IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
RANJAN SHARMA, J.
M/s S.D. Trading Company – Appellant
Versus
State of H.P. and Another – Respondents
Arbitration Case No. 289 of 2025
Decided On : 05-09-2025
| Table of Content |
|---|
| 1. petition seeks extension of arbitrator mandate under section 29a. (Para 1 , 2 , 3 , 4) |
| 2. section 29a mandates 12+6 month timelines; court extends beyond. (Para 5 , 6) |
| 3. supreme court allows extension on sufficient cause shown. (Para 7) |
| 4. sufficient cause: procedural delays, parties' participation, no objections. (Para 8) |
| 5. parties agree; covered by prior court judgments. (Para 9) |
| 6. mandate extended six months to conclude proceedings. (Para 10) |
JUDGMENT :
RANJAN SHARMA, J.
1. Instant petition has been filed under Section 29-A (4) (5) and (6) of the ARBITRATION AND CONCILIATION ACT , 1996, seeking the following relief(s):-
“It is, therefore, prayed that the present application may kindly be allowed and the time period for completing the Arbitration proceeding and passing the award in the Arbitration proceeding in respect of work C/o Providing LIS Horticulture Land from Changawati Khad to G.P. Kalbog Nagan and Ram Nagar, Tehsil Kotkhai, Distt Shimla may kindly be ordered to be extended for further period of 6 months, in the interest of law and justice.”
2. Instant petition has been filed under Section 29-A (4) (5) and (6) of the ARBITRATION AND CONCILIATION ACT , 1996, seeking extension of the mandate of Learned Sole Arbitrator, for concluding the arbitral proceedings and passing of the Award, in respect of the contract work “C/o Providing LIS Horticulture Land from Changawati Khad to G.P. Kalbog Nagan and Ram Nagar, Tehsil Kotkhai, District Shimla” awarded by Jal Shakti Vibhag, Himachal Pradesh, vide Award letter dated 07.03.2019 for an amount of Rs. 6,78,53,553/-. Clause 25 of the Agreement provided for referring the disputes to a Sole Arbitrator to be appointed by Engineer-in-Chief/Chief Engineer, Jal Shakti Vibhag.
3. Since some dispute arose, therefore, in order to resolve the same through alternative disputes resolution the petitioner issued notice to the State Authorities on 18.01.2022. Since no action was taken, the petitioner approached this Court, by way of Arb. Case No.112 of 2022, under Section 11(6) of the Act and in terms of the judgment dated 28.10.2022 passed by this Court Shri J.S. Mahantan, District & Sessions Judge (Retd.) was appointed as the Sole Arbitrator. Pursuant thereto, Learned Arbitrator commenced the arbitral proceedings on 23.12.2022 after the completion of pleadings, an application was filed for additional documents and for leading further evidence. The testimony of one of the claimants was recorded and claimant’s evidence was closed on 22.04.2025. As many as 17 hearings were conducted and on 22.04.2025 [Annexure P-2, at page 21] Learned Arbitrator directed the parties to seek extension of time, so as to enable the Arbitrator to conclude the proceedings expeditiously.
4. Upon issuance of notice on 29.08.2025, Mr. Pranay Pratap Singh, Learned Additional Advocate General, appeared for the State Authorities- respondents and placed on record a communication dated 05.09.2025 [Taken on Record], conveying no objection to the prayer for extending the time for concluding the arbitral proceedings.
5. Heard, Mr. Santosh Kumar, Counsel appearing on behalf of petitioner and Mr. Pranay Pratap Singh, Learned Additional Advocate General, for the respondents.
6. Perusal of Section 29A (1) mandates the arbitral tribunal to complete the arbitral proceedings within 12 months from the date of completion of pleadings and this time-line was further extendable by six months with consent of parties. Beyond the period of 18 months, the mandate of the Arbitrator was extendable only by this Court, on an application revealing sufficient cause under Section 29A(4) and (5) of the Act.
7. In terms of the judgment in TATA Sons Pvt. Ltd. (Formerly TATA Sons Ltd.) vs. Siva Industries and Holdings Ltd. and others, 2023 (1) SCALE 793, the mandate of an Arbitrator is liable to be extended by the Court on sufficient cause, being made out, under Section 29A(4) and 29A(5) of the Act, in the following terms:-
“24 The provisions o
TATA Sons Pvt. Ltd. (Formerly TATA Sons Ltd.) vs. Siva Industries and Holdings Ltd. and others
Court extends arbitrator's mandate under Section 29A upon sufficient cause like procedural delays and parties' participation, even post-18 months, to prevent defeating arbitration object by technical....
Court extends arbitrator's mandate under Section 29A(5) post-expiry and termination upon sufficient cause, quashing abeyance where delays due to respondent and administration, prioritizing efficient ....
Court may extend arbitrator's mandate under Section 29A(4),(5) post-termination for sufficient cause not attributable to petitioners, prioritizing pragmatic and effective arbitral conclusion.
Court extends arbitrator's mandate post-termination under Section 29A(5) for sufficient cause like procedural and administrative delays not attributable to petitioner, ensuring practical, expeditious....
Court extends arbitrator mandate post-expiry under Sec 29A(4),(5) on sufficient cause like advanced proceedings, non-attributable delay, ensuring logical conclusion without petitioner fault.
Court extends arbitrator's mandate under Section 29A(5) for sufficient cause including clerical errors, procedural delays, pandemic effects not attributable to parties, ensuring logical conclusion of....
The court ruled that arbitration mandates may be extended due to administrative delays not attributable to the parties, affirming the need for the timely resolution of disputes while preventing preju....
The court ruled that delays in arbitral proceedings due to administrative reasons and the COVID-19 pandemic justified extending the Arbitrator's mandate under Section 29A of the Arbitration and Conci....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.