SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Mad) 633

HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
Arkay Energy (Rameswarm) Limited, Rep. by its Authorised Signatory T.S. Das - Appellant
Versus
TIDEL Park Limited, Rep. by its Managing Director, B. Elangovan - Respondent
Arb.O.P. No. 274 of 2021 & A. No. 4623 of 2021
Decided On : 23-03-2023

Advocates appeared:
For the Petitioner:M/s. Anirudh Krishnan, K, Ramkishore, Varun Venkatesan, Advocates. For the Respondent:M. Jose John, M. Narendran, Lilly Francis for M/s. King and Partridge, Advocates.

The court upheld the Arbitral Tribunal's decision, emphasizing that the supply obligation was continuous, not successive, and any error in interpreting or applying provisions of the Limitation Act did not contravene the fundamental policy of Indian law.

Headnote:

Limitation - Arbitration - Arbitration and Conciliation Act, 1996 - State of Gujarat v. Kothari and Associates - M.D.Enterprise v. Whirlpool of India Ltd. - Associate Builders v. Delhi Development Authority - Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India - Arkay Energy (Rameswarm) Limited - TIDEL Park Limited - Section 34 of the Arbitration Act

Fact of the Case:

The petitioner, Arkay Energy (Rameswarm) Limited, entered into agreements with TIDEL Park Limited for supply of electricity. Disputes arose, and the matter was referred to arbitration. The Arbitral Tribunal awarded a sum to TIDEL Park, which Arkay challenged under Section 34 of the Arbitration Act.

Finding of the Court:

The court dismissed the petition, upholding the Arbitral Tribunal's decision. The court found that the supply obligation was continuous, not successive, and declined to apply the judgment in State of Gujarat. The court also held that any error in interpreting or applying provisions of the Limitation Act did not contravene the fundamental policy of Indian law. The court further concluded that the obligations were not reciprocal, and the contentions on waiver and course of dealing did not warrant interference with the Award.

Issues: Interpretation of supply obligation, application of the Limitation Act, consideration of Section 54 of the Contract Act, and waiver and course of dealing.

Ratio Decidendi: The supply obligation was continuous, not successive, and the judgment in State of Gujarat was distinguishable. Any error in interpreting or applying provisions of the Limitation Act did not contravene the fundamental policy of Indian law. The obligations were not reciprocal, and the contentions on waiver and course of dealing did not warrant interference with the Award.

Final Decision: The petition was dismissed, and the parties were ordered to bear their own costs.

JUDGMENT

(Prayer: This Arbitration Original Petition has been filed to set aside the impugned award dated 07.01.2021 and additional award dated 05.03.2021.)

The petitioner, Arkay Energy (Rameswarm) Limited (Arkay), was the respondent before the Arbitral Tribunal. Arkay is a gas based electricity generation company. After obtaining permission from the Tamil Nadu Electricity Board (TNEB) for supply of electricity to third party consumers, Arkay entered into two separate agreements [a shareholders agreement (SHA) and a power supply agreement(PSA)] with the respondent, TIDEL Park Limited (TIDEL Park), on 10.11.2005. Pursuant thereto, disputes arose between Arkay and TIDEL Park with regard to alleged breach of the PSA. Eventually, the PSA was terminated by TIDEL Park on 19.01.2011.

2. After such termination, initially, TIDEL Park initiated civil proceedings before this Court (C.S.No.389 of 2011) in relation to disputes arising both under the SHA and PSA. Arkay filed an application under Section 8 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act) for reference of disputes to arbitration in view of the arbitration clause in the PSA. The application under Section 8 was allowed. The order was carried in appeal by TIDEL Park before the Division Bench but the Division Bench dismissed the appeal. In these circumstances, after issuing a notice under Section 21 of the Arbitration Act, the Arbitral Tribunal was constituted.

3. Before the Arbitral Tribunal, TIDEL Park claimed a sum of Rs.4,85,32,773/- towards short supply and non-supply of power by Arkay. The said claim was made by computing the difference between the TNEB tariff and the rate at which Arkay was required to supply power. Interest was claimed on the above amount at the rate of 13% per annum. Arkay made a counter claim for a sum of Rs.23,66,140/- towards unpaid dues and interest thereon at the rate of 13% per annum from the date the amount became payable until realization. Upon examining the pleadings and material documents, the Arbitral Tribunal framed 11 issues. TIDEL Park adduced evidence by examining Mr.N.R.S.Ganesh Babu, General Manager (Finance) as CW-1 and by exhibiting 60 documents as Exs.C1-C60. Arkay examined Mr.T.S.Das, Vice-President (Commercial), as RW-1 and exhibited 57 documents as Exs.R1-R57. By a majority award dated 07.01.2021 and additional award dated 05.03.2021, the principal claim of Rs.4,85,32,773/- was allowed with interest thereon at the rate of 13% per annum from 11.09.2017 until realization. In addition, the petitioner was directed to pay a sum of Rs.66,10,000/- as costs. By the minority award, all the claims and counter claims were held to be barred by limitation. By this petition, Arkay challenges the above mentioned awards under Section 34 of the Arbitration Act. For ease of reference, the majority award, including the additional award, is referred to as the Award in this order.

4. Oral arguments on behalf of Arkay were advanced by Mr.Anirudh Krishnan, learned counsel; and on behalf of TIDEL Park by Mr.Jose John, learned counsel. Written arguments were also provided by the parties.

5. The first contention of Mr.Anirudh Krishnan was that the claims are barred by limitation because both the supply and payment obligations were monthly and, therefore, limitation for non-supply and short supply should be computed from the end of the relevant month. Learned counsel submitted that the PSA provided for supply of power on monthly basis by Arkay to TIDEL Park. In this connection, he referred to the definitions of “Billing Period” and “Billing Month” in Article I and to Article – II.1.3 which stipulates that the captive consumer shall consume the monthly guaranteed energy in a billing month. He also referred to Article – III.1.2 and pointed out that TIDEL Park was required to pay Arkay on monthly basis for the monthly delivered energy at the TNEB''s prevailing tariff less 10% on TNEB''s prevailing energy charges. By drawing reference to the stateme

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top