SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Del) 757

IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J.
Mohd. Amin (deceased) Through Lrs & Ors. - Appellant
Versus
Mohd. Iqbal (deceased) Through Lrs & Ors. - Respondents
O.M.P. (COMM) 250 of 2021 & I.A. 10669 of 2021
Decided On : 05-04-2024

Advocates appeared:
Ms. Sumita Hazarika, Ms. Nazia Parveen, Advocates, for the Petitioner in OMP (COMM.) 250/2021 & I.A. 10669/2021 & for the Judgement Debtor in OMP (ENF.) (COMM.) 129/2021.
Mr. Sanjay Bansal, Mr. Pushkar Sood, Ms. Swati Bansal, Ms. Ayushi Bansal, Ms. Vaishali Gupta, Mr. Priyadarshi Kumar, Advocates, for the Respondent in OMP (COMM.) 250/2021 & I.A. 10669/2021 for the Decree Holder in OMP (ENF.) (COMM.) 129/2021.

The court ruled that arbitration findings are minimally subject to judicial review, confirming compensation awarded for unlawful possession and possession restoration based on the terms of the compromise agreement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitration award - The court reviews the legality of the award concerning the reversion of land and compensation awarded for illegal occupation - Compromise Agreement dated 25.02.1991 specifies conditions for the reversion of property and allowed claims for possession and damages. (Paras 1, 70)

(B) Public Policy - The court notes the principles under which an arbitral award can be set aside, emphasizing minimal intervention unless the award is perverse or violates public policy. (Paras 28-39)

Facts of the case:
The dispute involves claims regarding land possession and compensation following a Compromise Agreement between parties that alleged illegal possession and construction on the property. The arbitration arose after a prolonged legal battle over the enforcement of the Agreement. (Paras 3-10)

Findings of Court:
The arbitrator ordered the return of possession and compensation of Rs.15,00,000/- to the claimants for constructions on the land. The counter-claim by the petitioners was rejected. (Paras 64-76)

Issues: Whether the claims were barred by limitation; the applicability of Section 14 of the Limitation Act; and whether the arbitrator exceeded jurisdiction regarding the claims for damages were key issues addressed.

Ratio Decidendi: The arbitrator's findings were upheld as reasonable, supported by evidence and law, especially concerning the handling of limitation and damages. The award did not constitute a violation of the Agreement. (Paras 58-72)

Result: Petition dismissed. The award confirmed, allowing the claimants possession of the land and damages to be paid within a stipulated time frame. (Paras 78-81)

Table of Content
1. introduction of case and its basic facts regarding possession. (Para 1)
2. background of the dispute regarding property possession. (Para 2 , 3 , 4 , 5 , 6 , 7 , 10)
3. claims made by respondents and subsequent arbitration process. (Para 11 , 12)
4. arguments presented by petitioners challenging the arbitrator's award. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 25 , 26)
5. respondents' defense on limitation and arbitration validity. (Para 27 , 28 , 29 , 30 , 31 , 32)
6. judicial approach to reviewing arbitration awards. (Para 33 , 34 , 35 , 36)
7. discussion on principles of natural justice in arbitration. (Para 39 , 40 , 41 , 42 , 43 , 44)
8. case law analysis on applicability of section 14 of limitation act. (Para 54 , 55 , 56 , 57 , 58)
9. award's basis on limitation and damages under contract. (Para 60)
10. assessment of damages awarded by arbitrator. (Para 64 , 65 , 66 , 67 , 68 , 69)
11. counter-claim rejection reasoning. (Para 74 , 75 , 76)

JUDGMENT

Jasmeet Singh, J.

O.M.P. (COMM) 250/2021

1. This is a petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter, "the Act") challenging the Award dated 18.05.2021 (hereinafter, "Impugned Award") passed in Arbitration Case No. (AR) 9/2019, whereby the learned Sole Arbitrator has allowed the claims of the respondents against the petitioners and thereby has primarily directed the petitioners to redeliver the possession of land measuring 435 sq. yds, situated at 268, Naseem Bagh, Jamia Nagar, Okhla, New Delhi (hereinafter, "disputed plot/land").

Brief Facts

2. The brief facts are as under:

3. The predecessor-in-interest of the respondents (claimants in the arbitration proceedings) i.e. Late Mohd. Iqbal was allegedly in illegal and unauthorized possession of the disputed plot since 1974 and as on 25.02.1991.

4. The predecessor-in-interest of the petitioners (counter-claimants and respondents in the arbitration proceedings) i.e. Late Mohd. Amin instituted Suit No. 331/1989 against Late Mohd. Iqbal for permanent injunction, to restrain the defendant (Mohd. Iqbal) from interfering with his (Mohd. Amin) possession and right of peaceful enjoyment of the disputed land. During the pendency of the suit, the parties entered into a Compromise Agreement dated 25.02.1991 (hereinafter, "Agreement") and filed a joint application under Order XXIII Rule 3 of the Code of Civil Procedure, 1908 (hereinafter, "CPC") along with their affidavits, and the suit was dismissed as withdrawn with the direction that the parties shall remain bound by the terms of the Agreement.

5. The Agreement recorded that Mohd. Amin was the exclusive owner and in possession of the property known as Nasim Bagh bearing Khasra No. 138 (5 Bigha, 3 Biswa), 139 (11 Biswa), 140 (2 Bigha, 6 Biswa) and 141 (2 Bigha, 1 Biswa) comprising of an area measuring about 8430 sq. metres. Mohd. Amin had entered into an agreement with developer M/s Unitech Limited for developing a portion of the said property measuring 6000 sq. mts. into a Multi Storeyed Group Housing Complex (hereinafter, "Project"). The Agreement also recorded that Mohd. Iqbal was "allegedly" in illegal and unauthorised possession of the disputed land and had "allegedly" made illegal constructions thereon. The Agreement was entered into to avoid further litigation, and by way of the same, the disputed land was handed over to Mohd. Amin for the Project on the condition that Mohd. Amin would deliver 6% of the total built up area in the Project building to Mohd. Iqbal.

6. As per Clause 10 of the Agreement, both the parties agreed that if for any reason the proposed Project was abandoned, the disputed land would be returned to Mohd. Iqbal who would then be free to use the said land as desired by him and the Agreement would become null and void. Clause 10 reads as under:

    "10. That without prejudice to the aforesaid, it is hereby specifically agreed by and between the parties that if for any reasons, the aforesaid Multistoreyed Group Housing Project is aban

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top