ARUN DEV CHOUDHURY
Mrigen Bhagawati, S/o. Sri Jiten Bhagawati – Appellant
Versus
State Of Assam, rep. By The Comm. And Secy. To The Govt. Of Assam, Irrigation Deptt. – Respondent
ORDER :
1. Heard Mr. A Biswas learned counsel for the petitioner and Mr. N. Upadhyay learned standing counsel, Irrigation Department.
2. The present writ petition is filed assailing a speaking order dated 28.11.2019 whereby the claim for “escalation of price” made by the petitioner in execution of a contract was rejected.
3. Pursuant to a NIT dated 10.12.2004 for execution of work, namely “Bordikorai Irrigation Scheme-Extension of Spillway Road Slab, Railing etc, the petitioner was awarded the said contract on 07.03.2007. During the continuation execution of the work, the petitioner sought for escalation of price for various reasons including delay attributable to the respondents.
4. When such claim of escalation was not considered, the petitioner preferred a writ petition being WP(C) No.6162/2015. This court under its order dated 10.12.2018 disposed of the writ petition directing the Chief Engineer, Irrigation Department to treat the writ petition as a part of the representation and to dispose of the representation dated 10.05.2015 submitted by the petitioner by a speaking order. Subsequently the impugned speaking order was passed.
5. By way of the speaking order the Chief Engineer, Ir
ABL International ltd vs. Export Credit Guarantee Corporation of India Ltd.
Joshi Technologies International Inc. Vs. Union of India and others
The court emphasized the limitations and parameters of exercising jurisdiction under Article 226, particularly in cases involving private contracts, and highlighted the need for detailed evidence and....
The court affirmed contractors' rights to price escalation due to delays in site handover by the Municipal Corporation, emphasizing non-compliance with contract terms and fair hearing principles in a....
A contractor cannot claim price escalation if the work execution exceeds stipulated timelines and lacks a price adjustment clause in the contract.
The court established that a contractor may be entitled to price escalation under a contract if the actual completion period extends beyond the originally stipulated time, even if the initial contrac....
Nature of award is more or less is a consent award, based on admitted facts with respect to handing over partial site and delay in handing over complete site causing non-completion of work within sti....
A contract's timelines affected by mutual agreements for delays allow claims for price escalation under applicable clauses, establishing equity in contractual relations with state entities.
The main legal point established in the judgment is the entitlement of the petitioner to escalation cost under the contractual provision of Clause-32(a)(b)(c) despite the submission of a 'no claim ce....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.