SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(HP) 1227

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
RANJAN SHARMA, J.
M/s S.D. Trading Company – Appellant
Versus
State of H.P. and Another – Respondents
Arbitration Case No. 289 of 2025 
Decided On : 05-09-2025

Advocates Appeared:
For the Appellants : Santosh Kumar, Sumeet Raj Sharma
For the Respondent: Pranay Pratap Singh

Court extends arbitrator's mandate under Section 29A upon sufficient cause like procedural delays and parties' participation, even post-18 months, to prevent defeating arbitration object by technicalities.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 29A(4), (5) and (6) - Extension of time for concluding arbitral proceedings and passing award beyond 18 months - Proceedings to be completed within 12 months from completion of pleadings, extendable by 6 months with consent of parties - Beyond that, court may extend on sufficient cause - Sufficient cause includes procedural delays attributable to respondents and parties' continued participation without objection - Arbitrator's direction to seek extension upheld, mandate extended by court even post-expiry as application keeps mandate alive - Object of expeditious resolution not to be defeated by technicalities. (Paras 3,6,7,8)

(B) Arbitration and Conciliation Act, 1996 - Section 29A - Court while extending time may impose terms, reduce fees for delays, substitute arbitrator if needed - Extension not mechanical, judicial discretion exercised on cause shown - Parties cannot suffer prejudice due to non-conclusion despite multiple hearings and evidence closure. (Paras 7,8)

Facts of the case:
Petition filed seeking extension of sole arbitrator's mandate for completing proceedings and passing award in respect of contract disputes. Arbitrator appointed by court, proceedings commenced post-pleadings, 17 hearings held, claimants' evidence closed, arbitrator directed parties to seek extension due to expiry of time. Respondents conveyed no objection.

Findings of Court:
Arbitrator mandated to complete proceedings and pass award within six months from receipt of judgment; costs made easy.

Issues: Whether sufficient cause exists for extending arbitrator's mandate beyond statutory timelines; effect of parties' participation post-expiry and procedural delays on continuance of proceedings.

Ratio Decidendi: Sufficient cause made out where delays due to procedural aspects and respondents' instance, parties participated without demur, intent of alternative dispute resolution to be fulfilled logically without prejudice by technicalities - Court empowered to extend time, quashing arbitrator's deferral order. Result : Petition allowed.

Table of Content
1. petition seeks extension of arbitrator mandate under section 29a. (Para 1 , 2 , 3 , 4)
2. section 29a mandates 12+6 month timelines; court extends beyond. (Para 5 , 6)
3. supreme court allows extension on sufficient cause shown. (Para 7)
4. sufficient cause: procedural delays, parties' participation, no objections. (Para 8)
5. parties agree; covered by prior court judgments. (Para 9)
6. mandate extended six months to conclude proceedings. (Para 10)

JUDGMENT :

RANJAN SHARMA, J.

1. Instant petition has been filed under Section 29-A (4) (5) and (6) of the ARBITRATION AND CONCILIATION ACT , 1996, seeking the following relief(s):-

“It is, therefore, prayed that the present application may kindly be allowed and the time period for completing the Arbitration proceeding and passing the award in the Arbitration proceeding in respect of work C/o Providing LIS Horticulture Land from Changawati Khad to G.P. Kalbog Nagan and Ram Nagar, Tehsil Kotkhai, Distt Shimla may kindly be ordered to be extended for further period of 6 months, in the interest of law and justice.”

2. Instant petition has been filed under Section 29-A (4) (5) and (6) of the ARBITRATION AND CONCILIATION ACT , 1996, seeking extension of the mandate of Learned Sole Arbitrator, for concluding the arbitral proceedings and passing of the Award, in respect of the contract work “C/o Providing LIS Horticulture Land from Changawati Khad to G.P. Kalbog Nagan and Ram Nagar, Tehsil Kotkhai, District Shimla” awarded by Jal Shakti Vibhag, Himachal Pradesh, vide Award letter dated 07.03.2019 for an amount of Rs. 6,78,53,553/-. Clause 25 of the Agreement provided for referring the disputes to a Sole Arbitrator to be appointed by Engineer-in-Chief/Chief Engineer, Jal Shakti Vibhag.

3. Since some dispute arose, therefore, in order to resolve the same through alternative disputes resolution the petitioner issued notice to the State Authorities on 18.01.2022. Since no action was taken, the petitioner approached this Court, by way of Arb. Case No.112 of 2022, under Section 11(6) of the Act and in terms of the judgment dated 28.10.2022 passed by this Court Shri J.S. Mahantan, District & Sessions Judge (Retd.) was appointed as the Sole Arbitrator. Pursuant thereto, Learned Arbitrator commenced the arbitral proceedings on 23.12.2022 after the completion of pleadings, an application was filed for additional documents and for leading further evidence. The testimony of one of the claimants was recorded and claimant’s evidence was closed on 22.04.2025. As many as 17 hearings were conducted and on 22.04.2025 [Annexure P-2, at page 21] Learned Arbitrator directed the parties to seek extension of time, so as to enable the Arbitrator to conclude the proceedings expeditiously.

4. Upon issuance of notice on 29.08.2025, Mr. Pranay Pratap Singh, Learned Additional Advocate General, appeared for the State Authorities- respondents and placed on record a communication dated 05.09.2025 [Taken on Record], conveying no objection to the prayer for extending the time for concluding the arbitral proceedings.

5. Heard, Mr. Santosh Kumar, Counsel appearing on behalf of petitioner and Mr. Pranay Pratap Singh, Learned Additional Advocate General, for the respondents.

6. Perusal of Section 29A (1) mandates the arbitral tribunal to complete the arbitral proceedings within 12 months from the date of completion of pleadings and this time-line was further extendable by six months with consent of parties. Beyond the period of 18 months, the mandate of the Arbitrator was extendable only by this Court, on an application revealing sufficient cause under Section 29A(4) and (5) of the Act.

7. In terms of the judgment in TATA Sons Pvt. Ltd. (Formerly TATA Sons Ltd.) vs. Siva Industries and Holdings Ltd. and others, 2023 (1) SCALE 793, the mandate of an Arbitrator is liable to be extended by the Court on sufficient cause, being made out, under Section 29A(4) and 29A(5) of the Act, in the following terms:-

“24 The provisions o




Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top