THE GAUHATI HIGH COURT AT GUWAHATI, (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
(PRINCIPAL SEAT AT GUWAHATI)
ROBIN PHUKAN, J.
Sri Prasanta Saha, S/o Prabir Kr. Saha – Appellant
Versus
Sri Biplab Kumar Chetia, S/o. Late Dr. Bipin Chetia – Respondent
RFA No. 100 of 2017
Decided On : 28-07-2025
| Table of Content |
|---|
| 1. procedural history and factual foundation of the suit. (Para 1 , 2 , 3 , 4 , 5) |
| 2. arguments concerning contract breach and the applicability of section 70 versus section 73 of the indian contract act. (Para 6 , 7) |
| 3. evaluation of evidence regarding the alleged oral agreement and admissibility of banking records. (Para 8 , 9) |
| 4. analysis of quasi-contractual obligations under section 70 of the indian contract act in the presence of an existing agreement. (Para 10 , 11 , 12 , 13) |
| 5. final determination on failure to prove damages and dismissal of the appeal. (Para 14 , 15 , 16 , 17) |
JUDGMENT :
ROBIN PHUKAN, J.
Heard Mr. B.K. Bhagawati, learned counsel for the appellant and Mr. S.P. Choudhury, learned counsel for the respondent.
2. In this appeal, under Order 41 Rules 1 & 2 of the CPC, the appellant has put to challenge the correctness or otherwise of the Judgment and Decree dated 30.03.2017, passed by the learned Civil Judge No. 2, Kamrup (M) at Guwahati (trial court hereinafter), in Title Suit No. 229/2010.
3. For the sake of convenience and to avoid confusion, the name of the parties appeared in the said title suit is adopted herein also.
4. It is to be noted here that vide impugned Judgment and Decree dated 30.03.2017, the learned trial court had dismissed the suit of the plaintiff, wherein the plaintiff had prayed for the outstanding amount of Rs.57,56,699/- along with interest @ 15% per annum.
Background Facts:-
5. The background facts, leading to filing of the present appeal, are adumbrated herein below:-
“The plaintiff is a Class I(A) contractor and the defendant is a government contractor running a proprietorship concern. On 16.05.2005, the defendant obtained a work order from the PWD (Border Roads), Government of Assam in respect of construction of IBB bund-cum-road including security fencing along the Surma river bank from Kinnerkhel to Harinagar, in Cachar and the bid price was Rs. 2,48,33,396/- and the Executive Engineer, Badarpur, BRC Division, vide letter dated 02.03.2006, directed the defendant to commence the work so as to complete the same by December, 2006. Since the defendant could not execute the work properly due to resistance from local people, against acquisition proceedings, the work could not be executed. Thereafter, on 25.03.2008, the Government of Assam notified the acquisition of land for construction of the said road.
Since the year 2005-2006, the defendant requested the plaintiff to provide his services in executing the aforesaid work against the work order. Then, the plaintiff and the defendant mutually agreed that the plaintiff would take entire responsibilities for execution of the aforesaid work as per the terms of the agreement. However, no written contract was executed between them but, it was agreed that the plaintiff would raise bills and he would be compensated for the work. Thereafter, the plaintiff had completed the work and he received various payments for the period 2006 - 2008. But, after 2008, the defendant did not clear any of the bills for work done and the plaintiff has alleged that the work done worth of Rs. 1,07,76,699/-, he has received only Rs.50,20,000/- and despite repeated request, the defendant failed to pay the outstanding amount of Rs. 57,56,699/- along with an interest @ 15% per annum.
Being aggrieved, the plaintiff had instituted the suit before the learned trial court. But, the same came to be dismissed vide impugned judgment and decree dated 30.03.2017.
The defendant had contested the suit by filing his written statement, wherein a stand had been taken that there is no cause of action, there is no privity of contract between him and the plaintiff and the suit is not maintainable and barred by limitation and is bad for non- joinder of parties. It is also stated that though there was initial problem in commencing the work due to non- acquisition of land but, the land was acquisitioned and thereafter, he started the work as awarded to him. It is also stated that the
State of W.B. vs. M/s B.K. Mondal and Sons
The court upheld that a party may be compensated for work done despite absence of a written contract when the other party benefits, reinforcing principles of unjust enrichment under Section 70 of the....
Section 16 lays down that even interest is payable on amount entitled to by a unit.
Point of law: When a contract has been broken, if a sum is named in the contract as the amount be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the....
The court affirmed that the scope of interference in arbitral awards is limited, emphasizing that awards can only be set aside on specific grounds, including patent illegality or violation of public ....
Fraud allegations require specific pleadings with particulars under CPC Order VI Rule 4; vague pleas rejected. Limitation for work recovery runs from contract-specified final bill settlement date. Pr....
Contractors must adhere to measurement protocols outlined in contract agreements; failure by the other party to fulfill their obligations does not negate a claimant's right to recover amounts due.
The plaintiff must substantiate claims with clear evidence; failure to do so renders the trial court's decree arbitrary and subject to remand.
A contract can be frustrated by an event that makes it impossible for the parties to perform their obligations under the contract.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.