SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Del) 797

2025 DHC 2238
IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, SACHIN DATTA, JJ.
M/S Seaspray Shipping Co Ltd. – Appellant
Versus
Steel Authority Of India Ltd. – Respondent
FAO(OS) (COMM) 109 of 2019, FAO(OS) (COMM) 144 of 2019
Decided On : 02-04-2025
Advocates Appeared :
For the Appellant : Mr. Gaurav Mitra, Mr. Dhruv Kapur, Mr. Maharishi Kaler, Mr. Adit Singh, Ms. Aishwarya Modi, Mr. A. Fazelbhoy and Ms. Chahat Arya, Advocates.
For the Respondent : Mr. Raj Shekhar Rao, Sr. Advocate along with Mr. Sunil K. Jain, Mr. Deepanshu Jain, Mr. S. Jain and Mr. Prateek Kumar, Advocates. 

The court affirmed that an arbitral tribunal’s interpretation of a contract is binding if plausible, emphasizing limited grounds for interference under the Arbitration Act, especially in international commercial arbitration.

Headnote:(A) Arbitration & Conciliation Act, 1996 - Section 37(1)(c) - The court addressed the validity of the termination of a Contract of Affreightment (COA) dated 04.12.2007 between shipping and maritime entities, specifically focusing on Clause 62 which permitted termination by the supplier under defined circumstances. The learned Single Judge upheld the arbitral tribunal’s finding that the termination was invalid due to lack of proper reasoning and that the COA was a binding contract. (Paras 4, 45, 62, 86)

(B) The court found that the arbitral tribunal had correctly determined the COA was valid and contained enforceable obligations, rejecting SAIL's arguments regarding force majeure and commercial impracticability. (Paras 38, 70)

(C) The award of damages was held consistent with Section 73 of the Indian Contract Act, reaffirming that compensation should reflect losses due to non-performance. (Paras 73, 80)

(D) Issues included the interpretation of the termination clause, the applicability of maritime jurisdiction, and the nature of awarded damages. (Paras 61, 87) (E) Ruling established that an arbitral award may only be set aside under limited grounds in international commercial arbitration, emphasizing the necessity for decisions to rely on public policy considerations. (Paras 62, 86) (F)

Result: Appeals decided in favor of the appellant, confirming the validity of the arbitral award.

Table of Content
1. intervention of court in arbitration (Para 1 , 6 , 22 , 25)
2. validity of contract interpretation (Para 4)
3. existence of binding agreements (Para 30 , 31 , 32 , 39)
4. finality of arbitration awards (Para 44 , 62 , 88)

JUDGMENT :

SACHIN DATTA, J.

1. These cross-appeals have been filed under Section 37(1)(c) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as the “A&C Act”), challenging the judgment dated 28.02.2019 (hereinafter referred to as the “Impugned Judgment”) passed by the learned Single Judge in OMP No. 76 of 2015. The said petition was filed by the Steel Authority of India Limited (hereinafter referred to as “SAIL”) under Section 34 of the A&C Act, assailing an arbitral award dated 20.08.2014 (hereinafter referred to as the “Original Award”) rendered by an Arbitral Tribunal comprising of three arbitrators: Capt. Satish P. Anand (Presiding Arbitrator), Capt. S.M. Berry, and Mr. Niranjan Chakraborty (hereinafter referred to as the “Arbitral Tribunal”).

2. By the Original Award, the Arbitral Tribunal awarded a net sum of USD 14,049,506.74, which was determined after deducting a 2.5% commission payable to the Charterers and a 1.25% brokerage fee. Additionally, the Arbitral Tribunal awarded an amount of USD 100,000.00 towards legal fees and expenses. The costs of the arbitration, including fees and expenses of the arbitrators and administrative fees of the Indian Council of Arbitration, were fixed at INR 19,60,000. Furthermore, an amount of INR 4,90,000 was awarded to be paid to each arbitrator in accordance with Indian Council of Arbitration rules, and an additional INR 4,90,000 was awarded towards Indian Council of Arbitration administrative fees. Additionally, the Tribunal awarded interest at the rate of 6% per annum from 01.12.2012, until the publication of the award on the net sum of USD 14,049,506.74, and thereafter at 6% per annum until the total awarded amount is fully paid.

3. In the proceedings under Section 34 of the A&C Act, SAIL highlighted that the Arbitral Tribunal had not provided reasoning for its conclusions on certain issues. In light of this, the learned Single Judge, on 22.02.2017, directed the Arbitral Tribunal to reconvene and provide reasons in respect of the specified issues. Complying with this directive, the Arbitral Tribunal passed an Additional Award on 10.06.2017 (hereinafter “Additional Award”) detailing its reasoning for the specified issues of the Original Award. Hereafter, the Original Award and the Additional Award will collectively be referred to as the “Impugned Award.”

4. The learned Single Judge partly allowed SAIL’s petition and set aside the impugned award to the extent of damages computed for the quantity of coal that would have been shipped after the termination of the Agreement till December 2012. It was held that the agreement stood validly terminated by SAIL vide communication dated 11.09.2012 under Clause 62 of the Agreement. The learned Single Judge made the following observations in the impugned Judgement –

“63. Having said so, the Arbitral Award, insofar as it awards damages for the quantity of coal that would have been shipped after the termination of the Agreement till December 2012, cannot be sustained as the exercise of power by the petitioner under Clause 62 of the Agreement has been held to be valid in this order.

64. As the shipment was to be made on “evenly spread per month basis”, the amount due to the respondent would be reworked by taking the Shipment quantity that was due till the date of termination of the Contract.”

5. Additionally, the learned Single Judge modified the award of interest in line with the Hon’ble Supreme Court’s decision in Vedanta Ltd. v. Shenzen Shandong Nuclear Power Construction Co. Ltd , 2018 SCC OnLine SC 1922, setting it at the London Inter Bank Offered Rate (LIBOR).

6. M/s. Seaspray Shipping Co. Ltd. (hereafter Seaspray) has assailed the impugned judgment to the extent that the Impugned Judgment has reverse

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top