IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
HEMANT M. PRACHCHHAK
State Of Gujarat – Appellant
Versus
Shashi R Shah – Respondent
JUDGMENT :
Hemant M. Prachchhak, J.
1. The appellants State Authorities have preferred present appeal under Section 96 of the Civil Procedure Code read with section 41 of Civil Procedure Code against the judgment and decree dated 30.10.1999 passed by the Civil Judge (S.D.) Bharuch (hereinafter be referred to as the "trial Court") in Special Civil Suit No. 149 of 1991, whereby the suit was partly allowed an amount of Rs. 9,72,582/- along with 12% simple interest was awarded in favour of the present respondent-original plaintiff.
FACTS OF THE CASE
2. The facts giving rise to present appeal are that the respondent herein-original plaintiff (hereinafter be referred to as the "plaintiff") is an Engineer and Contractor, duly registered as a P.W.D. contractor and with other departments. The present appellant No.2- original defendant No.2, Executive Engineer, Roads and Buildings Division, Bharuch, on behalf of original defendant No.1, had invited tenders for construction of an Administrative Block and Workshop Building for Muni I.T.I. at Jhagadia in Bharuch District.
2.1 The plaintiff had submitted his tender, which was found to be competitive and was accepted by defendant No.2. The plaintiff w
Mohd. Salamatullah and others vs. Government of Andhra Pradesh
Interest awarded by the trial court must be just and reasonable; the appellate court reduced the interest rate from 12% to 9%, upholding the damage assessment.
State authorities are liable for breach of contract when failing to fulfill terms, allowing for the contractor to claim due payments and interest, subject to evidentiary support and stipulations.
A party's failure to perform crucial contractual obligations constitutes a fundamental breach, thereby entitling the other party to seek compensation, with appropriate adjustments on interest rates b....
The court upheld the plaintiff's claims for withheld payments under the contract, establishing entitlement based on completed work despite defendants' claims of substandard quality and modified the i....
The court upheld the trial Court's decree for recovery of contract payments, emphasizing the contractor's timely completion of work and the defendants' failure to prove claims of substandard work.
The court affirmed that a contractor's claims for delays caused by defendants were valid, and it has the discretion to adjust interest rates based on economic conditions.
Court may exercise discretion in awarding interest to compensate for money value diminution under Section 34 of CPC.
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
Civil Courts have jurisdiction to hear claims under construction contracts barred from arbitration, provided they arise within the limitation period set by specific contract conditions.
Escalation of contract rates is permissible when delays are not due to the contractor's fault, allowing for additional payment for work done after significant delays.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.