IN THE HIGH COURT OF JUDICATURE AT MADRAS
T. RAJA, D. BHARATHA CHAKRAVARTHY, JJ.
M/s. Transtonnelstroy – Afcons (JV) & Ors. - Appellants
Versus
M/s. Chennai Metro Rail Ltd. & Ors. - Respondents
O.S.A.(CAD) Nos.147 of 2021, 85 and 79 of 2022 and 148 of 2021 and C.M.P. Nos.21000, 21003, 21008 and 21010 of 2021
Decided On : 01-02-2023
The Court held that the Arbitral Tribunal erred in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case. The Court further held that the observations / directions of the learned Single Judge in paragraph No.22 of the impugned judgment, enabling the parties to raise the issue once again before the Tribunals in pending Arbitrations, is unsustainable.
Fact of the Case:
Chennai Metro Rail Limited (CMRL) is a company incorporated under the Companies Act, 2013 for the purpose of creating, designing, establishing, maintaining, and running metro rail in and around the city of Chennai. CMRL issued notice inviting tenders on 21.04.2010 for the works of design and construction of five underground stations and associated tunnel works between Washermanpet to May Day Park (5.6 kms, four stations) and Chennai Central to Egmore (1.7 kms, two stations) where Chennai Central is the common station in both the routes. This tender is termed as 'UAA-01' package of the Chennai Metro Rail Project under Phase - I. TTA-JV emerged as the successful bidder for a total project consideration of Rs.1566,81,00,000/- (Rupees One Thousand Five Hundred and Sixty Six Crores and Eighty One Lakh only). The contract is a Design-Build Lumpsum Turnkey, governed by F.I.D.I.C (Federation Internationale Des Ingenieurs - Conseils) Part - 1 of 1995 Edition, the General Conditions of Contract (GCC) modified via Conditions of Particular Application (CPA), the Employer's Requirements on design, construction, Interface Management, etc., Outline Design Specifications including Tender Documents, etc. CMRL issued another notice inviting tenders on 21.04.2010 for the works of design and construction of four underground stations between Shenoy Nagar (SSN) and Thirumangalam Ramp (2TI) and Associated Tunnels in Corridor 2. This tender is termed as 'UAA-05' package of the Chennai Metro Rail Project under Phase – I. TTA-JV emerged as the successful bidder for a total project consideration of Rs.1030,99,50,000/- (Rupees One Thousand Thirty Crores Ninety Nine Lakhs and Fifty Thousand only). The contract is a Design-Build Lumpsum Turnkey, governed by F.I.D.I.C (Federation Internationale Des Ingenieurs - Conseils) Part - 1 of 1995 Edition, the General Conditions of Contract (GCC) modified via Conditions of Particular Application (CPA), the Employer's Requirements on design, construction, Interface Management, etc., Outline Design Specifications including Tender Documents, etc.
Finding of the Court:
The Court found that the Arbitral Tribunal erred in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case. The Court further held that the observations / directions of the learned Single Judge in paragraph No.22 of the impugned judgment, enabling the parties to raise the issue once again before the Tribunals in pending Arbitrations, is unsustainable.
Issues: Whether the course adopted by the Arbitral Tribunal, in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case?
Ratio Decidendi: The Court held that the Arbitral Tribunal erred in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case. The Court further held that the observations / directions of the learned Single Judge in paragraph No.22 of the impugned judgment, enabling the parties to raise the issue once again before the Tribunals in pending Arbitrations, is unsustainable.
Final Decision: The Court held that the Arbitral Tribunal erred in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case. The Court further held that the observations / directions of the learned Single Judge in paragraph No.22 of the impugned judgment, enabling the parties to raise the issue once again before the Tribunals in pending Arbitrations, is unsustainable.
JUDGMENT :
D. Bharatha Chakravarthy, J.
[Prayer in O.S.A(CAD).No.147 of 2021 : Original Side Appeal - Commercial Appellate Division filed under Section 13(1A) of Commercial Courts Act of 2015 and Order XXXVII Rule 1 of the Original Side Rules of the High Court of Madras, 1956 read with Section 37 of the Arbitration and Conciliation Act, 1996 to allow this appeal and set aside the order of the learned Single Judge, dated 28.10.2021, consequently, confirming the detailed, well-reasoned unanimous Arbitral Award, dated 07.05.2021 passed by the Tribunal.
