IN THE HIGH COURT OF DELHI AT NEW DELHI
REKHA PALLI, SAURABH BANERJEE, JJ.
National Health Authority – Appellant
Versus
M S Intermarc - Respondent
FAO (COMM) 137/2024, CM APPL. 40513/2024-Stay, CM 65899/2024-By appellant seeking ad-interim ex-parte stay of order dt. 07.10.2024.
Decided on : 12-11-2024
(A) Arbitration and Conciliation Act, 1996 - Section 34(3) - Limitation for setting aside arbitral award - Application filed beyond the statutory period of limitation - The appellant's application was rejected as it was filed on the 134th day from the date of the award, exceeding the permissible limit of 120 days including condonable delay. (Paras 11, 16, 18)
(B) Limitation Act, 1963 - Section 14 - Exclusion of time - The court held that the period during which the application remained pending before the High Court could be excluded, but the overall application was still barred by limitation. (Paras 12, 14)
Facts of the case:
The appellant, a government body, challenged the arbitral award on grounds of limitation after a delay in filing the application under Section 34 of the Act.
Findings of Court:
The application was rightly dismissed as it was filed beyond the mandatory limitation period.
Issues: Whether the appellant was entitled to the benefit of exclusion of time under Section 14 of the Limitation Act.
Ratio Decidendi: The court ruled that the statutory limitation period is inflexible and cannot be extended, even for administrative delays.
Result: Appeal dismissed.
JUDGMENT :
REKHA PALLI, J.
1. The present appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “Act”) seeks to assail order dated 07.05.2024 passed by the learned District Judge, Commercial Court, Patiala House Courts, New Delhi in OMP (Comm.) 121/2023.
2. Vide the impugned order, the learned Trial Court has rejected the application preferred by the appellant under Section 34 (3) of the Act for setting aside of the arbitral award dated 21.02.2023 on the sole ground of the same having been filed beyond the period of limitation as provided under the Act.
3. The brief factual matrix as emerging from the record shows that the appellant is a Government body under the aegis of the Ministry of Health and Welfare, Government of India and the respondent is a contractor who was awarded the contract for renovation of the office of the appellant in the Jeevan Bharti Building, Connaught Place, New Delhi.
4. On 19.08.2019, the appellant issued a tender inviting bids for renovation of its office at the third floor of the said Jeevan Bharti Building. The respondent, being the lowest bidder was awarded the contract for “Refurbishment and Renovation of approx. 10235 Sq. Fts.” vide agreement dated 28.11.2019 (hereinafter referred to as “Contract”). The value of the entire contract was initially fixed at Rs.3,65,00,000/- but was later reduced to Rs. 3,14,95,840/- and the work was to be completed within a period of 80 days, i.e. by 16.02.2020.
5. As per the appellant, since time was an essence of the contract, it was agreed that in case the work was not completed by the respondent within the agreed 80 days, the appellant would be entitled to liquidated damages of Rs.5,00,000/- per day, a term, which was also encapsulated in clause 6 of the Contract. As the work, which commenced on 28.11.2019, was completed on 25.02.2020 there was a delay of eight days and consequently the appellant was entitled to deduct an amount of Rs. 40,00,000/-, by way of liquidated damages. However, as the building was closed from 01:00 p.m. on 25.01.2020 and on 26.01.2020 i.e. for 1½ days, on account of Republic day, liquidated damages of Rs. 32,50,000/- were levied on the respondent on account of the 6½ days delay as per clause 6.2.3 of the Contract.
6. This resulted in invocation of arbitration by the respondent, and upon conclusion of the arbitration proceedings the learned Arbitrator vide arbitral award dated 21.02.2023 (hereinafter referred to as “Award”) awarded a sum of Rs. 35,53,500/- in favour of the respondent.
7. Being aggrieved by the Award, the appellant filed an application under Section 34 of the Act before this Court on 03.05.2023 only to be subsequently withdrawn on 03.07.2023 for want of pecuniary jurisdiction albeit with liberty to move an appropriate application before the appropriate Court. It is then that the appellant after waiting for over two months chose to file a fresh application under Section 34 of the Act before the learned Trial Court i.e., the District Judge, Commercial Court, Patiala House Courts, New Delhi on 05.09.2023.
8. It is this application, filed by the appellant, which has been rejected under the impugned order by the learned Trial Court by holding as under:
The statutory limitation period under Section 34(3) of the Arbitration and Conciliation Act is inflexible, and applications filed beyond this period cannot be entertained.
The court emphasized the peremptory language of section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for sufficient cause to condone any delay in filing the application.
The court affirmed that claims in arbitration must be asserted within the limitation period, and undue delays in invoking arbitration can render claims invalid.
The period of limitation under the Arbitration and Conciliation Act should exclude non-working days, allowing for sufficient cause extension beyond three months.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.