SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(UK) 486

IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
Manoj Kumar Tiwari, Vivek Bharti Sharma, JJ.
State of Uttarakhand & Others - Appellants
Versus
M/s Hillways Construction Company Pvt. Ltd. - Respondent
Appeal from Order No. 127 of 2021
Decided On : 12-12-2023

Advocates:
Advocate Appeared:
For the Appellant : Mr. P.C. Bisht, Additional CSC
For the Respondent:Mr. Siddhartha Singh, Advocate

The main legal point established in the judgment is that the limitation period for challenging an award under Section 34(3) of the Arbitration and Conciliation Act is strict and cannot be extended beyond the additional 30 days, as prescribed by the Act.

Headnote:

Arbitration and Conciliation Act - Delay in Filing Application - Section 34 of the Arbitration and Conciliation Act, 1996 - 34(3)

Fact of the Case:

The appellant's application under Section 34 of the Arbitration and Conciliation Act, 1996 was dismissed by the Commercial Court, Dehradun on the ground of delay. The appellant had earlier filed a similar application before the District Judge, New Tehri, which was dismissed as not pressed. Subsequently, the appellants filed an application seeking restoration of the previous application, which was also rejected.

Finding of the Court:

The Commercial Court dismissed the application on the ground of delay, considering the time spent by the appellant in pursuing the remedy before the District Judge, Tehri Garhwal. The court held that even excluding the time spent before the District Judge, the application was beyond the prescribed time limit.

Issues: The main issue was the delay in filing the application under Section 34 of the Act and whether the delay could be condoned.

Ratio Decidendi: The court relied on Section 34(3) of the Arbitration and Conciliation Act, which prescribes a three-month limitation period for challenging an award, extendable by a further 30 days in appropriate cases. The court emphasized that the provision does not allow for extension beyond the additional 30 days.

Final Decision: The court found no fault in the decision of the Commercial Court and dismissed the appeal.

JUDGMENT :

Manoj Kumar Tiwari, J.

This appeal is directed against judgment and order dated 10.2.2021, passed by Commercial Court, Dehradun in Miscellaneous Case No. 42 of 2020. By the said judgment, application filed by the appellants under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, “the Act”) was dismissed on the ground of delay.

2. It is not in dispute that the appellant had earlier filed application under Section 34 of the Act before District Judge, New Tehri challenging the award dated 28/30.5.2018, which was dismissed as not pressed on 3.7.2019. Subsequently, appellants filed application before District Judge, New Tehri seeking restoration of the application under Section 34 of the Act; in the meantime, Commercial Court was established at Dehradun and the application seeking restoration of proceedings under Section 34 of the Act was transferred to Commercial Court, Dehradun; Commercial Court, Dehradun rejected the said application vide order dated 12.12.2019 and the said order was challenged by the appellants in Appeal from Order No. 42 of 2020, which was disposed of by Division Bench of this Court vide order dated 18.2.2020. Para 7 and 8 of the said order are extracted below:

    “7. At this stage, however, the learned counsel for the respondent Construction Company, very fairly submits that he has no objection if the State Government moves a fresh application for setting aside the award along with the delay condonation application before the Commercial Court at Dehradun.

8. In view thereof, and on consideration of the fact that the application for setting aside the award which has also been filed by the Construction Company is already pending before the court below, we dispose the present appeal with a direction to the State Government/appellant to move a fresh application before the Commercial Court at Dehradun, which shall be considered by the court in the light of our above observation.”

3. In terms of the liberty granted by Division Bench of this Court in A.O. No. 42 of 2020, appellants moved fresh application under Section 34 of the Act before the Commercial Court, Dehradun, which was registered as Miscellaneous Case No. 42 of 2020. Learned Commercial Court dismissed the said application on the ground of delay vide order dated 10.2.2021, which is under challenge in this appeal.

4. Learned Commercial Court considered and discussed the matter in great detail. Perusal of para 12 of the impugned order reveals that learned Commercial Court has factored in the time spent by the appellant while pursuing the remedy before the District Judge, Tehri Garhwal and held that even if the time spent before District Judge, Tehri Garhwal is excluded, then also the application filed by the appellant is beyond time.

5. In our considered opinion, the view taken by the learned Commercial Court cannot be faulted. Arbitration and Conciliation Act, 1996 is a self contained code. Section 34(3) of the Act, which prescribes the period of limitation for challenging an award under Section 34 of the Act, reads as under:

    “34. Application for setting aside arbitral award.—

(1)……

(2)…..

(3) An application for setting aside may not be made after-three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under Section 33, from the date on which that request had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.”

6. Thus, from perusal of provision contained under Section 34(3) of the Act, it is quite apparent that the period of limitation prescribed for challenging an award is three months, which can be extended in appropriate cases for a further period of 30 days. The expression “but not thereafter” in the proviso

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top