SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Guj) 1932

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Hemant M. Prachchhak, J.
State Of Gujarat & Anr. – Appellants
Versus
Shashi R Shah – Respondent
R/First Appeal No. 563 of 2000
Decided On : 10-09-2025

Advocates Appeared:
For the Appellant : Ms Roshni Patel AGP
For the Defendant : Mr Shaivang D Mehta

Interest awarded by the trial court must be just and reasonable; the appellate court reduced the interest rate from 12% to 9%, upholding the damage assessment.

Headnote:(A) Civil Procedure Code - Section 96 - Indian Contract Act, 1872 - Section 73 - Appeal against the judgment and decree awarding Rs. 9,72,582/- with 12% interest. The appeal sought reduction of interest which was deemed excessive. The court modified the interest rate to 9% while upholding the damages awarded. (Para 8)

(B) Appeal - The court emphasized that the award of interest must be just and reasonable, and discretion should be exercised with cogent reasoning. Findings of the trial court were upheld, indicating no infirmity in damage assessment. (Para 7)

Facts of the case:
The plaintiff, an Engineer and Contractor, was awarded a contract for construction by State authorities. Disputes arose over delays and unapproved plans, leading to damages claimed and a suit filed to recover amounts due. The trial court awarded partial judgment favoring the plaintiff. (Paras 2.1 - 2.4)

Findings of Court:
The trial court's award of Rs. 9,72,582/- was found to be reasonable, and the awarded interest was deemed excessive, requiring modification. (Para 8)

Issues: The appeal addressed whether the interest awarded was appropriate and if damages had been correctly assessed.

Ratio Decidendi: The appellate court held that the assessment of damages by the trial court was proper under Section 73 of the Indian Contract Act and noted the discretion in awarding interest must be reasonable and justified. (Para 8)

Result: The appeal was allowed in part, modifying the interest rate to 9%, with other findings upheld.

Table of Content
1. facts of the case involving a construction dispute. (Para 1 , 2)
2. appellant's arguments against the trial court's decision. (Para 3)
3. respondent's defense of the trial court's judgment. (Para 4)
4. court's analysis and reasoning on interest rates. (Para 5 , 6 , 7 , 8)
5. court's modified order on interest rate. (Para 9 , 10)

JUDGMENT :

Hemant M. Prachchhak, J.

1. The appellants State Authorities have preferred present appeal under Section 96 of the Civil Procedure Code read with section 41 of Civil Procedure Code against the judgment and decree dated 30.10.1999 passed by the Civil Judge (S.D.) Bharuch (hereinafter be referred to as the "trial Court") in Special Civil Suit No. 149 of 1991, whereby the suit was partly allowed an amount of Rs. 9,72,582/- along with 12% simple interest was awarded in favour of the present respondent-original plaintiff.

FACTS OF THE CASE

2. The facts giving rise to present appeal are that the respondent herein-original plaintiff (hereinafter be referred to as the "plaintiff") is an Engineer and Contractor, duly registered as a P.W.D. contractor and with other departments. The present appellant No.2- original defendant No.2, Executive Engineer, Roads and Buildings Division, Bharuch, on behalf of original defendant No.1, had invited tenders for construction of an Administrative Block and Workshop Building for Muni I.T.I. at Jhagadia in Bharuch District.

2.1 The plaintiff had submitted his tender, which was found to be competitive and was accepted by defendant No.2. The plaintiff was called upon to deposit an initial security of Rs.23,000/- and upon payment of the same, a regular agreement bearing No. B-1/31 of 1987-88 was executed between the plaintiff and defendant No.2. As per the agreement, the work valued at Rs.12,93,120.80 ps. was to commence from 11.08.1987 and was to be completed within 18 months, i.e., on or before 10.02.1989. After issuance of the work order, the plaintiff commenced the work by mobilising materials and labour, but only one set of plans was given.

2.2 The plaintiff by letter dated 01.11.1987 requested details of doors, windows, trusses, reinforcement etc. and further informed on 27.12.1987 that the foundation excavation was completed in the first week of December 1987, but concreting could not be done as the foundation details were not clear. He also requested soil testing and further drawings. The plaintiff further intimated by letter dated 20.02.1988 that he had excavated one metre below the estimated depth but the foundations were not approved, and by letter dated 25.03.1988 he pointed out that as the strata consisted of black cotton soil, it was essential to excavate with 1:1:15 slope and that measurement should be paid accordingly. On 06.04.1988, he informed that the Deputy Executive Engineer had directed stoppage of work till final decision on the foundation strata was taken, and by letter dated 12.06.1988 stated that final plans and drawings were not supplied and the design was not finalised, which resulted in repeated removal of executed work. On 17.08.1988 and 30.08.1988, the plaintiff again pointed out that the design was still not finalised and that though initially a load- bearing design was given, the defendants later ordered continuation with partly load-bearing and partly frame structure, due to which he had to dismantle some work. By letter dated 10.09.1988, the plaintiff stated that he had incurred heavy losses due to indecision of the authorities and that he would submit a separate claim, and also raised the issue of overhead expenses, loss of interest on unpaid work and additional expenditure due to delay. By letter dated 02.10.1988, he informed that the drawings supplied by the Deputy Engineer were incomplete and, since the design was changed, he demanded new rates and costs for dismantled work, which he reiterated on 18.12.1988 after discussions with the Executive Engineer. At one stage, the plaintiff even expressed willingness to continue the




Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top