IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
KMP Expressways Ltd. - Appellant
Versus
IDBI Bank Limited - Respondent
O.M.P. (COMM) No. 35 of 2021 & IA No. 1165 of 2021
Decided On : 29-03-2022
| Table of Content |
|---|
| 1. challenge to arbitral award details (Para 1 , 2 , 3 , 4 , 5) |
| 2. context of concession and financial obligations (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 3. communication and agreements regarding concession termination (Para 16 , 17 , 18 , 19 , 20) |
| 4. initiation of proceedings and judicial notice (Para 21 , 22 , 23 , 24) |
| 5. execution of contractual obligations and lender concerns (Para 25 , 26 , 27 , 28) |
| 6. claims and counterclaims in arbitration (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36) |
| 7. details of the arbitral award and claims (Para 37 , 38) |
| 8. arguments presented by kmpel (Para 39 , 40) |
| 9. court's analysis of the arbitral decision (Para 41 , 42 , 43 , 44 , 45 , 46) |
| 10. clarifications regarding rights of kmpel (Para 47 , 48 , 49 , 50) |
| 11. final order of dismissal of the petition (Para 51) |
JUDGMENT :
Vibhu Bakhru, J
Introduction
1. KMP Expressways Limited (hereafter `KMPEL') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter the `A&C Act') impugning an arbitral award dated 24.03.2020 (hereafter the `impugned award') delivered by an Arbitral Tribunal comprising of two former Judges of the Supreme Court of India with a Former Chief Justice of India acting as a Presiding Arbitrator (hereafter the `Arbitral Tribunal').
2. The impugned award was rendered in the context of claims made by respondent no.1 (hereafter `IDBI') on its behalf as well as on behalf of the `Senior Lenders' as the `Lenders' Representative', against respondent no. 2 (hereafter `HSIIDC'). In this order, a reference to IDBI unless the context indicates otherwise, be construed as referring to the `Senior Lenders' or to IDBI acting as the `Lender's Representative'.
3. IDBI claimed that HSIIDC had breached its obligations under the Substitution Agreement dated 08.01.2007 (hereafter the `Substitution Agreement') as HSIIDC had appointed new Concessionaires in place of KMPEL to complete the development of the KMP Expressway, without safeguarding its dues and those of the `Senior Lenders'. The Arbitral Tribunal found in favour of IDBI and against HSIIDC and, awarded damages in favour of IDBI for a sum of Rs.1737.11 crores along with future interest at the rate of 9% per annum from the date of the impugned award. The Arbitral Tribunal further found that HSIIDC would be entitled to reimbursement of the amount that IDBI would recover from KMPEL pursuant to the proceedings instituted before the Debts Recovery Tribunal. Further, IDBI would be liable to pay simple interest at the rate of 9% per annum on the recovered amount if the same is not paid to HSIIDC within one month from the date of recovery of such amount.
4. The Arbitral Tribunal had quantified the aforesaid damages to be equivalent to the amount due to IDBI and the `Senior Lenders' from KMPEL against the loan disbursed by IDBI, for the development of the Kundli-Manesar-Palwal Expressway (hereafter the `KMP Expressway').
5. KMPEL has challenged the operative part of the impugned award to extent that (i) it directs that the KMPEL shall bear its own costs; and (ii) it contemplates recovery of any amount by IDBI from KMPEL in proceedings instituted before the Debts Recovery Tribunal and directs reimbursement of the said amount to HSIIDC. According to KMPEL, the impugned award to the aforesaid extent is vitiated by patent illegality.
Factual Context
6. The Government of Haryana had appointed HSIIDC as the Nodal Agency for Development of 135.650 km long KMP Expressway in the State of Haryana and its operation and maintenance, on a Build, Operate and Transfer basis (BoT basis).
7. HSIIDC had invited proposals for the development and operation of KMP Expressway on a BoT basis (hereafter the `Project'). Pursuant to the said invitation, M/s Madhucon Projects Limited, M/s Apollo Enterprises Limited and M/s D.S. Constructions Limited had submitted their bid as a Consortium with M/s Madhucon Projects Limited as the Consortium Leader. T
The measure of damages adopted by the arbitral Tribunal and its influence on the decision.
The court held that the arbitral Tribunal's decision that HSIIDC had breached the Substitution agreement and that the Senior Lenders were entitled to damages was based on a plausible construction of ....
NHAI is contractually obliged to pay 90% of the Debt Due to lenders irrespective of defaults by the concessionaire, with no deductions permitted.
The court affirmed that arbitral awards are upheld unless blatant illegality is shown, emphasizing the tribunal's final authority under Section 34 of the Arbitration and Conciliation Act.
(1) Construction of contract is within jurisdiction of Tribunal and merely because another view is possible, Court cannot interfere with such construction and substitute its own view.(2) If an arbitr....
An expulsion under a contract must have legitimate causes, and unjustified actions by one party render such expulsion illegal, reaffirming constraints under arbitration frameworks.
The court emphasized that arbitration awards must adhere strictly to contract terms regarding payment and interest, rejecting arbitrary reductions of entitlement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.