SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Esteem Projects Private Limited - Appellant
Versus
Lloyd Insulations India Ltd. - Respondent
FAO (COMM) 197 of 2021 & CM No. 17598 of 2020
Decided On : 05-12-2022




The court held that claims for arbitration are not barred by limitation if ongoing negotiations substantiate the cause of action arising upon refusal of payment, not upon contract completion.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - The court addressed the appeal against the Commercial Court's rejection of an application to set aside an interim arbitral award. The court upheld that the claim was not barred by limitation as the cause of action arose when the claim was denied on 23.12.2015. (Paras 10, 25)

(B) Limitation - The arbitration claim was deemed timely as negotiations between parties extended the limitation period. The Arbitral Tribunal found that correspondence indicated uncertainty regarding the claim's justification, necessitating a full examination of the facts surrounding the delay. (Paras 20, 25)

Facts of the case:
The appellant issued work orders for a project, imposing penalties for delays it attributed to the respondent's completion of work past the stipulated date. The respondent initiated arbitration over withheld penalties amounting to Rs. 37,00,000, claiming the application was barred by limitation due to delay in invoking arbitration.

Findings of Court:
The learned Commercial Court confirmed the arbitration award, stating that the denial of the claim by the appellant did not render the claim time-barred, affirming the Arbitral Tribunal's finding of no patent illegality.

Issues: The key issue was whether the claim was barred by limitation considering the circumstances surrounding the delay and communications exchanged by the parties.

Ratio Decidendi: The court reasoned that the correspondence suggested ongoing negotiations, and the cause of action arose upon the appellant's refusal of payment, rather than upon the completion date.

Result: Appeal dismissed.

Table of Content
1. factual background of the case. (Para 2 , 3 , 4 , 5)
2. arguments regarding limitation and claim. (Para 6 , 7 , 8 , 9)
3. court's analysis of correspondence and claims. (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27)
4. final decision to dismiss the appeal. (Para 28)

JUDGMENT

Vibhu Bakhru, J. The appellant has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning a judgment dated 12.03.2020 (hereafter `the impugned judgment') passed by the learned Commercial Court, whereby the appellant's application (being Arbitration Petition No. 1947 of 2018) under Section 34 of the A&C Act, seeking to set aside an interim arbitral award dated 07.05.2018 (hereafter `the impugned award'), was rejected.

Factual Context

2. On 06.09.2008, the appellant awarded three work orders for the work of "Detailed Engineering, Supply and Installation of Refractory Lining of HGU Reformer Package of Bongaigaon Refinery and Petrochemicals Ltd at Bongaigaon, Assam" (hereafter `the Project') to the respondent. The date of completion of the Project was stipulated to be 30.04.2009. The contract value was set as Rs.3,70,00,000.

3. The appellant claims that both parties had agreed to consider the three work orders as a singular contract for the purposes of levying penalty and therefore, a penalty (10% of contract value) would be levied on the total contract value of Rs.3,70,00,000.

4. The appellant states that the respondent - due to delays solely attributable to the respondent - completed the work by 23.08.2010, which was well after the stipulated date of completion. Thus, the appellant invoked the penalty clause and imposed a penalty amounting to Rs.37,00,000.

5. Aggrieved by the decision of the appellant to recover damages for the delay, the respondent issued a notice dated 20.01.2016, invoking recourse to the arbitration agreement. Thereafter, the respondent filed a petition under Section 11(6) of the A&C Act for appointment of a sole arbitrator. By an order dated 16.12.2016, this Court referred the parties to the Delhi International Arbitration Centre (DIAC) for the arbitration to be conducted under the aegis of DIAC.

Arbitration

6. The respondent filed its Statement of Claims before the Arbitral Tribunal, inter alia, claiming the amount of Rs.37,00,000, which was withheld by the appellant. On 18.04.2017, the respondent filed an application under Section 16 of the A&C Act, stating that the claim of the respondent be dismissed as being barred by limitation as the notice invoking arbitration, under Section 21 of the A&C Act, was issued beyond the period of three years from the date of completion of the works in question, that is, from 23.08.2010.

7. The Arbitral Tribunal held that the cause of action arose when the appellant - by a letter dated 23.12.2015 sent in response to the legal notice sent by the respondent - finally declined to pay the amount of Rs.37,00,000 withheld by it. The Arbitral Tribunal noted that prior to this communication, the appellant never refuted the claim and therefore, the respondent's claim was not barred by limitation.

Section 34 of the A&C Act

8. The appellant challenged the interim impugned award by filing an application under Section 34 of the A&C Act. The learned Commercial Court found that Article 18 of the Schedule of the Limitation Act, 1963 applies where no schedule for payment is fixed; however, in the present case, the time for payment was fixed as per the agreements. Therefore, Article 18 of the Schedule of the Limitation Act, 1963 would not apply in this case.

9. The learned Commercial Court held that the correspondence between the parties showed that the appellant was leading the respondent to believe that the appellant was considering its request for extension of time until 23.08.2010 and would release the amount of Rs.37,00,000, if the time for completion was extended

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top