SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 2112

IN THE HIGH COURT OF DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Welspun Enterprises Ltd. - Appellant
Versus
NCC Ltd. - Respondent
FAO(OS)(COMM) No. 9 of 2019 & CM No. 2239 of 2019
Decided On : 10-10-2022

Headnote:

The court held that the claims of Welspun, as included in the Final Bill dated 30.10.2010, were not barred by limitation. The court found that the arbitration had not commenced within a period of three years from the due date for payment of the Final Bill, as claimed. However, the court also found that Welspun had failed to explain the delay in invoking the arbitration after the dispute resolution process had failed on 21.12.2012.

Fact of the Case:

An Engineering, Procurement and Construction (EPC) contract in respect of "Balance Offsite & Utilities and Interconnection with Panipat Refinery/Marketing Terminal (EPCC-9 Package)" in the Panipat Naphtha Cracker Project was executed between Indian Oil Corporation Limited (hereafter `IOCL') and Nafto Gaz India Private Limited (hereafter `Nafto Gaz'). The scope of work under the said EPCC-9 Package included "Design, Engineering, Procurement, Supply Transport, Fabrication, Construction, Painting, Insulation, Testing and Commissioning of Raw Water Storage and Treatment Plant, Fire water Storage & Pump House, Storm Water Storage & Pump House, Flare System, interconnecting Process Streams between Refinery and Panipath Naphtha Cracker Project (PNCP) including hook ups with the existing system, Naphtha unloading and transfer from Panipat Marketing Terminal to PNCP and construction of inter-connecting flyover between Panipat Refinery and PNCP".

Finding of the Court:

The court found that the claims of Welspun, as included in the Final Bill dated 30.10.2010, were not barred by limitation. The court found that the arbitration had not commenced within a period of three years from the due date for payment of the Final Bill, as claimed. However, the court also found that Welspun had failed to explain the delay in invoking the arbitration after the dispute resolution process had failed on 21.12.2012.

Issues: Whether the claims of Welspun, as included in the Final Bill dated 30.10.2010, were barred by limitation.

Ratio Decidendi: The court held that the claims of Welspun, as included in the Final Bill dated 30.10.2010, were not barred by limitation. The court found that the arbitration had not commenced within a period of three years from the due date for payment of the Final Bill, as claimed. However, the court also found that Welspun had failed to explain the delay in invoking the arbitration after the dispute resolution process had failed on 21.12.2012.

Final Decision: The court allowed the appeal and set aside the impugned award and the impugned order. The court also clarified that the claimant is entitled to take steps for reference of the disputes to arbitration afresh.

JUDGMENT

Vibhu Bakhru, J.

INTRODUCTION

1. The appellant (hereafter `Welspun') has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an order dated 20.11.2018 (hereafter `the impugned order') passed by the learned Single Judge, whereby the appellant's application under Section 34 of the A&C Act, seeking to set aside an arbitral award dated 23.07.2018 (hereafter `the impugned award'), was rejected.

2. The impugned award was rendered by majority of 2:1 by an Arbitral Tribunal comprising of three members. Whilst the majority was of the view that the claims of Welspun, as included in the Final Bill, were barred by limitation, one of the members of the Arbitral Tribunal (minority) expressed a contrary view.

3. The learned Single Judge concurred with the view that the claims, as contained in the Final Bill, were barred by limitation for the reason that the arbitration had not commenced within a period of three years from the due date for payment of the Final Bill, as claimed.

4. The Arbitration Clause contemplated a pre-arbitration dispute resolution mechanism by referring the disputes to the Chief Executives of the parties. The dispute resolution process failed on 21.12.2012 and the notice for arbitration was issued on 27.01.2014. According to Welspun, the right to seek reference to arbitration would arise on failure of the amicable dispute resolution procedure and thus, invocation of the arbitration was within the period of limitation. However, the learned Single Judge rejected the said contention, inter alia, on the ground that Welspun had failed to explain the delay in invoking the arbitration after the dispute resolution process had failed on 21.12.2012.

5. The principal controversy to be addressed in the present appeal is whether the claims of Welspun, as included in the Final Bill dated 30.10.2010, were barred by limitation.

FACTUAL CONTEXT

6. An Engineering, Procurement and Construction (EPC) contract in respect of "Balance Offsite & Utilities and Interconnection with Panipat Refinery/Marketing Terminal (EPCC-9 Package)" in the Panipat Naphtha Cracker Project was executed between Indian Oil Corporation Limited (hereafter `IOCL') and Nafto Gaz India Private Limited (hereafter `Nafto Gaz'). The scope of work under the said EPCC-9 Package included "Design, Engineering, Procurement, Supply Transport, Fabrication, Construction, Painting, Insulation, Testing and Commissioning of Raw Water Storage and Treatment Plant, Fire water Storage & Pump House, Storm Water Storage & Pump House, Flare System, interconnecting Process Streams between Refinery and Panipath Naphtha Cracker Project (PNCP) including hook ups with the existing system, Naphtha unloading and transfer from Panipat Marketing Terminal to PNCP and construction of inter-connecting flyover between Panipat Refinery and PNCP".

7. Subsequently, Nafto Gaz awarded the said EPC contract in favour of the respondent (hereafter `NCC'). Thereafter, NCC sub-contracted the work in respect of the inter-connecting flyover between the existing Panipat Refinery and Panipat Naphtha Cracker Project (PNCP) to Welspun.

8. By a Letter of Intent dated 24.10.2006 (hereafter `the LoI'), NCC subcontracted the works in respect of the interconnecting flyover between Panipat Refinery and PNCP to MSK Projects (India) Ltd. (hereafter `MSK').

9. On 19.12.2006, a Memorandum of Agreement (hereafter `the MoA') was executed between MSK and NCC. In terms of the said MoA, NCC had subcontracted the work concerning a flyover project (hereafter `the Project') on an item rate basis for a total value of Rs.53.25 crores, in favour of MSK.

10. Subsequently, MSK was acquired by Welspun.

11. On 12.06.2010, the Mechanical Completion Certificate was issued to Welspun by IOCL.

12. Thereafter, on 03.08.2010, a meeting was held between the parties, wherein NCC had agreed to pay various amounts due to Welspun.

13. Thereafter, on 30.10.201











Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top