IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
Venuthurumalli Gopala Krishna Rao, J.
The Chief Engineer, and Others – Appellants
Versus
Y V Swami Reddy - Respondent
First Appeal No: 223/2005
Decided On : 02-01-2025
(A) Code of Civil Procedure, 1908 - Section 96 - Appeal against decree and judgment - The plaintiff, a registered contractor, sought recovery of Rs.3,85,371/- from the defendants for work completed under a contract, including withheld security deposits and additional work. The trial Court decreed the suit, leading to this appeal. (Paras 1-9)
(B) Contract Law - The plaintiff completed the work within the stipulated time and the defendants failed to prove substandard work. The trial Court's findings were upheld except for the interest rate. (Paras 14-24)
Facts of the case:
The plaintiff was awarded a contract for road work, completed ahead of schedule, but faced deductions and non-payment for additional work. The defendants claimed substandard work but failed to substantiate this.
Findings of Court:
The trial Court awarded Rs.3,85,371/- to the plaintiff, which was upheld with a modification of the interest rate.
Issues: The main issues included the binding nature of government orders on the plaintiff, the quality of work, and entitlement to recover the suit amount.
Ratio Decidendi: The court found that the plaintiff completed the work satisfactorily and the defendants did not provide sufficient evidence for their claims of substandard work.
Result: Appeal allowed in part, modifying interest rate to 6% per annum.
JUDGMENT :
VENUTHURUMALLI GOPALA KRISHNA RAO, J.
This Appeal, under Section 96 of the Code of Civil Procedure [for short 'the C.P.C.'], is filed by the Appellants challenging the decree and judgment, dated 17.12.2004 in O.S.No.7 of 2001 passed by the Senior Civil Judge, Nandikotkur [for short 'the trial Court'].
2. The appellants herein are the defendants and Respondent herein is the plaintiff in O.S.No.7 of 2001.
3. The respondent/plaintiff filed the suit for recovery of Rs.3,85,371/- payable by the defendants/Government for the security deposit amount of Rs.1,85,317/- already deducted by the 3rd defendant in final bill on 10.10.2000 and Rs.1,00,000/- to be paid for the additional work completed by the plaintiff, Rs.50,000/- towards earnest money deposit deposited on 28.04.1997 and Rs.50,000/- deposited by the defendant in package No.3 B.T. Road from Parumanchala to Tudicherla with future interest at 18% per annum from the date of filing of the suit till realization and with costs.
4. Both the parties in the Appeal will be referred to as they are arrayed before the trial Court.
5. The brief averments of the plaint, in O.S.No.7 of 2001, are as under:
The plaintiff is a registered contractor. He was awarded execution of work that is providing B.T. Road from Parumanchala to Tudicherla under agreement No.11/96-97, dated 28.04.1997. As per terms of the contract, the plaintiff has to complete the work by 04.04.1998 and he has completed the work under the above agreement by 16.03.1998. The plaintiff further contended that while execution of work under the above agreement is going on, the 3rd defendant addressed a letter to 2nd defendant stating that additional work of the widening the road was also taken up and completed as per the guidelines of NABARD through the letter No.AE-2 NABARD/98, dated 28.08.1998 and excess amount of the additional work which was spent by the plaintiff was not yet paid even after completion of check measurement and finalization of bill. With regard to the above said works there was a correspondence between the defendant Nos.2 and 3 and from it, it is clear that the plaintiff completed the work by August, 1998 as per the terms and conditions of the original agreement. The maintenance period was also ended by 03.04.1999. So, the final bill was pending and as already the execution of work was also completed prior to the supplemental agreement. The plaintiff further contended that towards the agreement, dated 28.04.1997, the defendants 2 and 3 deducted F.S.D. in the final bill to an extent of Rs.1,85,371/- on 10.10.2000 and he has to get Rs.1,00,000/- towards balance payment of additional work and also earnest money deposit of Rs.50,000/- deposited by him at the time of agreement. Without issuing notice to the plaintiff, the defendants 2 and 3 deducted Rs.50,000/- in September, 2000 in other work i.e., package No.3 B.T. Road from Velgodu to Guntakandala and also an amount of Rs.1,00,000/- in the bills to be paid to the plaintiff in the agreement No.11/96-97. After knowing the above said deductions, the plaintiff approached the defendants 2 and 3 about the deductions made by them, but they failed to do so. Hence the suit.
6. The 3rd defendant filed written statement which was adopted by the defendants 1, 2 and 4 by denying all the averments mentioned in the plaint and further contended as under: -
The plaintiff originally entered into agreement with the Department for executing a work of estimate amount of Rs.20,00,000/- but he executed work of estimated amount of Rs.20,99,996/-. This revision was approved by the competent authority as per departmental rules i.e., the Superintending Engineer, Panchayat Raj, Ananthapur, Camp Office at Kurnool. Regarding the excess amount, the plaintiff entered into a supplemental agreement with the Department on 27.09.2000, the completion of work time gap occurred because excess work was executed beyond original agreement provision. For the additional amount of work executed, revised adm
The court upheld the trial Court's decree for recovery of contract payments, emphasizing the contractor's timely completion of work and the defendants' failure to prove claims of substandard work.
The court upheld the plaintiff's claims for withheld payments under the contract, establishing entitlement based on completed work despite defendants' claims of substandard quality and modified the i....
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
The court affirmed that a contractor's claims for delays caused by defendants were valid, and it has the discretion to adjust interest rates based on economic conditions.
The court upheld that delayed payments must be compensated with interest, emphasizing that the appellants’ claims of irregularities were unsubstantiated and did not impede the contractors' right to r....
The lack of privity of contract and failure to establish a cause of action were central to the court's decision.
A party's failure to perform crucial contractual obligations constitutes a fundamental breach, thereby entitling the other party to seek compensation, with appropriate adjustments on interest rates b....
The court upheld that a party may be compensated for work done despite absence of a written contract when the other party benefits, reinforcing principles of unjust enrichment under Section 70 of the....
Point of law: When the appeal is presented in terms of Section 96 CPC and when this Court is considering this appeal not only as a last Court of fact but also in terms of law, it is open for the appe....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.