Prayer in O.S.A(CAD).No.85 of 2022 : Original Side Appeal - Commercial Appellate Division filed under Section 13(1A) of Commercial Courts Act of 2015 and Section 37(2)(c) of the Arbitration and Conciliation Act, 1996 to allow this appeal and set aside the impugned common order, dated 28.10.2021 passed by the Court in Arbitration O.P. (Comm.Div.) No.96 of 2021, insofar as it grants liberty to the respondent to prove its claims for extension of time (EOT) under Claim Nos.1 and 2 in the existing cost related arbitration proceedings.
Prayer in O.S.A(CAD).No.79 of 2022 : Original Side Appeal - Commercial Appellate Division filed under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 and Section 13(1A) of Commercial Courts Act of 2015 to allow this appeal and set aside the impugned common order, dated 28.10.2021 passed by the Court in Arbitration O.P. (Comm.Div.) No.97 of 2021, insofar as it grants liberty to the respondent to prove its claims for extension of time (EOT) under Claim Nos.1 and 2 in the existing cost related arbitration proceedings.
Prayer in O.S.A(CAD).No.148 of 2021 : Original Side Appeal - Commercial Appellate Division filed under Section 13(1A) of Commercial Courts Act of 2015 and Order XXXVII Rule 1 of the Original Side Rules of the High Court of Madras, 1956 read with Section 37 of the Arbitration and Conciliation Act, 1996 to allow this appeal and set aside the order of the learned Single Judge, dated 28.10.2021, consequently, confirming the detailed, well-reasoned unanimous Arbitral Award, dated 01.06.2021 passed by the Tribunal.]
A. The Question :
1. The primary question entreats answer in these appeals is “Whether the course adopted by the Arbitral Tribunal, in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well after reserving orders and thereafter technically analysing the same on its own and consequently awarding the claim, is bad in law on the ground that the respondent was otherwise unable to present their case?"
B. The Appeals :
2. These four appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996 read with Clause 15 of the Letters Patent, are between the same parties arising out of two Arbitral Awards in respect of two contracts. Since all the appeals have raised common questions, they are taken up together and disposed off by this common judgment.
C. The Contracts & The Dispute :
3. Chennai Metro Rail Limited (hereinafter referred to as 'CMRL') is a company incorporated under the Companies Act, 2013 for the purpose of creating, designing, establishing, maintaining, and running metro rail in and around the city of Chennai.
3.1. The respondent is an unincorporated joint venture of two companies namely, Transtonnelstroy Limited and Afcons Infrastructure Limited (hereinafter referred to as 'TTA-JV'). They are contractors undertaking design and construction works.
3.2. In these matters, we are concerned with the disputes arising out of the execution of two contracts, termed as UAA-01 and UAA-05. To implement the project effectively, CMRL also appointed a consultant called as M/s.EMBYE (a consortium of consultants) consisting of five members namely, (i) EGIS Rail SA; (ii) EGIS India Consulting Engineers Pvt. Ltd. India; (iii)
Sohan Lal Gupta (Dead) through LRs. and Ors. Vs. Asha Devi Gupta (Smt) and Ors.
State of Madras, etc. Vs. A. Habibur Rehman and Sons, etc.
K.P. Poulose Vs. State of Kerala and Anr.
Renusagar Power Co. Ltd. v. General Electric Co.
Jugal Kishore Prabhatilal Sharma and Ors. Vs. Vijayendra Prabhatilal Sharma and Anr.
Cauvery Coffee Traders, Mangalore Vs. Hornor Resources (International) Company Limited
Associate Builders Vs. Delhi Development Authority
Kinnari Mullick and Anr. Vs. Ghanshyam Das Damani
Vijay Karia and Ors. Vs. Prysmian Cavi E Sistemi Srl and Ors.
Centrotrade Minerals and Metals Inc. Vs. Hindustan Copper Limited
Delhi Airport Metro Express Private Limited Vs. Delhi Metro Rail Corporation Limited
State of Chhattisgarh and Anr. Vs. Sal Udyog Private Limited
The Arbitral Tribunal erred in calling for additional materials being the data entered into by the parties during the execution of the contract and the relevant software, from the claimant, well afte....
Scanned signed copy of the award/order of the Arbitral Tribunal to the parties would be a valid delivery as envisaged under Section 31(5) of the Arbitration and Conciliation Act, 1996.
The main legal point established in the judgment is the limited scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.