SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 275

IN THE HIGH COURT OF KERALA AT ERNAKULAM
Viju Abraham, J.
M/s.Crezin Infra LLP – Petitioner
Versus
State Of Kerala Rep. By The Secretary To The Government, Public Works Department – Respondent
WP(C) NO. 21874 OF 2022
Decided On : 17-03-2026

Advocates Appeared:
For the Petitioner: Sri.K.Babu Thomas, Smt.Marykutty Babu
For the Respondent: GP Riyal Devassy

Time limits in contracts must exclude the first day when calculating execution periods, following relevant legislative guidelines.

Headnote:(A) Kerala Public Works Department Manual - Clause 2009.6 - Writ petition challenging the termination of a contract for public works due to alleged failure to execute an agreement within prescribed time limits - Dispute over the commencement date of the time limits; petitioner contended that it should be from the date of registered post receipt, while the respondents argued it should be from the emailed notice of selection. Court held that the date of email is to be excluded in calculating the period for executing the agreement - The petitioner approached the authorities within the stipulated time. (Paras 2-8)

(B) Legal Principles - The court emphasized that time limits set for contractual obligations must be interpreted in light of explicit legislative provisions regarding commencement and termination of periods - Based on related case law, the court reiterated that the first day in a series of days should be excluded from such calculations. (Paras 7-8)

Facts of the case:
The petitioner, a limited liability partnership, was awarded a contract for flood rectification works. An email was sent for acceptance of the tender with corresponding documents, and there was a claim of an illegitimate termination of the contract due to failure to execute the agreement timely. Many communications ensued between the parties regarding the status of the contract.

Findings of Court:
The court found the termination of the contract unjust and ruled that the actions taken by the authorities were not in accordance with the allowed timelines as per the PWD manual.

Issues: The primary issue was whether the time period for executing the agreement should begin from the date of the registered postal notice or the email.

Ratio Decidendi: The court ruled that the date of sending the email must be excluded when calculating the agreement execution period per the applicable schedule and PWD manual provisions, allowing the petitioner up until the appropriate deadline.

Result: The writ petition is allowed, and the termination of the contract is set aside.

Table of Content
1. details of the contract and its execution timeline. (Para 2)

JUDGMENT :

Viju Abraham, J.

The above writ petition is filed challenging Exts.P4 and P9 and for other consequential reliefs.

2. Brief facts necessary for the disposal of the writ petition are as follows: Petitioner, a Limited Liability Partnership, was awarded a contract by the respondents for "FD work-2018-19 Flood rectification works to Chiyyaram Convent Road from ch.2/150 to ch.3/000, providing BM & BC (Balance Works)" on issuing Letter of Acceptance dated 24.01.2022 for works valued Rs.79,95,465.20, sent by registered post on 28.01.2022, directing to furnish security deposit of Rs.3,99,800/- and additional performance guarantee for Rs.7,66,300/-, to execute an agreement for carrying out the works, within 14 days of registration of the same. The copy of the said letter of acceptance, dated 24.01.2022, and the postal cover are produced as Ext.P1. The specific case of the petitioner is that the period of 14 days stipulated is to be reckoned from 28.01.2022 since the postal application was registered on 28.01.2022, and the said time limit will expire only on 11.02.2022. But, the 3rd respondent has sent Ext.P2 letter dated 08.02.2022, intimating that the agreement could be executed within a period of 10 days up to 17.02.2022, with a fine of Rs.25,000/-, and directing to furnish security deposit and other documents required. Petitioner would submit that the further period of 10 days to execute an agreement with a fine of Rs.25,000/- reckoned from 11.02.2022 expired only on 21.02.2022 and therefore, the direction in Ext.P2 to execute the agreement before 17.02.2022 is unauthorised, arbitrary and illegal. Ext.P3 stamp papers were purchased by the petitioner on 14.02.2022 and on 17.02.2022, petitioner remitted fine of Rs.25,000/- as evident from Ext.P3(a) and further that as per Ext.P3(b) petitioner deposited Rs.2,00,000/- and Rs.3,83,500/- at the District Treasury, Kasaragod towards 50% of the security deposit and additional performance guarantee. It is submitted that on 17.02.2022 petitioner had deposited Rs.2,00,000/- and Rs.3,83,200/- at the South Indian Bank, duly pledged to the 3rd respondent towards 50% of security deposit and additional performance guarantee as evident from Ext.P3(c). on 17.02.2022 insurance policy for an amount of Rs.2,00,000/- was taken from United India Insurance Company Ltd., Kasaragod as evident from Ex.P3(d). The contention of the petitioner is that they are entitled to execute an agreement till 21.02.2022. But, on 18.02.2022, Ext.P4 order was issued illegally, terminating the contract at the risk and costs of the petitioner. On 21.02.2022, the 3rd respondent sent Ext.P5 communication illegally denying the legitimate right of the petitioner to execute an agreement for carrying out the works specified in Ext.P1 within the period available up to 21.02.2022, relying on the e-mail dated 25.01.2022, pretending unawareness of the clear intimation in Ext.P1 that agreement is to be executed within 14 days of registration of the same on 28.01.2022. On 23.2.2022, the petitioner sent Ext.P6 letter to the 3rd respondent requesting the release of Ext.P3 series of fixed deposits pledged. On 24.02.2022, the petitioner sent Ext.P8 letter to the 2ndrespondent requesting to revoke the unauthorised and illegal termination of the contract and to waive the risk and cost unlawfully imposed. Thereafter, Ext.P9 letter was issued by the 3rd respondent to the petitioner, illegally demanding payment of Rs.25,87,506/- allegedly towards 30% of the value of work of Rs.79,95,465.20 based on Ext.P4. Petitioner submits that the said demand is absolutely illegal, without jurisdiction, arbitrary, and invalid. It is in the said circumstance that the petitioner has approached this Court.

3. A detailed statement has been filed by the 3rd respondent, wherein the stand taken is that the petitioner’s quotation was accepted and the petitioner was informed, as per e-mai

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top