SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(Raj) 406

IN THE HIGH COURT OF RAJASTHAN
P.K. Lohra, J.
M/s. GVPR-DARA JV 8-2-273/82/A, Plot No. 739-A, Road No. 37, Jubilee Hills, Hyderabad through Power of Attorney Holder - Petitioner
Versus
State of Rajasthan & Ors. - Respondents
Civil Writ Petition Nos. 9188, 9186 of 2015
Decided On : 02-02-2016

Advocates Appeared:
For the Petitioner:M.R. Singhvi, Senior Advocate assisted by Sunil Joshi & S.P. Joshi, Advocates.
For the Respondents:Dr. P.S. Bhati, Additional Advocate General with S.S. Rathore, Advocate.
For Intervenor – Larsen and Toubro Ltd. :M.S. Singhvi, Senior Advocate assisted by V.K. Mathur, Deepak Chandak and Abhishek Mehta, Advocates.
For intervenor – M/s. Megha Engineers & Infrastructure Ltd. :Sanjeet Purohit with Rajat Arora, Advocates.

Headnote:

Civil Procedure Code , 1908 - Order 6 - Rule 2 - Order 6 - Rule 1 - Constitution of India - Articles 21 , 311 , 19 , 14 , 226 , 32 , 298 and 299 - Rajasthan Transparency Public Procurement Act, 2012 - Sections 39 , 2,ii , 7, 14, 18 , 25 , 49 , 25 , 40 and 22 - Rajasthan Transparency in Public Procurement Rules, 2013 - Rules 83 , 79,F , 41 , 39 , 59 , 42 , 38 and 62 - Public Procurement Rules, 2015 - Seeking certain clarifications - Eligibility criteria - Eligibility of Joint Venture to participate in tender process, detailed submissions are made in writ petition pertaining to fulfilling experience criteria with a positive assertion that as both are enlisted as Class AA Contractor, therefore, in terms of Note-10 of NIT, they are required to deposit 0.5% of estimated costs of NIT as earnest money - Requisite certificates about experience which were enclosed with tender document are also placed on record by petitioner - After issuance of advertisement a corrigendum was issued by respondent-Department extending last date for on-line submission of tender - After receipt of tender form of petitioner, third respondent addressed a communication to it seeking certain clarifications - While responding to that letter, petitioner submitted its clarification Annexure-9 - Third respondent vide Annexure-8 solicited clarifications from petitioner on six points upon examination of its technical bid - Most of clarifications sought for were pertaining to first party of Joint Venture - While submitting its clarification, petitioner enclosed bank certificates issued by Andhra Bank and Induslnd Bank - In order to show financial stability, affidavit of authorised signatory of first party is also enclosed besides communication received from Executive Engineer, KNNL, SLIS, Division along with work experience certificate and work experience certificate issued to second party to JV by Executive Engineer, PHED Dn - Petitioner has submitted with emphasis that vide Annexure-9, it has furnished desired clarification and documents to prove its eligibility to participate in tender process and that being so, it harboured a legitimate expectation that its technical bid would be evaluated for declaring responsive to participate for price offer i.e. opening of envelope - However, petitioner was conveyed letter issued by third respondent whereby technical bids of only two bidders were considered responsive for opening of ir envelope B – price offer – Held , Argument of petitioner in this behalf appears to be quite attractive but not of substance - Moreover, in entire pleadings, no motive has been imputed against any officials of respondents - Element of lack of bona fide by respondents is conspicuously missing in considered opinion of this Court - It may be true that in order impugned, detailed reasons are not assigned for declaring technical bid of petitioner non-responsive but then, said order cannot be read and construed in isolation to communication addressed to petitioner - Moreover, if impugned order is tested on touchstone, Court at loss to say that same cannot be categorised as infirm or against mandatory provisions of Act - Object of observance of principles of natural justice is to test fairness of procedure adopted by decision-maker - If fairness is shown by decision-maker to man proceeded against, form, features and fundamentals of such essential processual propriety being conditioned by facts and circumstances of each situation, no breach of natural justice can be complained of - There cannot be two opinions that principles of natural justice are not inflexible and may differ in different circumstances - present one is a contractual matter wherein even upon delving deep into matter, Court has not been able to find out any unfairness in decision making, therefore, by applying limited scope of judicial review, it is not desirable to overstretch principles of natural justice - There is yet another aspect of matter that when only one conclusion is possible, observance of principles of natural justice can be dispensed with in a given case - May it be that impugned order is not a reasoned order but on basis of materials available on record, it is not possible to draw an inference that procuring entity has not examined tender of petitioner for declaring its technical bid non-responsive - That apart, in want of any specific allegation against any of officers of respondents, proceedings undertaken by procuring entity and recording reasons for issuance of impugned order cannot be doubted - This aspect also deserves examination on anvil of lack of eligibility of petitioner to fulfil eligibility criteria in terms of Clause 6,B,1,c of NIT. Therefore, Court unable to concur with petitioner that impugned order is vitiated in want of reasons - Petitioner has submitted an application for taking additional documents on record after conclusion of final arguments and reserving of judgment/order - Learned Additional Advocate General has conceded for taking those documents on record without going into technicalities that after conclusion of arguments when matter is posted for pronouncement of order, there is no hiatus so as to entertain any application or document - Therefore, sans technicalities, Court has made endeavour to examine documents - Endeavour of petitioner to place on record these documents is to persuade this Court that lead partner of petitioner-JV is fulfilling eligibility criteria - Documents are pertaining to NIT floated by Additional Chief Engineer PHED - Eligibility criteria prescribed under NIT issued by Additional Chief Engineer PHED, is different and even otherwise any decision taken by said authority vis-a-vis lead partner of petitioner-JV cannot be cited as a precedent - What consideration has prevailed upon competent authority in that project cannot be made subject-matter of judicial scrutiny in instant petitions and these petitions are required to be examined on basis of material available on record - Therefore, in totality, documents tendered by petitioner by application are of no avail and consequence - Writ petition dismissed

