SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Mad) 2224

IN THE HIGH COURT OF JUDICATURE AT MADRAS
SANJIB BANERJEE, P.D. AUDIKESAVALU, JJ.
M/s. NAPC Limited, Royapettah – Appellant
Versus
The Superintending Engineer, National Highways, Chennai & Another – Respondents
OSA Nos. 188 & 189 of 2019
Decided on : 30-09-2021

Advocates:
Advocate Appeared:
For the Appellant:Satish Parasaran, Senior Counsel, Arun C. Mohan, Advocate.
For the Respondents: Edwin Prabhakar, Special Government Pleader (Civil Side).

Headnote:

Arbitration and Conciliation Act, 1996 - Section 34, Section 21, Section 11(6) - Arbitration - Appointment - Appeals filed against the common order on the file of original side of this court by upholding the arbitration award published for implementation - Whether appeal is maintainable - Held, By the same yardstick, the arbitrator was justified in rejecting the claim initially made by the contractor, since the cause of action in respect thereof arose at a point of time more than three years when the arbitral proceedings are deemed to have commenced - For the reasons aforesaid, the judgment and order impugned cannot be accepted and the same are hereby set aside - Arbitral award is restored - It is recorded that the challenge to the award made by the contractor, to the extent the further claim made therein was rejected, has been expressly abandoned at this appellate stage - Appeal dismissed

JUDGMENT :

Sanjib Banerjee, J.

(Prayer: Appeals filed against the common order dated 10.07.2019 in OP Nos.881 and 899 of 2018 on the file of original side of this court by upholding the arbitration award published for implementation.)

The contractor is the appellant questioning an order passed under Section 34 of the Arbitration and Conciliation Act, 1996 setting aside an award on the ground of lack of authority and limitation. The appellant had partially succeeded before the arbitrator and the award provided for a sum of slightly over Rs.4.21 crore, inclusive of interest till the date of the award.

2. The contract was for the construction of a two-lane by-pass around Kanchipuram in the Villupuram Division connecting NH4 and the Kancheepuram – Vandavasi Road. It included the construction of a major bridge. The contract was, as accepted by the parties, for a period of 24 months from April 18, 2010. A first lot of claim was made by the contractor on January 9, 2012 for the period up to October, 2011, which was rejected by the respondent employer on March 9, 2012. The tenure under the contract was extended on or about April 17, 2012 for a period of seven months. On July 27, 2012, a second lot of claim came to be made by the contractor for the period November, 2011 to May, 2012. Again, the employer rejected the claim on September 7, 2012. On or about October 16, 2012, the tenure was extended for a further six months. On January 30, 2014, the third lot of claim was made by the contractor. There is no dispute that the demand for arbitration was made by the contractor on August 14, 2015. Under Section 21 of the Act of 1996, the commencement of arbitration happens upon a demand for an arbitral reference made by one party being received by the other party. Despite the demand for an arbitral reference in accordance with the arbitration clause found at clause 50 of the agreement between the parties which is dated April 19, 2010, the contractor was constrained to request the Chief Justice’s Designate under Section 11(6) of the Act of 1996 to constitute an arbitral tribunal. A sole arbitrator was appointed.

3. Unfortunately, the arbitrator has been quite unnecessarily impleaded as a party to the appeal since the arbitrator was also impleaded before the arbitration court. It is completely unnecessary for arbitrators to be arrayed as party unless personal allegations are made and the arbitrator is required to answer such allegations. Despite several orders in such regard, the unsavory practice continues in this court, of needlessly impleading arbitrators.

4. There is no dispute that the request under Section 11(6) of the Act of 1996 was prosecuted upon notice to the employer. At such point of time, the employer did not step up to suggest that there was no arbitration agreement between the parties or that the disputes raised by the contractor were not covered by any arbitration agreement. It was only upon the arbitrator appointed by the Chief Justice’s Designate taking up the reference that an application was moved under Section 16 of the Act of 1996 questioning the authority of the arbitrator to proceed with the reference on the ground that a particular government order of 1990 vintage issued by the Public Works Department precluded arbitral references where the value of the claim was in excess of Rs.5 lakh. Though the employer asserted the application of G.O.Ms.No.1545 dated July 26, 1990 before the arbitrator and seeks to rely on such notification to sustain the judgment and order impugned herein dated July 10, 2010, it does not appear that the relevant notification was referred to, even indirectly, in the agreement of April 19, 2020.

5. According to the respondent employer, the agreement between the parties makes a reference to "PS to SSRB" at clause 4.2(c). Clause 4.2 covers the governing law and the heading of such clause is "Laws governing contract, observance of laws". Sub-clause (c) and the reference to "PS to SSRB" implies the set of guide

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top