IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
DINESH MEHTA, J.
PMP Infratech Private Limited & Ors. - Petitioners
Versus
Rajasthan State Mines and Minerals Limited, through its Chairman & Ors. - Respondents
S.B. Civil Writ Petition Nos. 200, 416, 1805 of 2024
Decided On : 19-07-2024
CONTRACT LAW - Revival of Terminated Contracts - Rajasthan Transparency in Public Procurement Act, 2010 (RTPP Act) - The court discussed the provisions of the RTPP Act, emphasizing that once a contract is terminated following due process, it cannot be revived by the awardee or any authority not designated as an appellate authority. The court highlighted the importance of transparency and fairness in public procurement, ruling that administrative orders cannot override duly considered decisions regarding contract termination.
Fact of the Case:
The Rajasthan State Mines & Minerals Ltd. (RSMML) awarded a contract to United Coal Carrier (UCC) for loading and transporting limestone. After UCC failed to commence work on time, RSMML terminated the contract and issued a new letter of acceptance to PMP Infratech Pvt. Ltd. (PMP). However, RSMML later kept both the termination and the new contract in abeyance following a telephonic direction from the Chairman, leading to multiple writ petitions challenging this decision.
Finding of the Court:
The court found that the termination of the contract with UCC was valid and that the subsequent administrative order to keep the termination in abeyance was arbitrary and lacked legal authority. The court emphasized that a terminated contract cannot be revived by administrative fiat and that the principles of transparency and fairness must govern public procurement processes.
Issues: 1. Can a contract once cancelled by the awardee be revived? 2. Can the Chairman or any authority not being the Appellate Authority order the revival of a terminated contract? 3. Can the termination of a contract be kept in abeyance by an administrative order?
Ratio Decidendi: The court held that a contract, once terminated following due process, cannot be revived by the awardee or any authority not designated as an appellate authority. The court underscored the necessity for transparency and fairness in public procurement, ruling that administrative orders cannot negate duly considered decisions regarding contract termination.
Final Decision: The writ petition filed by PMP Infratech Pvt. Ltd. was allowed, the order dated 26.12.2023 was quashed, and RSMML was directed to initiate a fresh tender process. The court clarified that it did not adjudicate on the legality of the termination of UCC's contract or the eligibility of PMP.
JUDGMENT :
Dinesh Mehta, J.
1. In these writ petitions, following questions have arisen for consideration of this Court :
(ii) Whether the Chairman or any authority not being the Appellate Authority or the Court can order revival of an already terminated contract?
(iii) Whether by way of an administrative order, the termination of contract can be kept in abeyance?
2. The above questions are different than usual questions and the same have perhaps come up for consideration of this Court for the first time. Before dilating upon these questions, it would be appropriate to unfold the factual canvass, from which these questions have cropped up.
3. The respondent – Rajasthan State Mines & Minerals Ltd. (hereinafter referred to as ‘the RSMML’) is a Public Sector Enterprises of Government of Rajasthan - the State is having pervasive control over it and the Chief Secretary of the State is its Chairman. Being Public Sector Enterprises, the grant of contract by it is governed by an enactment known as Rajasthan Transparency in Public Procurement Act, 2010 (hereinafter referred to as ‘the RTPP Act’).
4. RSMML issued a notice dated 23.03.2023 inviting e-bids from the eligible entities for the contract of “Loading of limestone gitti of various sizes into tippers/dumpers from crusher hopper (s) and/ or different stacks lying at company’s Sanu mines, District Jaisalmer, its transportation from mines to railway siding at Sanu railway station and its unloading, stacking, watch & ward and mechanized loading of limestone gitti into railway wagons using front end loaders etc.” (hereinafter referred to as ‘the Loading & Transportation Contract or ‘the Contract’’).
