IN THE HIGH COURT OF JHARKHAND AT RANCHI
SHREE CHANDRASHEKHAR, RATNAKER BHENGRA, JJ.
M/s Bharat Sanchar Nigam Limited – Appellant
Versus
M/s Hind Electric Company (Electrical Engineers and Machinery Merchants) – Respondent
Commercial Appeal No. 16 of 2022
Decided on : 09-05-2023
Arbitration - Challenge to Arbitral Award - Arbitration and Conciliation Act, 1996 - Section 34 - Commercial Appeal No.16 of 2022 - Summary of Acts and Sections: Arbitration and Conciliation Act, 1996, Section 34 - The court discussed the grounds for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, and emphasized the limited scope of judicial interference with arbitral awards. The court also highlighted the importance of preserving the sanctity of arbitral awards and the need for adherence to the specified grounds for setting aside an award.
Fact of the Case:
M/s Bharat Sanchar Nigam Limited (BSNL) challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, on the ground of procedural irregularity committed by the Sole Arbitrator. The BSNL objected to the award of Rs.31,31,083/- with simple interest @ 10% to the claimant-company, claiming that the legally payable dues were already paid to the claimant-company after statutory deductions and recoveries.
Finding of the Court:
The court found that the objections raised by the BSNL did not fall under any of the grounds mentioned in Section 34 of the Arbitration and Conciliation Act, 1996, on which an arbitral award can be set aside. The court emphasized that it was not required to re-appreciate or re-evaluate the evidence led before the arbitrator and concluded that the BSNL failed to make a case for any interference with the impugned award.
Issues: The key issues included the challenge to the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, and the interpretation of Clause 25 of the Conditions of Contract regarding the appointment of the Sole Arbitrator.
Ratio Decidendi: The court's decision was based on the limited grounds for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, and the interpretation of Clause 25 of the Conditions of Contract. The court emphasized the need to adhere to the specified grounds for setting aside an award and the importance of preserving the sanctity of arbitral awards.
Final Decision: The Commercial Appeal No.16 of 2022 was dismissed, and the parties were directed to bear their own costs.
ORDER :
Per Shree Chandrashekhar, J.
M/s Bharat Sanchar Nigam Limited (in short, “BSNL”) has challenged the order passed in Commercial (Arbitration) Case No.54 of 2019 by which the objection taken by the BSNL to challenge the arbitral award dated 7th January 2019 through a petition under section 34 of the Arbitration and Conciliation Act, 1996 has been found without any substance.
2. Against the order dated 25th May 2022 passed by the Commercial Court at Ranchi, the present Commercial Appeal has been filed by the BSNL under section 13 (1-A) of the Commercial Courts Act, 2015.
3. The BSNL awarded the subject work to the claimant-company for the “Operation and Comprehensive Maintenance of Electro-Mechanical Service for USOF sites in Giridih and Koderma district under Cluster 26”. The work order dated 20th May 2009 was for Rs.51,85,104/-and the completion period was 24 months starting from 1st July 2009. However, the period for completion of the subject work under Master Agreement No.01A/USO/SLA/TEC/ RCH/2009-10 was extended till 30th April 2012.
4. Since a dispute had arisen between the parties in connection to the aforesaid contracts about payments made to the claimant-company and deductions by the BSNL on various counts, the claimant-company invoked Clause 25 of the Conditions of Contract on 8th June 2015 for appointment of the Arbitrator for resolving the dispute which had erupted between the parties, and the Sole Arbitrator was appointed by the Senior Chief Engineer (Electrical) of the BSNL vide Memorandum dated 26th October 2016. Pursuant to his appointment, the Arbitrator issued letter dated 26th November 2016 to both the parties for their no objection before proceeding further in the matter. Later on, after both the parties submitted their no objection to the appointment of the Sole Arbitrator notice dated 31th January 2017 was issued to them. Subsequently, the claimant-company unsuccessfully approached the High Court of Jharkhand in Arbitration Application No. 17 of 2017 to challenge the appointment of Sri Saurabh Tyagi as the Sole Arbitrator and his appointment was affirmed by the High Court, whereafter a fresh notice was given by the Sole Arbitrator to both the parties for submission of their claim and counter-claim.
5. The Arbitrator commenced the proceedings on 9th January 2018 by directing the parties to submit their respective statement of claim(s) and counter-claim(s). On 9th August 2018, the first hearing in respect of all five arbitration cases was held by the Sole Arbitrator at New Delhi. Thereafter, the arbitral proceedings were held on 24th August 2018 and 25th August 2018 and the BSNL was directed to furnish certain documents.
6. The Arbitrator has awarded Rs.31,31,083/-to the claimant-company on account of the claims found admissible and justifiable by him. The awarded sum carried simple interest @ 10% from three months after the date of completion of work for the amount due till 31st December 2018 and future interest on the awarded sum @ 10% from 1st May 2019 till the date of payment or the decree of a competent Court – the interest upto 31st December 2018 has been calculated at Rs.10,88,397/-.
7. By filing a petition under section 34 of the Arbitration and Conciliation Act 1996, the BSNL challenged the aforesaid award on the ground of procedural irregularity committed by the Sole Arbitrator inasmuch as without framing issues and affording an opportunity to the parties to examine witness the Sole Arbitrator has conducted the arbitral proceedings and made the award dated 7th January 2019.
8. The Presiding Officer of the Commercial Court at Ranchi has referred to the judgments in “Navodaya Mass Entertainment Limited v. J. M. Combines” (2015) 5 SCC 698 and “Associate Builders v. DDA” (2015) 3 SCC 49 to fortify his decision that the objections raised by the BSNL in the petition under section 34 of the Arbitration and Conciliation Act, 1996 do not fall under any of the grounds mentioned therein on which an arbitral awar
Associate Builders v. DDA (2015) 3 SCC 49
Maqbul Ahmad v. Onkar Pratap Narain Singh AIR 1935 PC 85
Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority” (1988) 2 SCC 338
Navodaya Mass Entertainment Limited v. J. M. Combines” (2015) 5 SCC 698
The main legal point established in the judgment is the interpretation of 'live dispute' and 'admitted liability' in the context of arbitration proceedings, and the court's reliance on relevant provi....
Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing arbitration.
Court determined claims are not time-barred and appointment of an arbitrator is valid despite the respondent's challenges regarding jurisdiction and limitations.
The arbitration agreement's validity is independent of stamp duty on the substantive contract, and courts have limited grounds for interfering with arbitral awards under Section 34 of the Arbitration....
The court affirmed that deductions for non-performance are valid when based on contract conditions and substantiated by timely verification reports, emphasizing the importance of evidentiary reasonin....
The court upheld the right to appoint a Substitute Arbitrator due to the previous Arbitrator's mandate termination, ensuring the unresolved disputes could be adjudicated. This reflects the essential ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.