA') read with section 37 of the Arbitration and Conciliation Act, 1996 (`the Act') the order of the learned Single Judge dated 04.01.2021 passed in O.M.P. (COMM.) No 440 of 2020, allowing the respondent's petition under section 34 of the Act which set aside the Arbitral Award dated 20.05.2020.
2. Mr. Hiroo Advani, the learned Advocate for Indeen submitted that the impugned order has erred inasmuch as i) it has re-appreciated the evidence led before the learned Arbitrator; and ii) the delay in preparation of the Final Business Plan ('FBP') was occasioned entirely because of M/s EFS Facilities Services (India) Pvt. Ltd. ('EFS'), (earlier known as Dalkia India Private Limited ('DIPL')). A Project Development Agreement ('PDA') was entered into between DIPL and Indeen on 02.05.2010 for setting up an 8 MW Master Residue Biomass Plant at Chandli, Tehsil Devli, District Tonk, Rajasthan. A Synchronization and Coordination Agreement ('SCA') was signed between DIPL and Indeen on 08.09.2011. It along with some other documents such as a Supply Contract Agreement, a Service Contract Agreement and a Works Contract Agreement, all undated, became the subject of interpretation.
3. The controversy revolves around the aforenoted five documents. Dispute arose between the parties regarding the project, which got referred to Arbitration. A claim was brought forward by Indeen. By the Arbitral Award dated 20.05.2020, Indeen has been awarded the following reliefs:
"Claim 1-Loss of revenue in power generation-INR 11.37 crores
Claim 2-Costs for Price Escalation-INR 4,33,57,100/- along with pendente lite interest @ 8% per annum and post pendente lite interest @9% per annum."
4. The reason for the learned Arbitrator to award loss of revenue in power generation to the tune of Rs.11.37 crores was based on a Reference Business Plan (`RBP'), which was a part of the Project Development Agreement (`PDA') but not part of SCA. EFS contended that there could be no reason for granting the award because RPB was not included in the `Entire Agreement Clause' of SCA dated 08.09.2011. No finding was rendered by the learned Arbitrator on this ground. The learned Arbitrator had come to the finding that the exception in Clause 11.4 of the SCA will apply. EFS had argued before the learned Single Judge that great prejudice had been caused to it by referring to a document, which was not a part of the `Entire Agreement Clause..
5. On being impugned under S.34 of the Act, the award was quashed and set it aside, with liberty to Indeen to re-agitate its claims before the Arbitral Tribunal and in case it is so re-agitated, the Arbitral Tribunal would reconsider the claims of Indeen, in accordance with law, keeping in view the observations made in the impugned order.
6. EFS says that reference was made by the learned Arbitrator to the RBP, but the said document could not be relied upon because the SCA represented the 'Entire Agreement.' Indeen says that RBP and FBP have not lent any weight to the claim. The claim was not posited on them, there are only individual pieces of evidence, the said documents were merely referred to; there was no cross-examination of the two witnesses of the claimants who deposed apropos quantification of claims; it was never Indeen's case that either the RBP or the FBP was part of the SCA. Therefore, the argument of 'Entire Agreement' has no application to the facts of this case.
7. The impugned judgment has referred to the dicta of High Court of Singapore in CRW Joint Operation v. PT Perushaan Gas Nagara (Persero) TBK, (2011) SGCA 33, which has held as under:
"The significance of the issues that were not dealt with has to be considered in relation to the award as a whole. For example, it is not difficult to envisage a situation in which the issues that were overlooked
Delhi Airport Metro Express Private Limited vs. Delhi Metro Rail Corporation Limited
AI
The court upheld the arbitrator's award, emphasizing limited grounds for judicial interference in arbitration matters.
The Court held that the impugned award with respect to Claim 7 was not well-reasoned as required by the Act under Section 31(3), and the impugned award with respect to the award in Claim 11 is contra....
The court upheld the validity of the arbitral award, emphasizing limited grounds for judicial interference and the necessity of demonstrating clear error or illegality.
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.