IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
SATYEN VAIDYA, J.
Himachal Pradesh Power Corporation Ltd. - Petitioner
Versus
M/s KSR Infra Structure Pvt. Ltd. - Respondent
Arb. Case No. 4040 of 2013
Decided On : 13-06-2023
Arbitration and Conciliation Act, 1996 - Section 34, 28 (3), 31(3) - Contract - Arbitral award - Patent illegality - Petitioner has taken exception to award by filing objections under Section 34 of Arbitration and Conciliation Act, 1996 - Petitioner has not been able to show that it has insisted for strict proof of documents relied upon by respondent - Para 19.
Finding of the Court :
Respondent had been able to prove its claim by placing on record relevant material - Documents placed on record on behalf of parties have been taken into consideration - On assessment of material on record such finding cannot be said to be perverse - Petitioner has not been able to show that it has insisted for strict proof of documents relied upon by respondent - Similarly findings that four applications by respondent for extension of time remained unattended at end of petitioner cannot be said to be unwarranted - Learned Senior Counsel representing respondent during course of hearing had referred to relevant documents evidencing existence of such fact - Court has not found any material so as to conclude that award was patently illegal.
Result: Petition dismissed.
JUDGMENT :
Satyen Vaidya, J.
Award dated 9.7.2013, passed by learned Arbitrator in the matter of arbitration arising out of Contract Agreement No. SKHEP-51/2007 Dt. 28.3.2008 between the parties in respect of Sawra Kuddu HEP (111MW) located in District Shimla, H.P., is the subject matter of present proceedings. Petitioner has taken exception to aforesaid award by filing objections under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, ‘the A&C Act).
2. The work involved was construction of Main Access Tunnel (MAT) Size 7.50M (Finished) D-shaped 172 Meter Long for underground power house at Snail, Tehsil Jubbal, District Shimla.
3. The claimant (respondent herein) was the successful bidder. The estimated cost of the work was 4,19,38,829/-. Letter of Intent (LOI) was issued in favour of claimant on 29.9.2007. Formal agreement was drawn between the parties on 28.3.2008. The Parwati Valley Power Corporation Ltd. was the owner/employer of the work. However, the Parwati Valley Power Corporation Ltd. was succeeded by Himachal Pradesh Power Corporation Ltd. (petitioner herein) during the course of time.
4. Certain dates relevant to the adjudication of instant petition are as under:-
(i) Period stipulated for completion of work was four months to be reckoned w.e.f. 31.10.2007.
(ii) The petitioner postponed the date to 30.11.2007 for the purpose of commencement of work.
(iii) Site was handed over to the respondent on 31.3.2008.
(iv) The Work had actually commenced on 18.4.2008 after another agency employed by petitioner for carrying out the work at portal had completed its job on 17.4.2008.
(v) Construction power was made available to the respondent on 5.6.2008.
(vi) Work was completed on 6.1.2009.
The request of respondent for extension of time was approved by petitioner in April, 2010.
5. Learned Arbitrator entered into reference on five claims, as under:-
“1. Claim No.1: Release of Rs. 5 lacs wrongly withheld with interest= Rs. 7,12,500/-
2. Claim No.2: De-watering Abnormal increase in quantum provided in BOQ= Rs. 6,80,373/-
3. Claim No.3: Demand Charges- Excess recovered-Refund of Rs. 1,49,906/-.
4. Claim No.4: Compensation towards Price Variation Adjustment= Rs. 67,72,534/-.
5. Claim No.5: compensation towards idle and/or under utilization of resources =Rs. 1,37,57,998/-.”
6. All the above claims were raised by the respondent. Petitioner simply contested the claims of respondent. No counter claim was submitted on behalf of the petitioner.
7. Learned Arbitrator has allowed Claims No. (1), (3) and (5) of the respondent, whereas Claim No. (2) and (4) have been rejected. Against Claim No.1, the learned Arbitrator has held as under :
“Arbitral Tribunal therefore decides and awards Claim No.1 of SOC in favour of Claimants for refund of Rs. 5 lac subject to adjustment of any amount if already paid over and above the deducted amount of liquidated damages which is the matter of reconciliation of record, otherwise full with held amount of Rs. 5 lac be refunded. A simple interest @ 12% per annum from the date of amount of Rs. 5.00 lac was withheld, as per record of measurement book, till actual date of payment within 90 days, and after 90 days of receipt of Award to the actual date of payment on awarded amount @ 15% per annum, is also awarded in favour of the claimant.”
8. Claim No.3 has been allowed in the manner and to the extent as under:-
“Arbitral Tribunal therefore concludes that there is no substance to support defence and there is enough evidence in support of Claim No.3 of the claimant and accordingly Arbitral Tribunal decides and awards in favour of claimant for refund of amount of Rs. 1,49,906/- charged in excess of demand charges of 125 KVA required for the work of MAT by the Claimant.
A simple interest @ 12% per annum on the awarded amount of Rs. 1,49,906/- from the date such amount was deducted, as per record of M.B. till actual date of payment within 90 days, and after 90 days of receipt of award to the actual date of payment @ 15%
Associate Builders vs. Delhi Development Authority
Delhi Airport Metro Express Private Limited vs. Delhi metro Rail Corporation Limited
Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd.
SupremeToday
Court while deciding objections under Section 34 of A & C Act will not review exercise conduct by learned Arbitrator on merits, once it is not found to be without jurisdiction.
The jurisdiction of courts under Sections 34 and 37 of the Arbitration Act is limited to specific legal grounds, and mere disagreement with arbitral findings does not suffice for setting aside an awa....
An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.
The main legal point established in the judgment is the limited scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for th....
The main legal point established in the judgment is the narrow scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and the emphasis on reasonableness, natural justice, and....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
The main legal point established in the judgment is that the court should not interfere with an arbitral award unless the arbitrator's conclusions are arbitrary, capricious, or perverse. The court's ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.