SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(MP) 266

IN THE HIGH COURT OF MADHYA PRADESH (JABALPUR BENCH)
SUBODH ABHYANKAR, J.
Asha Jain - Appellant
Versus
Union of India - Respondent
Arbitration Case No. 78 of 2019
Decided On : 24-02-2021

Advocates Appeared:
For the Appellant : Satish Agrawal, Learned Counsel.
For the Respondents: Atul Choudhary, Learned Counsel.

The main legal point established in the judgment is that parties may waive the applicability of Section 12 (5) of the Arbitration & Conciliation Act, 1996 by their conduct, and the appointment of an Arbitrator by the respondent was held to be valid based on the applicant's conduct.

Headnote:

Arbitration - Appointment of Arbitrator - Arbitration & Conciliation Act, 1996 - Section 11 (6) - Clause 2900 - Amendment Act of 2015 - Appointment of Arbitrator by General Manager of the respondent - Dispute regarding deduction of amount from bills - Waiver of applicability of Section 12 (5) of the Act

Fact of the Case:

The applicant, an approved vendor for supply of Composite Grooved Rubber Sole Plates to the Indian Railways, had a dispute with the respondent regarding deduction of amount from bills. The applicant sought appointment of an Arbitrator as per the arbitration clause, contending that the respondent cannot appoint a departmental arbitrator after the amendment in the Act in 2015. The respondent had already appointed an Arbitrator who terminated the proceedings due to the applicant's non-appearance.

Finding of the Court:

The court found that the applicant had waived the applicability of Section 12 (5) of the Act by not objecting to the amendment in the arbitration clause post the 2015 Amendment. The court held that the respondent's General Manager was within his right to appoint an Arbitrator. The court also directed the applicant to submit its claim before the Arbitrator within a further period of one month.

Issues: The main issue was whether the respondent could appoint an Arbitrator in terms of the amended arbitration clause after the 2015 Amendment Act, and whether the applicant had waived the applicability of Section 12 (5) of the Act by not objecting to the amendment.

Ratio Decidendi: The court held that the applicant's conduct indicated a waiver of the applicability of Section 12 (5) of the Act, and therefore, the respondent's appointment of an Arbitrator was valid. The court also emphasized the importance of parties' conduct in relation to arbitration agreements.

Final Decision: The application was dismissed, but the applicant was given the opportunity to submit its claim before the Arbitrator within a further period of one month.

ORDER :

Subodh Abhyankar, J.

1. This is an application filed under Section 11 (6) of the Arbitration & Conciliation Act, 1996 (herein after referred to as the Act) for appointment of an Arbitrator to adjudicate the dispute between the parties.

2. The sole question which falls for consideration of this Court is whether the General Manager of the respondent, Union of India, West Central Railway can appoint an Arbitrator in terms of the arbitration clause, after the amendment in Section 12 (6) of the Act as per the Amendment Act of 2015 of the Act.

3. In brief, the facts of the case are that the applicant Smt. Asha Jain is the proprietary of M/s. D.K. Steels, an approved vendor for manufacture and supply of Composite Grooved Rubber Sole Plates (herein after referred to as CGRSP). Applicant is also duly approved by the Research Design & Standard Organization for supply of CGRSP to the Indian Railways. The respondent is the West Central Railway.

4. The case of the applicant is that in an e-tender floated on 8th February, 2013 by the respondent for manufacture and supply of Composite Grooved Rubber Sole Plate for 60 kilograms rail DRG, as per IRS specification for CGRSP for placing beneath rails. E-tender value as specified in the tender document was of Rs. 5,85,96,363/- (rupees five crore eighty five lakh ninety six thousand three hundred sixty three) and the completion period of the said work was eight months. It is not disputed that after some negotiation, the bid as submitted by the applicant was accepted by the respondent.

5. It is not disputed between the parties that in execution of the aforesaid works order, a dispute has arisen between them in respect of deduction of Rs. 34,42,337/- (rupees thirty four lakhs forty two thousand three hundred thirty seven) from the petitioner's different bills by the respondent. Thus, the petitioner is claiming the aforesaid sum along with interest from the respondent. To settle the dispute, the applicant has already resorted to the arbitration clause No. 2900 of the existing Indian Railways Standards Conditions of Contract, wherein it is provided that such dispute should be adjudicated by an Arbitrator to be appointed by the General Manager of the Indian Railways.

6. The contention of the applicant is that the Act stood amended with effect from 23rd October, 2015 and as per the new Amended Act of 2015, the respondent cannot now appoint a departmental arbitrator and procedure as laid down under the new Amendment Act has to be strictly followed. In view of the same, the applicant also issued a notice through its advocate on 5th December 2016 and proposed the name of Hon'ble Justice (Retired) Shri Alok Chakraborty of Calcutta High Court as an Arbitrator to adjudicate the dispute and claims of the parties but the said nomination was rejected by the respondent vide their letter dated 16th January, 2017.

7. Applicant's contention is that after the issuance of the letter dated 5th December, 2016, the respondent had revised the clause 2900 of the Indian Railway Standard Conditions of Contract vide its memo dated 16th February, 2017 in order to appoint an Arbitrator of their own choice.

8. Counsel for the applicant has vehemently argued before this court that a Retired Railway Officer cannot be appointed as the Sole Arbitrator to adjudicate the dispute between the parties, as the appointment of such Arbitrator would be contrary to the Act.

9. In support of his contention, Shri Satish Agrawal, learned counsel for the applicant has relied upon a decision rendered by the Hon'ble Supreme Court in the case of Perkins Eastman Architects DPC and another v. HSCC (India) Limited in Arbitration Application No. 32 of 2019 dated 26th of November 2019.

10. A reply to the aforesaid application has also been filed by the respondent Railways, refuting the averments made in the application under section 11 (6) of the Act

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top