IN THE HIGH COURT OF DELHI AT NEW DELHI
C. HARI SHANKAR, OM PRAKASH SHUKLA, JJ.
M.S. Ircon International Limited and Another – Appellants
Versus
M.S. Cannon Engineering Construction Cannon Cottage – Respondent
F.A.O. (OS) (COMM) No. 16 of 2022
Decided On : 24-02-2026
| Table of Content |
|---|
| 1. appeal details and context. (Para 1 , 2 , 3 , 4) |
| 2. factual background of contract execution. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11) |
| 3. disputes concerning extra work and classifications. (Para 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24) |
| 4. arbitral tribunal's findings on claim nos 1 and 2. (Para 25 , 26 , 27 , 28 , 29 , 30) |
| 5. interest and statutory provisions. (Para 34) |
| 6. court's affirmations on arbitration findings. (Para 36 , 37 , 38 , 39 , 40 , 41) |
| 7. appellants' arguments against tribunal's findings. (Para 43 , 44 , 45 , 46 , 47 , 48 , 50 , 51 , 52 , 53) |
| 8. judicial review and limitations of interference. (Para 56 , 57 , 58 , 60 , 61 , 62 , 63 , 66 , 70 , 71) |
| 9. final judgment and appeal dismissal. (Para 86 , 89 , 90) |
JUDGMENT :
OM PRAKASH SHUKLA, J.
Introduction
1. The present intra-court appeal has been preferred by the Appellants under Section 37 (1)(c) of the Arbitration and Conciliation Act, 1996 [“The Act” hereinafter] read with Section 13 of the Commercial Courts Act, 2015 and Section 151 of Code of Civil Procedure, 1908. The appeal assails the judgment dated 01.10.2021 [“Impugned Judgment” hereinafter] passed by the learned Single Judge in O.M.P. (COMM) No. 181/2021, titled as M/s Ircon International Limited & Anr. v. M/s Cannon Engineering Construction Cannon Cottage. The impugned judgment arose out of a petition filed by the Appellants under Section 34 of the Act, seeking to set aside the arbitral award dated 30.01.2021 [“Arbitral Award” hereinafter] rendered by the learned Sole Arbitrator.
2. The dispute giving rise to the arbitral proceedings pertains to a contract dated 05.11.2014 [“contract” hereinafter] executed between the parties, for the “Construction of service buildings, loco shed, RCC Trunk Drain and Misc. Civil Works in connection with the Construction of Private Railway Siding for Solapur Super Thermal Power Project of NTPC Limited near Hotgi Railway Station in Solapur District, Maharashtra-Pkg.4”. By the arbitral award, the learned Arbitral Tribunal [“Tribunal” hereinafter] allowed the majority of the claims raised by the Respondent herein (Claimant before the Tribunal), rejecting only Claim No. 3 and the sole counter-claim made by the Appellants.
3. Vide the Impugned Judgment, the learned Single Judge partly allowed the petition under Section 34 of the Act. The learned Single Judge interfered with the arbitral award only to the limited extent of setting aside the grant of pre-award interest for the period from 06.11.2016 till 30.01.2021, holding that the contract expressly prohibited the grant of such interest. The remaining claims, i.e. Claim Nos. 1, 2, 4, and 5, along with the entitlement to future interest and costs, were upheld by the learned Single Judge.
4. The present appeal is confined to challenging the impugned judgment only insofar as it upholds the arbitral award in respect of Claim No. 1 (hard rock in earth excavation) and Claim No. 2 (tie bolts for RCC wall), as well as the entitlement to future interest and costs. The Appellants contended that the findings underlying the said claims suffer from patent illegality and, therefore, warrant interference by this Court in the exercise of its jurisdiction under Section 37 of the Act.
Facts
5. The factual matrix, as relevant for the adjudication of the present appeal, is outlined below.
6. NTPC Limited [“Appellant No. 2” hereinafter] appointed M/s Ircon International Limited [“Appellant No. 1” hereinafter] as the Project Management Consultant for the Coal Transportation System of its Solapur Super Thermal Power Project (2×660 MW) in Solapur, pursuant to a purchase order dated 01.06.2012. In furtherance of this, a Power of Attorney dated 07.12.2012 was executed in favour of Appellant No.1, authorising it to act on behalf of Appellant No.2, with Appellant No.2 being the employer for the project.
7. For execution of the project, Appellant No.1 issued a Notice Inviting Tender dated 10.07.2014 for Package–4, which pertained to

Godhra Electricity Co. Ltd. & Anr v. State of Gujarat & Anr.
State of Rajasthan v. Puri Construction Co. Ltd.
MCD v. Jagan Nath Ashok Kumar and Another
Oswal Woollen Mills Ltd. v. Oswal Agro Mills Ltd.
Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
The court affirmed the factual determinations of the arbitral tribunal regarding payment for hard rock excavation and tie bolts, highlighting the limited grounds for interference with arbitral awards....
The court affirmed that arbitral awards challenging under Sections 34 and 37 are limited in scope, requiring clear evidence of illegality or perversion; otherwise, the Arbitrator's decision stands.
Arbitration - If the Arbitrator so appointed resigns his appointment or vacates his office or is unable or unwilling to act due to any reason whatsoever, the authority appointing him may appoint a ne....
An award for extra payment due to change in quarry source is valid if proper authority sanction exists and statutory provisions take precedence over contractual limitations.
An arbitrator cannot exceed jurisdiction by awarding claims not supported by written approval as mandated by the contract, rendering the award illegal.
Point of law: Arbitral Tribunal is not bound by the Code of Civil Procedure or the Indian Evidence Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.