SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Alstom Systems India Pvt. Ltd. - Appellant
Versus
Zillion Infraprojects Pvt. Ltd. - Respondent
O.M.P. (COMM) 351 of 2021, I.A. 15661 of 2021 (Section 36 for Stay), I.A. 15662 of 2021 (Section 151 CPC for exemption), I.A. 15663 of 2021 (Section 151 CPC for exemption), I.A. 15664 of 2021 (Section 151 CPC for exemption), I.A. 15665 of 2021 (Section 15
Decided On : 31-01-2022




Arbitration claims must be initiated only after requisite mediation processes have failed; the cause of action arises post mediation conclusion, impacting limitation periods.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Limitation Act, 1963 - Claim barred by time - Petition filed to challenge arbitral award upholding claims not barred by limitation as mediation was requisite before arbitration - The Tribunal found that the dispute arose only after the mediation's conclusion on 7th September, 2020, after which arbitration was invoked on 24th March, 2021 - Claims held not time-barred (Paras 7, 14, 21, 24, 34).

(B) Limitation Period - The cause of action for initiating arbitration is determined based on adherence to mediation processes as stipulated in contract terms, making prior adherence to mediation mandatory before invoking arbitration (Paras 28, 31).

(C) Examination of claims - The Tribunal’s decision to distinguish between the commencement of mediation and arbitration upheld, emphasizing that the disputes need resolution via mediation before arbitration (Paras 28, 32).

Facts of the case:
The petitioner sought to dismiss claims from arbitration as time-barred, postulating the time for limitation initiated on termination of the contract on 21st September, 2016, while the respondent argued for mediation initiated before arbitration which concluded on 7th September, 2020 (Paras 3, 5, 6).

Findings of Court:
The Tribunal correctly identified the need for mediation prior to arbitration per contract clause and evaluated claims based on this fundamental procedural requirement (Paras 26, 29).

Issues: Whether the arbitration invocation was time-barred due to delays and the binding nature of mediation per the contractual agreement (Paras 3, 10).

Ratio Decidendi: The Tribunal ruled that the arbitration process could not commence until mediation efforts culminated in failure, determining the cause of action for arbitration arose only after this point (Paras 28, 39).

Result: Petition dismissed; claims upheld as not time-barred.

Table of Content
1. establishment of limitation period for arbitration claims. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. court's analysis of limitation based on mediation failure. (Para 7)
3. petitioner's contention regarding arbitration timeline. (Para 8 , 9 , 10 , 11 , 12)
4. interpretation of legal precedent impacting limitation. (Para 14 , 16 , 17 , 18 , 19 , 20)
5. citing jurisdiction limits concerning arbitration disputes. (Para 21 , 22 , 23 , 24 , 25 , 26)
6. implications of delay in initiating arbitration. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33)
7. deciding factors for not interfering in arbitration award. (Para 34 , 35 , 36 , 37 , 38)
8. final decision to dismiss petition without intervention. (Para 39 , 40 , 41)

JUDGMENT

(By video conference on account of COVID-19)

OMP (COMM) 351/2021

1. The petitioner assails, by means of this petition, preferred under Section 34 of the Arbitration and Conciliation Act, 1996 ("1996 Act"), order dated 29th October 2021, passed by a learned three member Arbitral Tribunal, presently in seisin of the dispute between the petitioner and the respondent.

The impugned order

2. The impugned order came to be passed on an application by the petitioner, as the respondent before the learned Arbitral Tribunal, under Order VII Rule 11 of the Code of Civil Procedure, 1908 (CPC), seeking dismissal of the respondent's case as being barred by time. To support this request, the petitioner furnished, to the learned Arbitral Tribunal the following tabular statement of dates, reproduced verbatim from para 2 of the impugned order:

24.09.2015Claimant and Respondent entered into a sub-contract.
16.09.2016The Respondent terminated the sub-contract.
21.09.2016Termination letter was delivered to the Claimant.
21.09.2016The Claimant raised a dispute stating that termination is illegal.
07.10.2016Invocation of Bank Guarantees by the Respondent.
07.02.2017Bank Guarantees encashed and money transferred to Respondent's Account.
24.03.2021Date of commencement of arbitration under Article 4(2) of the ICC Rules 2017.

3. Premised on the afore-extracted table, the petitioner contended that the cause of action, for the respondent to initiate the arbitral process, arose on 21st September, 2016. Reckoned from the said date, and applying Articles 551 and 582 of the Limitation Act, 1963, which envisaged a limitation period of three years from the date of arising of the cause of action, the petitioner contended that the claims were barred by time.

4. Responding to the above assertion of the petitioner, the respondent, as the claimant before the learned Arbitral Tribunal, relied on Clause 29 of the Subcontract Agreement between the petitioner and the respondent, which contemplated resolution of disputes by arbitration, and read thus:

    "29 APPLICABLE LAW - SETTLEMENT OF DISPUTES

    29.1 This Subcontract Agreement shall be governed by the laws of [India] with courts at [Delhi] having exclusive jurisdiction to adjudicate on all dispute/matters arising out of this Sub-Contract.

    29.2 Reference to Mediation

    29.2.1 In the event of any dispute or difference between the Contractor and the Subcontractor, whether arising during the execution or after the completion or abandonment of the Subcontract Works or after the determination of the employment of the Subcontractor under this Subcontract (whether by breach or in any other manner}, m regard to any matter or thing of whatsoever nature arising out of this Subcontract or in connection therewith, then either Party shall give to the other notice in writing of such dispute or difference and such dispute or difference shall be and is hereby referred to mediation. A Party who receives a notice for mediation from the other Party shall consent and participate in the mediation process and shall make all reasonable efforts to resolve the same through mediation in accordance with the mediation rules of the International Chamber of Commerce- Alternate Dispute Resolution- ICC ADR

    29.2.2 Notwithstanding anything in this

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top