5. On 30.06.2023, the technical bids were opened and immediately thereafter, financial bids out of the bidders, who were technically found fit were opened. The result of the financial bids were as under:-
(ii) JRL Mining Pvt. Ltd – (hereinafter referred to as ‘JRL’) - L2
(iii) PMP Infratech Pvt. Ltd. (hereinafter referred to as ‘PMP’) - L3
(iv) Adhunik Khanan va Parivahan Theka Sahkari Samiti (hereinafter referred to as ‘Adhunik’) - L4
(v) Shri Karni Traders – L5
6. On 17.07.2023 a letter of acceptance came to be issued in favour of United Coal Carrier (‘United’), which in turn accepted to transport the quantity as per the bid document. To complete the facts, it may be noted that the letter of acceptance was later on amended vide Corrigendum dated 20.07.2023. Subsequently a formal contract (agreement dated 16.08.2023) came to be executed between ‘RSMML’ and ‘UCC’ (through Jai Tanot Mata Mining and Transportation Society Ltd).
7. Though the contractor (UCC) was supposed to commence the work on 17.08.2023 - within 30 days from the date of issuance of Letter of Acceptance, but it could not do so, on account of deteriorated law and order situation (as claimed by UCC). As the facts have emerged, RSMML issued reminders requiring the Contractor ‘UCC’ to commence work inter-alia stating that its established market tie-ups with customers like Steal Authority of India and Tata etc., are adversely affected as they are not able to get the coal and consequently, their sale commitment with them are being breached.
8. Though ‘RSMML’ issued various letters and required the contractor to commence the work, but the work could commence on 08.10.2023. However, since satisfactory quantity was not being lifted/transported, a score of letters were sent and lastly, a final notice dated 15.12.2023 came to be issued propsing action under the relevant clauses of the Contract. When the Company - ‘RSMML’ did not see any improvement, Clause 4.86 of the Contract was invoked and by way of order dated 24.12.2023, the contract was terminated and the contractor was blacklisted from participating in future tenders for a period of three years, as per Clause-5.42 of the contract.
9. Simultaneous wi
Shree Chamundi Mopeds Ltd. vs. Church of South India Trust Association CSI Cinod Secretariat, Madras
Indian Oil Corporation Ltd. vs. Amritsar Gas Service & Ors.
Dipak Babaria & Anr. vs. State of Gujarat & Ors.
Mary vs. State of Kerala & Ors.
Radhakrishna Agarwal & Ors. vs. State of Bihar & Ors.
M.P. Power Management Co. Ltd., Jabalpur vs. Sky Power Southeast Solar India Pvt. Ltd. & Ors.
Speech and Software Tech. (India) Pvt. Ltd. vs. Neos Interactive Ltd.
PSA Mumbai Investments Pte. Ltd. vs. Board of Trustees of the Jawaharlal Nehru Port Trust & Anr.
Rishi Kiran Logistics Pvt. Ltd. vs. Board of Trustees of Kandla Port Trust
Rajasthan Cooperative Dairy Federation Ltd. vs. Maha Laxmi Mingrate Marketing Services Pvt. Ltd.
Afcons Infrastructure Ltd. vs. Nagpur Metro Rail Corp. Ltd. & Anr.
Jagdish Mandal vs. State of Orissa & Ors.
A terminated contract cannot be revived by administrative order, and the principles of transparency and fairness must be upheld in public procurement processes.
A terminated contract cannot be revived by administrative order, and any such action must adhere to principles of transparency and fairness as mandated by public procurement laws.
The court emphasized that public authority's arbitrary termination of a contract without following due procedures violates principles of fairness and justness, meriting judicial intervention.
Public authorities must act fairly and cannot arbitrarily terminate contracts without justification, reinforcing the legitimacy of expectations within public-private partnerships.
The State must act fairly and cannot terminate contracts arbitrarily without providing reasons, even in contractual matters.
The court reinforced that the existence of an arbitration clause limits the scope for judicial intervention in contractual disputes involving the state.
Government can cancel contracts within lawful scope; absence of irreparable injury negates injunction applications.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.