IN THE HIGH COURT OF GAUHATI
S. SERTO, J.
Lalthuama Sailo - Appellant
Versus
State Of Mizoram - Respondent
W.P(C) No. 99 & 151 of 2019
Decided On : 05-04-2022
Electricity Act - Compensation for Transmission Line Towers - Sec. 67(2)(e) of the Electricity Act, 2003, Sec. 10 and 16 of the Indian Telegraph Act, 1885 - The court discussed the applicability of the Electricity Act and the guidelines framed by the Central Government for determining compensation towards damages. The court emphasized the constitutional right to property and the duty of the State Government to pay due compensation, irrespective of the delay in making the claim. The court also addressed the issue of responsibility for paying compensation, ultimately directing the State Government to pay the compensation first and get it reimbursed by the Contractor if found liable.
Fact of the Case:
The petitioners claimed compensation for their lands on which transmission towers were constructed for the 132 KV Single Circuit Transmission Lines, citing the Electricity Act and guidelines for determining compensation. The State respondents argued that the petitioners' claims were too late and that the responsibility for compensation lay with the Contractor or the State Government.
Finding of the Court:
The court found that the petitioners were entitled to compensation as per the law applicable, emphasizing the constitutional right to property and the duty of the State Government to pay due compensation. The court also determined that the State Government should pay the compensation first and get it reimbursed by the Contractor if found liable.
Issues: The issues involved whether the petitioners were still entitled to claim compensation and who among the respondents would be responsible for giving the compensation.
Ratio Decidendi: The court held that the petitioners were entitled to compensation regardless of the delay in making the claim, emphasizing the constitutional right to property and the duty of the State Government to pay due compensation. The court also determined that the State Government should pay the compensation first and get it reimbursed by the Contractor if found liable.
Final Decision: The court directed the State Government to pay the compensation as may be determined by the competent authority as per law within a period of six months.
JUDGMENT :
(S. Serto, J.) : –
1. Heard Mr. C. Lalfakzuala, learned counsel appearing for the petitioners in WP(C)/99/2019, Mr. Rosangzuala Ralte, learned counsel for the petitioners in WP(C)/151/2019, Ms. Linda L. Fambawl, learned Government Advocate appearing for the State respondents in both the Writ Petitions and Mr. Zoramchhana, learned counsel appearing for the private respondent in both the Writ Petitions.
2. The claim of the petitioners in both the Writ Petitions- the three petitioners in WP(C)/99/2019, and the four petitioners in the other Writ Petition, i.e., WP(C)/151/2019- is that, though the respondents had erected/constructed transmission towers of 132 KV Single Circuit Transmission Lines in their lands situated at Kawnpui and Khamrang (in WP(C)/99/2019), and Thlanmual Veng, Thingdawl, Melveng Lui Ram, Thingdawl, Parvalui Ruam, Thingdawl and Berawlui Ram, Thing-dawl (in WP(C)/151/2019), no compensation as per law applicable in the State has ever been awarded to them. It has been submitted by both the learned counsels of the petitioners in the Writ Petitions that, as per sec. 67(2)(e) of the Electricity Act, 2003, whenever towers are constructed for electricity power lines, appropriate Authority as per the applicable law has to determine the compensation or rent payable to the persons affected by such project works, but the petitioners have never been paid any compensation for their respective lands on which the towers have been constructed for the 132 KV Single Circuit Transmission Line. The learned counsel has also submitted that though no rule has been framed by the State Government under the Electricity Act, Guidelines framed by the Central Government which provides for determining the compensation towards damages as stipulated in sec. 67 and 68 of the Electricity Act, 2003, read with Sec. 10 and 16 of the Indian Telegraph Act, 1885 has been adopted. And as per the guidelines, the persons whose lands are affected by such works are entitled to adequate compensation, which is 100% of the land value as given in Notification No. D.11028/8/2017-P&E dtd. 1/5/2019, issued by the Secretary to the Government of Mizoram, Power and Electricity Department. Therefore, the respondents are liable to pay compensation to the petitioners for their land values on which the transmission towers have been constructed.
3. Ms. Linda L. Fambawl, learned Government Advocate appearing for the State respondents submitted that though the Notification dtd. 21/1/2010 was issued before the construction of the towers for putting up of the 132 KV Single Circuit Transmission Line, none of the petitioners made their claim, therefore, it is too late in the day for them to make their claims. The learned Government Advocate, by referring to Clause 3.0(v) of the General Conditions of the Contract signed between the Contractor and the Power and Electricity Department, Government of Mizoram also submitted that as per the Contract Agreement, Right of Way of the Transmission line is the responsibility of the Contractor. Therefore, even if compensation is to be paid it is the Contractor who is responsible to pay the same.
4. On the other hand, Mr. Zoramchhana, learned counsel for the private respondent by referring to Clause 2.7 of the Contract Agreement submitted that as per this Clause, 'owner' means the Power and Electricity Department, Government of Mizoram, therefore, it is the responsibility of the State Government to pay the compensation for the lands of the petitioners where the towers have been constructed.
5. In reply to the submissions of both the learned counsels of the respondents, the learned counsels of the petitioners submitted that though the Notification dtd. 21/1/2010 might have been issued it was never published widely for the land-owners to know the contents of the same. They also submitted that the respondents have not annexed copies of the newspaper in support of their submission that their Notification was published in the local pa
AI
The central legal point established in the judgment is the constitutional right to property and the duty of the State Government to pay due compensation, irrespective of the delay in making the claim....
Individual landowners have no legal, fundamental, or constitutional right to claim compensation for the 'aerial right of way' beneath transmission lines, as this right vests with the State, though th....
The court mandated reassessment of property compensation to comply with existing statutory provisions following the completion of construction.
The main legal point established in the judgment is that the claim for compensation for land acquisition is subject to the statutory period of limitation, and the retrospective effect of government r....
The court established that the authorities had the power to proceed with laying electricity lines and towers without obtaining prior consent from the landowners, and that the compensation was being d....
The Court established that landowners have the right to seek compensation for land acquired under the Electricity Act and the Indian Telegraph Act, and disputes regarding compensation should be addre....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.