SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Mad) 2964

IN THE HIGH COURT OF JUDICATURE AT MADRAS
K.R.Shriram, C.J., Mohammed Shaffiq, J.
Chennai Metropolitan Water Supply & Sewerage Board - Appellant
Versus
SPML Infra Limited and ors. – Respondents
OSA No.20 of 2019
Decided On : 21-03-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr.D.Balaraman
For the Respondent: Mr.M.S.Krishnan, Senior Counsel, for Mr.K.Ashok Kumar

The court upheld the arbitral award, affirming that arbitrators are the ultimate masters of evidence and that interference is only permissible in cases of arbitrariness or capriciousness.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Appellant contested majority award regarding additional work due to post-contract changes in pipeline alignment - Majority award directed payment of Rs.13,72,38,571/- with interest - Appellant's challenge primarily focused on Claim No.2, which involved increased excavation depth and pipeline length under the road. (Paras 1, 11, 12, 18, 24)

(B) Legal principles - Arbitrators are the ultimate masters of evidence; interference is limited to cases of arbitrariness or capriciousness - The court does not act as an appellate body in reviewing arbitral awards. (Paras 18, 22)

Facts of the case:
Disputes arose from a construction contract for a pipeline, leading to a majority award for additional payments due to changes in alignment and excavation depth. (Paras 2-6)

Findings of Court:
The court upheld the majority award, confirming the contractor's entitlement to payment for additional work due to significant post-contract changes. (Paras 18-24)

Issues: The main issue was whether the contractor was entitled to additional payment for changes in the scope of work due to post-contractual alterations. (Paras 11, 12)

Ratio Decidendi: The court ruled that the arbitrators' findings were not arbitrary or capricious, affirming the principle that the arbitrators are the ultimate authority on evidence and contract interpretation. (Paras 18, 22)

Result: Appeal dismissed, with costs awarded to the respondent.

JUDGMENT :

K.R.Shriram, C.J.

Appellant is unhappy with an order delivered on 14.06.2017 by learned Single Judge of this Court under Section 34 of the Arbitration and Conciliation Act, 1996 (the Act). By the said petition under Section 34 of the Act, appellant challenged the majority award dated 15.12.2007.

2. A tender was floated by appellant in October, 1997, inviting bids for construction of permeate conveyance pipeline. Respondent No.1 was the successful bidder and came to be appointed as contractor, pursuant to a contract dated 26.11.1998. The contract executed comprised of both Rupee as well as Japanese Yen component. Value of the contract in Indian rupees was INR 18,05,30,000/- while in Japanese Yen was fixed at JPY 51,90,42,904/-

3. The scope of work of the contract broadly obliged respondent No.1 to:

a) construct pumping station and emergency station at Koyambedu;

b) to supply and install electro mechanical and instrumentation equipment; and

c) to supply and lay down 1700m of ductile iron pipeline with all accessories of the requisite diameter.

4. Disputes arose between the parties as regards post-contractual changes brought about in the alignment of the pipeline, which respondent No.1 was obliged to lay down in terms of the contract.

5. The contract envisaged that only a part of the pipeline within the range of 10-15% would be laid underground and that a major part of the pipeline would have to be laid overground. It appears that due to post- contractual changes, not only the actual length of the pipeline which had to be laid got altered, but also the length of the pipeline which had to be laid underground also increased. In sum, while the actual length of the pipeline which had to be laid got changed from 17945m to 11887.2 m, the portion which had to be laid underground increased from 1759m to 5637m. In effect, the increase in that part of the pipeline which had to be laid below the road surface, in percentage terms increased from 10-15% to 47.42%.

6. Besides this, the main average depth of excavation evidently increased from 2.68m to 3.16m. In real terms, the increase was approximately 0.5m; while in percentage terms, the average depth of excavation increased by 18.65%. It is these post-contractual changes which made respondent No.1 to lodge its claim for recovery of monies under various heads.

7. As it appears from the majority award, respondent No.1 lodged 16 claims, which included claim for interest; while appellant lodged a counter- claim for the alleged delay committed by respondent No.1 in the execution of the contract. In the counter-claim, appellant claimed liquidated damages of 10% of the contract price.

8. As per the majority award, it contained 22 sub-heads under Claim- 1. Out of the 22 sub-heads, two sub-heads were rejected. Besides four other claims were also rejected.

9. In all, majority award directed payment of a sum of Rs.13,72,38,571/- to respondent No.1 with interest @12% per annum from 01.09.2003 till the date of payment. The award also provided that if the money as awarded was not paid within three months, respondent No.1 would be entitled to a further interest at the rate of 15% per annum till the date of actual payment of the amount so awarded. The parties were directed to bear their own costs.

10. Insofar as the minority award was concerned, the contractor was awarded Rs.1,54,57,574/- towards certain heads of claim. In addition, interest at the rate of 8% per annum for a period between August, 2003 and December, 2007 was also awarded and the interest is quantified at about Rs.54,61,676/-. The minority award also directed further interest at the rate of 6% per annum, if payment as ordered was not made on or before December, 2007. Even in the minority award, Board's counter-claim for liquidated damages has been rejected.

11. Appellant filed its Section 34 petition raising very broad grounds to assail the award. Appellant's challenge primarily was confined to claim Nos.2, 11 and 12. As regards Claim Nos.11 and

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top