IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Shree Vardhman Infrahome Private Limited - Appellant
Versus
Kushal Verma - Respondent
CM(M) 523 of 2022 and CM Appl. 26549 of 2022 (stay) and CM(M) 536 of 2022 and CM Appl. 26605 of 2022
Decided On : 07-07-2022
| Table of Content |
|---|
| 1. execution application and settlement context. (Para 1 , 2 , 3 , 5) |
| 2. force majeure clauses in agreements. (Para 6 , 7 , 8) |
| 3. communication of force majeure by the petitioner. (Para 9 , 10) |
| 4. petitioner’s obligations under the settlement agreement. (Para 11 , 12 , 13) |
| 5. court analysis of force majeure plea. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21) |
| 6. remand for reconsideration of force majeure. (Para 22 , 23 , 24 , 25 , 26) |
| 7. order conclusion without costs. (Para 29 , 30) |
1. These petitions, under Article 227 of the Constitution of India, assail order dated 25th April, 2022, passed by the learned National Consumer Disputes Redressal Commission ("the learned NCDRC") in a batch of execution applications, seeking execution of the order dated 15th January, 2019, passed by the learned NCRDC in Consumer Case no. 1893/2017, (Flora Welfare Association Vs. Shree Vardhman Infrahome Pvt. Ltd.).
2. The order dated 15th January, 2019 reads thus:
"Dated: 15 Jan 2019
ORDER
The matter has been settled between the parties. The learned counsel for the complainant, on instructions from Mr. Sangeet Bali, President of the complainant association who is present in the Court, seeks disposal of the complaint in terms of the written settlement dated 15.01.2019 which is annexed to the application IA No.894 of 2019 filed today in the Court for recording the settlement. The complaint is accordingly disposed of in terms of the settlement dated 15.01.2019 which shall form part of this order. It is also made clear that in case the OP offers to pay the balance payable in kind, such as through additional parking, additional power back-up etc. as per clause 4 and para 2 of the settlement, which shall be for the discretion of the concerned allottees whether to accept such balance in kind such as additional parking, additional power back-up etc. or not. In the event they are not agreeable to accept the said balance in kind, the OP shall pay the balance to them by way of Demand Drafts/bank transfers etc. It has also been agreed between the parties and is ordered accordingly that the aforesaid settlement would not be treated as a binding precedent."
3. The settlement agreement dated 15th January, 2019, in terms of which the learned NCDRC had, vide the afore-extracted order dated 15th January 2019, disposed of Consumer Case 1893/2017, required the petitioner to, inter alia, handover possession of the completed flats/units to the members of Flora Welfare Association, the complainant in Consumer Case 1893/2017, on or before 31st December, 2019, to apply with the concerned authorities for obtaining occupancy certificate in respect of the units on or before 31st March, 2020, and to obtain the occupancy certificate on or before 31st August, 2020.
4. The settlement agreement also incorporated the following clause:
"(d) It is agreed and understood that the terms of the Apartment Buyer Agreement in so far as the same are not inconsistent with the terms of this settlement, shall continue to binding between the parties."
5. The "Apartment Buyer Agreement" (hereinafter referred to as the "ABA") was, it may be noted, the agreement dated 16th January, 2012 referred to the individual agreements executed between the flat buyers and the petitioner, the alleged breach of the obligations contained in which constituted the basis of Consumer Case 1893/2017.
6. The ABAs, which were identically worded, provided for force majeure in Clause 14(a), which reads thus:
"14.(a) The Construction of the Flat is likely to be completed within a period of thirty six (36) months of commencement of construction of the particular tower/block in which the Flat is located with a grace period of six (6) months, on receipt of sanction of the building plans/revised plans and all other approvals subject to force majeure including any restraint/restrictions from any authorities, non-availability of building materials or dispute with construction agency/workforc
Force majeure includes delays due to external restrictions, such as the COVID-19 pandemic and government bans, impacting contract compliance and obligations.
The court remanded the case to reconsider the plea of force majeure, recognizing the developer's claim of Covid-19 related delays in complying with a settlement agreement timeline.
The JD Developer cannot evade responsibility for noncompliance due to force majeure claims when clear obligations exist under the settlement agreement.
1. EP Proceedings - The Execution Proceedings being separate proceedings and be filed under the Act which has been prevalent at the time of filing of the Execution Proceedings.2. Non Compliance of Or....
Builder is bound to complete construction and hand over possession of flat to buyer within stipulated time. Burden would lie on developer to explain steps taken to comply with contractual stipulation....
Written statement – Even when defendant’s/opposite party’s right to file a written statement is forfeited that by itself will not make it obligatory on part of NCDRC to pass an order in favour of a c....
A consumer complaint abates upon the death of a complainant if legal heirs are not substituted within the stipulated time; sufficient cause must be shown for condoning delays in such substitution app....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.