IN THE HIGH COURT OF DELHI
Sanjeev Narula, J.
Technofab Engineering Ltd. - Appellant
Versus
Tesla Transformers Ltd. - Respondent
O.M.P. (COMM.) 568 of 2020 & I.A. 11325 of 2020
Decided On : 04-08-2021
| Table of Content |
|---|
| 1. dispute origins from contract execution failures. (Para 2) |
| 2. parties' legal contentions before the court. (Para 5 , 6) |
| 3. court's analysis of contract termination and cpbg invocation. (Para 7 , 8 , 9 , 10) |
| 4. findings and conclusions regarding losses and cpbg legality. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21) |
| 5. final decision to dismiss the petition. (Para 22) |
JUDGMENT
[VIA VIDEO CONFERENCING]
Sanjeev Narula, J. (Oral):--The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (in short `the Act') assails the award dated 22nd May, 2020 whereby the learned Sole Arbitrator, has inter alia rejected all the counter-claims of the Petitioner- Technofab Engineering Limited (in short `TEL') and awarded an amount of Rs. 1,87,17,280/-, along with pre- reference, pendente-lite and future interest @ 9% towards the refund of unlawfully encashed Contract Performance Bank Guarantees (in short `CPBGs'), in favour of the Respondent- Tesla Transformers Limited (in short `TTL').
The Dispute
2. The brief facts, which led the parties to arbitration are as follows:
2.1. TEL entered into five separate contracts with the Power Grid Corporation of India Limited (`PGCIL') for installation, commissioning, assembling, running, operating and maintaining electricity substations in the State of Tripura. For this purpose, TEL needed transformers for running the substations. In order to meet a part of their requirement, negotiations were held and eventually three purchase orders were placed on TTL for the supply of 5 MVA and 7.5 MVA power transformers and 100 KVA station transformers in the month of June, 2017.
2.2. As per the agreed delivery schedule, TTL was to deliver the transformers on or before 30th September, 2018. It was provided in the terms of supply that in the event of any unforeseen circumstances, the time period for supply could be extended upto 3rd/4th quarter of the financial year 2018-19.
2.3. In July, 2017, TEL granted manufacturing clearance to TTL. TTL did not make much progress till November, 2017 and as on 26th March, 2018, only 11 5 MVA transformers, out of 43, were supplied to TEL. In these circumstances, TEL terminated the contract vide letter dated 1st October, 2018 and also expressed its intent to invoke the CPBGs. TEL claimed that it was constrained to engage another supplier for supply of the balance undelivered quantity and invoked three CPBGs to mitigate the losses.
2.4. Accordingly, TTL vide notice dated 26th October, 2018 invoked arbitration and sought adjudication of the disputes. Mr. Kuldeep Singh (Retd.), former Additional District Judge was appointed as the Sole Arbitrator.
2.5. Before the Arbitrator, the parties filed their respective claims. TTL prayed for the following reliefs:
"(i). Pass an award in favour of Claimant by declaring the invocation and encashment of Bank Guarantee(s) bearing no.1920188G0000020; 1920188G0000026; 1920188G0000027 by Respondent as illegal and null and void.
(ii). Pass and award in favour of Claimant by declaring the termination of Purchase Orders by Respondent vide letter dated 01.10.2018 as illegal and null and void.
(iii). Pass and award in favour of Claimant and against the Respondent for a sum of Rs. 187,17,280/- towards illegal encashment of bank Guarantee(s).
(iv). Pass and award in favour Claimant and against the Respondent for a sum of Rs. 9,07,787/- (being interest @ 18% per annum from the 01.10.2018 i.e., date of encashment of Bank Guarantee(s) till the date of filing of claim, on Rs. 187,17,280/-).
(v). Pass an award in favour of Claimant and against the Respondent for a sum of Rs. 58,40,000/- towards the cost of two transformers of 5MVA/33/11KV, which were ready and offered by Claimant were not accepted by Respondent.
(vi). Pass and award in favour of the Claimant and against the Respondent for a sum of Rs. 3,24,120/- (being interest @ 18% per annum from the 15.09.2018 i.e. date of inspection call for two transfo
AI
Arbitration awards must be clear and justified; arbitrary awards lacking detailed reasoning and analysis fail to meet legal standards.
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
Wrongful encashment of a bank guarantee can be claimed as restitution rather than strictly under damages, highlighting the sufficiency of entitlement rather than extensive evidence. This determinatio....
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliat....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.