JUDGMENT :

P.K. Lohra, J.

Both these writ petitions are founded on almost identical facts and the questions of law involved therein are also common, therefore, both are heard together and disposed of by this common order.

For convenience, pleadings of rival parties as incorporated in S.B. Civil Writ Petition No. 9188/2015 shall be referred herein.

2. Succinctly stated the facts of the case are that petitioner a Joint Venture Company (for short 'JV') having M/s. GVPR Engineers Limited with its Registered Office at Hyderabad as first party and M/s. DARA Construction, an incorporated company having its Registered Office at Jodhpur as second party entered into a Memorandum of Understanding for Joint Venture with effect from 03.07.2015 (Annex.1). The requisite terms and conditions for joint venture agreement are incorporated in the Memorandum of Understanding. In order to show the relative status of both the parties of JV, it is averred in the writ petition that both are registered as 'AA' Class Contractors with the respondent-Department with first party being registered as 'AA' Class Contractors vide order dated 02.07.2015 and the second party with effect from 03.11.2006 respectively. The renewal of registration of the second party as 'AA' Class Contractor vide order dated 23.04.2015 is also placed on record. Stressing the status and enlistment as 'AA' Class Contractor with the respondent-department of both the partners, a positive assertion is made in the writ petition that JV is fully eligible to participate in the bidding process issued by the respondent department. The third respondent vide its communication dated 21.04.2015 addressed to the Director, Directorate of Information and Public Relation (DIPR), Jaipur requested to arrange for publication/advertisement of NIT-1 & 2/15-16 in one leading regional daily newspaper, two State level leading daily newspaper, two all India level daily newspaper including financial publication and any trade general specialisation of publication of NITs and further requested to upload the soft copy of NIT on the official website www.dipronline.og.

3. Pursuant to the aforesaid order, the respondent-department proceeded to get the above referred NIT published in the newspaper as well as by way of updating it on the website of the department by resorting to Notice Inviting Tender (NIT Procedure) inviting contractors enlisted as 'AA' Class Contractor to participate in the said tender proceedings. The entire procedure pursuant to the NIT was made on-line on the said website and in response to the same, besides the petitioner JV, M/s. L&T Limited, Chennai, M/s. Megha Engineering & Infrastructure Limited, Hyderabad, M/s. NBCC Ltd. and M/s. VPRPL-WABAG-JV submitted the duly filled up form on-line. Thus, in all, five entities participated in the said bidding process. In order to show its participation in the bidding process pursuant to the aforesaid NIT, the petitioner-JV has placed on record its tender document as Annex.5.

4. For showing eligibility of the Joint Venture to participate in the tender process, detailed submissions are made in the writ petition pertaining to fulfilling the experience criteria with a positive assertion that as both are enlisted as Class 'AA' Contractor, therefore, in terms of Note-10 of the NIT, they are required to deposit 0.5% of the estimated costs of NIT as earnest money. The requisite certificates about the experience which were enclosed with the tender document are also placed on record by the petitioner. After issuance of advertisement dated 21.04.2015 a corrigendum was issued by the respondent-Department extending the last date for on-line submission of tender from 15.06.2015 to 06.07.2015. After receipt of the tender form of the petitioner-JV, the third respondent addressed a communication to it on 05.08.2015 (Annex.8) seeking certain clarifications. While responding to th


























































































































































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top