SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 344

IN THE HIGH COURT OF KERALA AT ERNAKULAM
SATHISH NINAN, P. KRISHNA KUMAR, JJ.
Kerala State Electrcity Board Limited – Appellant
Versus
M/s. Ceebuild Co. Ltd. – Respondent
R.F.A. No. 665 of 2016
Decided On : 26-03-2026

Advocates Appeared:
For the Appellant : B. Premod
For the Respondents: G. Balamuraleedharan, A.N. Santhosh

Actual damages must be proved for recovery in breach of contract. Clauses implying penalties cannot be enforced without valid demonstration of loss.

Headnote:(A) Indian Contract Act, 1872 - Sections 73 and 74 - Breach of contract - Recovery of amounts due under a supply contract - Plaintiff entitled to recover unpaid amounts and security deposit. (Paras 7, 22)

(B) Penalty and Liquidated Damages - Clause described as penalty - Must prove actual damages suffered - Stipulated amounts considered penalties rather than genuine pre-estimates. (Paras 14, 22)

(C) Preliminary objection regarding maintainability rejected based on prior ruling. (Paras 10, 12)

Facts of the case:
The suit for recovery was filed for the amount due under a supply contract where the total supplied was less than agreed. The plaintiff argued for the remaining amounts and damages claimed by the defendant were unproven.

Findings of Court:
The court held that the deductions by the defendant were not justified as actual damages were not evidenced.

Issues: Whether the defendant could forfeit the security deposit and deduct amounts for alleged damages without proving actual loss?

Ratio Decidendi: The court ruled that damages must be proved to recover against a breach, indicating that clauses in the contract being claimed as penalties must not be treated as genuine pre-estimates unless evidenced otherwise.

Result: Appeal dismissed.

Judgement Key Points

Key Points: - The suit concerns recovery of money for breach of supply contract and a decree for Rs.47,63,818/- with interest [1]. - Court held that deductions by the defendant were not justified as actual damages were not evidenced [7]. - Clauses described as penalties must be proven as genuine pre-estimates of damages or are limited to reasonable compensation under S.74 [14][15]. - Forfeiture of security deposit and deduction of 10% penalty require proof of actual damages unless a genuine pre-estimate is shown [12][14]. - The contract’s clause labeling as penalty does not automatically preclude recovery; must satisfy genuine pre-estimate criteria or reasonable compensation [14][15][46]. - Kerala State Electricity Board Ltd. is the successor; predecessor liabilities transfer; survivability of suit against transferee [11]. - The Supreme guidance: Section 74 permits compensation up to the stipulated amount, but only reasonable compensation; where loss is provable, actual loss must be considered [31][46][48]. - Clause 15 (penalty) described as penalty, not genuine pre-estimate; not enforceable beyond actual damages [21][22]. - The appeal dismissed; trial court’s finding that no damages were proven upheld [59]. - Precedent references to Fateh Chand, Maula Bux, Kailash Nath Associates, and BSNL v. Reliance for interpretation of penalties vs. liquidated damages [13][16][21][46].

What is the proper approach to recover unpaid amounts and security deposits in a breach of contract where actual damages are not proven?

What is the status of penalties described as penalties versus genuine pre-estimates of damages under Section 74 of the Indian Contract Act?

What are the rules for forfeiture of security deposits and deductions for damages when actual loss is demonstrable?


Table of Content
1. plaintiff's supply failure and ensuing contract dispute. (Para 1 , 2 , 3 , 4 , 5)
2. court's findings and rulings on deductions by defendant. (Para 6 , 7 , 8)
3. arguments advanced by both parties regarding claims. (Para 9 , 10 , 11)
4. legal principles surrounding penalties and proof of damages. (Para 12 , 13 , 14 , 15 , 16 , 17)
5. court's final reasoning and verdict leading to dismissal. (Para 18 , 19 , 20 , 21 , 22)

JUDGMENT :

P. KRISHNA KUMAR, J.

1. The respondents in this appeal instituted a suit for recovery of money on the basis of a supply contract entered into between them and the appellant herein, the Kerala State Electricity Board. The suit was decreed for Rs.47,63,818/- with interest at 6% per annum from the date of the suit. Aggrieved by the said decree and judgment, the Kerala State Electricity Board Ltd. has preferred this appeal.

2. The parties are hereinafter referred to as they were arrayed in the suit. Pursuant to a tender for the supply of 1,41,000 sets of 4-line cross arms with Clamp, Bolt and Nut (CNB), the defendants (hereinafter referred to as “the defendant”) issued a purchase order dated 05.01.2010 to the plaintiff company, and an agreement was executed between them. As per the delivery schedule under the purchase order, the plaintiff was required to supply 1,41,000 sets of 4-line cross arms with CNB, of which 33,000 sets were to be supplied within 45 days from the date of the purchase order, and the balance at the rate of 36,000 sets every month thereafter. The stipulated period for completion of the supply was 135 days.

3. The plaintiff contended that they supplied a total of 58,927 sets up to 25.10.2011, and thereafter, the defendant issued a letter dated 16.12.2011 (Ext.A16), directing the plaintiff to complete the supply on or before 30.01.2012. At that stage, the plaintiff approached the defendant and represented that, owing to a continuous labour strike in its unit, additional time was required to complete the supply. Upon acceptance of the request, the plaintiff supplied 5,000 sets on 28.01.2012. The plaintiff was again directed to complete the supply on or before 29.02.2012. However, by letter dated 20.04.2012 (Ext.A19), the defendant cancelled the purchase order by terminating the contract.

4. The plaintiff further contended that, towards the supply of 58,927 sets, it was entitled to Rs.1,62,77,108/-, out of which the defendant paid only Rs.1,34,46,034/-. The defendant, by letter dated 13.12.2012 (Ext.A25), claimed that it had sustained loss due to short supply of materials and, accordingly, forfeited the security deposit of Rs.19,46,000/-. The plaintiff also alleged that the defendant illegally deducted Rs.28,19,198/- as penalty. The suit was therefore instituted seeking recovery of the said amounts with interest.

5. The defendant contended that the plaintiff was responsible for the breach of contract and was bound by the conditions contained in the purchase order and the agreement, under which the defendant was entitled to forfeit the security deposit. It was further contended that, in terms of the contract, the defendant was entitled to make deductions in payment up to 10% by invoking the penalty clause and also to encash the bank guarantee furnished by the plaintiff. According to the defendant, upon valid termination of the contract at the risk and cost of the plaintiff and upon making deductions in accordance with the terms of the contract, the plaintiff is not entitled to any amount.

6. It was further contended that the defendant had sustained loss and damage due to the non-supply of materials and was compelled to procure the same through alternative means at higher cost. The defendant also asserted that such loss could not be quantified merely in monetary terms, as the inconvenience and hardship caused to the public at large due to the non-supply of materials was of paramount concern.

7. The evidence in this case consists of the oral testimonies of PW1 and DW1, along with Exts.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top