IN THE HIGH COURT OF DELHI
Sanjeev Narula, J.
Concept Communications Ltd. - Appellant
Versus
Bharat Sanchar Nigam Ltd. - Respondent
O.M.P. (COMM) 68 of 2022 & I.A. 1073 of 2022
Decided On : 20-01-2022
| Table of Content |
|---|
| 1. background of the arbitration case. (Para 2 , 3) |
| 2. arguments raised by ccl challenging the arbitration award. (Para 6) |
| 3. court's analysis and reasoning on the arbitration findings. (Para 7 , 8 , 11 , 12 , 14 , 15) |
| 4. ratios concerning the nature of liquidated damages and performance obligations. (Para 9 , 10 , 13) |
| 5. conclusion and dismissal of the petition. (Para 16) |
JUDGMENT
[VIA VIDEO CONFERENCING]
Sanjeev Narula, J. (Oral)--The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter, "the Act"] impugns the Arbitral Award dated 22nd September, 2021 passed by a Sole Arbitrator, wherein claims raised by the Petitioner (Claimant at Arbitration) were dismissed.
THE FACTS
2. The Petitioner-M/s. Concept Communications Ltd. [hereinafter, "CCL"] -- a company engaged in the business of providing Out of Home [hereinafter, "OOH"] advertising services - was the successful bidder in a tender floated by the Respondent-Bharat Sanchar Nigam Ltd. [hereinafter, "BSNL"]. Parties executed an Agreement dated 17th September, 2009 thereto, whereby CCL was engaged for providing OOH advertising services in five territorial Circles in India, namely - Maharashtra, Tamil Nadu, Andhra Pradesh, Chennai, Andaman and Nicobar and Andhra Pradesh [hereinafter, the "Project"]. The said territorial circles comprised of various Secondary Switching Areas [hereinafter, "SSAs"]. Pursuant thereto, BSNL issued a Release Order on 18th September, 2009, and awarded work for brand visibility of BSNL through PCO Glow Sign Boards namely -(i) `PCO Glow Sign Board (Double sided)-Lit Boards' [hereinafter, "Lit Boards"] and (ii) `PCO Signage (Flange Double Sided)-Non-Lit Boards' [hereinafter, "Non-Lit Boards"].
3. According to CCL, the work assigned to it was completed in accordance with the Release Order, yet, BSNL acted in blatant violation of the terms of the Agreement as well as the Release Order, and under false and specious pleas, refused to release payments to CCL. In these circumstances, CCL triggered the arbitration clause, and consequently, the Arbitral Tribunal was constituted to adjudicate the disputes.
AT ARBITRATION
4. CCL raised a claim of Rs.29,64,05,971.12/- which had two components -- (i) payment unlawfully withheld by BSNL; and (ii) deductions made on account of the liquidated damages and penalty imposed by BSNL. On the other, BSNL refuted the afore-noted claims and justified the imposition of damages. The following six issues were framed:
"1. Whether the claim has not been filed by authorized and competent person? (QPR)
2. Whether the Claimant had not executed the work and raised the bills in accordance with the conditions of Agreement dated 17.09.2009 and release order dated 18.09.2009? (OPR)
3. Whether the Claimant is entitled to the Claim? (OPC)
4. Whether the Claimant is entitled to Damages, if any? (OPC)
5. Whether the Claimant is entitled to interest, if any and at what rate? (OPC)
6. Relief. "
5. On consideration of documentary and oral evidence produced by the parties, Arbitral Tribunal passed the impugned Award dismissing CCL's claim in entirety. However, it was held entitled to the return of performance bank guarantees along with interest. The challenge in the present petition is confined to rejection of monetary claims.
CONTENTIONS OF CCL [THE PETITIONER]
6. Mr. Jayant Mehta, Senior Counsel for CCL, impugns the Award on the following grounds:
6.1. CCL was contracted to supply and install lit and non-lit sign boards of a certain quality. Despite having successfully completed the Project and there being no disputes with regard to quality, CCL was not paid for the work done. The Award essentially rewrites the contractual terms by imposing the obligation to maintain the sign boards upon CCL - which was never envisaged originally between the parties. The Award is in violation of the terms and conditions agreed upon by the parties and suffers from patent illegality, inasmuch as the
AI
The court affirmed that deductions for non-performance are valid when based on contract conditions and substantiated by timely verification reports, emphasizing the importance of evidentiary reasonin....
The main legal point established in the judgment is the limited scope of judicial interference with arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996, and the importance ....
The Court emphasized the limited scope of jurisdiction under Section 34 of the Act and the need for evidence to support claims for loss of profit.
The court emphasized the limited scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996, and highlighted the importance of evidence and reasoning in arbitral awards.
The scope of judicial review under Section 34 of the Arbitration Act is limited to reasons of law and pertains to the arbitral tribunal's adherence to the contract terms and evidence presented.
An arbitration award directing refund of encashed Performance Bank Guarantee upheld; claims for set-off rejected due to insufficient notice and limitations.
The petitioner is liable for damages due to breach of contract, regardless of inter-party settlements, requiring compensation for both lease rentals and expected profits.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
A party must prove actual losses to validly invoke a Contract Performance Bank Guarantee and cannot use it as a penalty for non-performance.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.