IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
P.NAVEEN RAO, SAMBASIVARAO NAIDU, JJ.
Naveen P Malvay, S/o. late P.N.Malvay – Appellant
Versus
M/s. Samskruthi Shelters rep.by its Managing Partners, Mr. Srinivas Kodai And Mr. S.Ravinder Reddy – Respondent
I.A.No.1 of 2019 In/And Civil Miscellaneous Appal No.32 of 2019
Decided on : 21-06-2022
Arbitration and Conciliation Act, 1996 - Section 37, 9 and 34 Limitation Act - Articles 116 – Dispute – Arbitrator- Seeking enforcement of Award - Appellants are landlords and respondent is builder - A Development Agreement is entered into by appellants and respondent on land belonging to appellants to construct villas and also to create infrastructure for purpose of villas project - Differences arose between them leading to availing arbitration clause and reference of dispute to the Arbitrator - Appellants were in possession and recently, respondent was trying to disturb their possession - Since Court ordered maintenance of status quo, unless order of status-quo is clarified or modified, interference continues compelling appellants to file this appeal and therefore there is no delay - He would further submit that appellants are not trying to interject process of arbitration proceedings - They are only seeking modification of interlocutory order passed by civil Court under Section 9 and in aid of enforcement of Award – Section 37 of the Act provides remedy of appeal against decision under Sections 9 and 34 etc. While Section 37 does not prescribe limitation, Section 34 which provides remedy to challenge the award stipulates limitation to avail such remedy. Section 37 is silent on time limit to avail the remedy of appeal (Para 8).
Finding of the Court :
Respondent also filed E.P. - It appears no orders are passed in these E.Ps., and both E.Ps., are pending - One year after impugned order and after filing of E.Ps., this Appeal is preferred - Cause of action to prefer appeal against order of lower Court arises only when an order is made, but not when some adverse action alleged to have been taken by opposing party subsequently - Except asserting that respondent started interfering compelling them to file appeal, no cogent reason is assigned for delay in filing appeal - Allegation of interference cannot amount to showing sufficient cause - Averments are general in nature, made casually - Appellants seem to assume as a matter of right to seek condonation of delay - When delay is long, burden is heavy on the applicant to assign detailed reasons to satisfaction of the Court - Reasons assigned by applicant are not to satisfaction of Court - More so, having regard to the objects of Act, 1996 - Delay of 435 days is too long to exercise discretion - No case is made out to condone long delay of 435 days.
Result: Application is dismissed.
JUDGMENT :
P.Naveen Rao, J.
The appellants are the landlords and the respondent is the builder. A Development Agreement is entered into by the appellants and respondent on the land belonging to the appellants to construct villas and also to create infrastructure for the purpose of villas project. Differences arose between them leading to availing the arbitration clause and reference of dispute to the Arbitrator. Before the Arbitrator, the parties have come to an understanding and entered into a settlement to resolve the inter se disputes. Recording the same the Arbitrator passed Award on 16.06.2015. However, for the misfortune of both contesting parties, the issues are not resolved. The appellants herein filed application under Section 9 of the Arbitration and Conciliation Act, 1996 in the Court of XVI Additional District and Sessions Judge-cum-XVI Additional Metropolitan Sessions Judge, Ranga Reddy District at Malkajgiri, praying to grant an order of restraint from interfering with the peaceful possession and enjoyment of the petitioners by the respondent. On detailed consideration of the matter, the trial Court passed an order of status-quo in respect of possession over the petition schedule mentioned property existing as on the date of filing of petition for a period of 90 days from the date of the order or till the filing of petition for enforcement of Ex.P.1 Award whichever is earlier.
2. The appellants herein filed E.P.No.615 of 2017 seeking enforcement of the Award, pending in the Court of VII Additional District and Sessions Judge, Ranga Reddy. The respondent filed E.P.No.819 of 2018 on 10.08.2018 in the Court of IV Additional District Judge, Ranga Reddy seeking enforcement of the very same Award. The Court is informed that both the E.Ps, are pending consideration of the respective Courts.
3. That being so, this appeal is filed challenging the status-quo order passed by the court below in A.O.P.No.262 of 2017. As there is delay of 435 days in preferring this appeal, the appellants filed I.A.No.1 of 2018 praying to condone the delay.
4. We have heard Sri Unnam Muralidhar Rao, learned counsel for the appellants and Sri M.Das Mahapatra, learned counsel for the respondent.
5. With reference to the issue of delay, learned counsel for the appellants sought to contend that in fact there is no delay. After the status quo order was granted, the appellants were in possession and recently, the respondent was trying to disturb their possession. Since the Court ordered maintenance of status quo, unless the order of status-quo is clarified or modified, the interference continues compelling the appellants to file this appeal and therefore there is no delay. He would further submit that appellants are not trying to interject the process of arbitration proceedings. They are only seeking modification of the interlocutory order passed by the civil Court under Section 9 and in aid of enforcement of the Award. Therefore, the view expressed by the Hon’ble Supreme Court in Government of Maharashtra (Water Resources Department) represented by Executive Engineer Vs Borse Brothers Engineers and Contractors Private Limited, (2021) 6 Supreme Court Cases 460, has no application and the appeal be considered on merits without regard to issue of delay. Unless the appeal is considered on merits, grave injustice would be caused to the appellants due to disturbance of possession held by them by the respondent, pending enforcement process before the competent Court.
6. Per contra, learned counsel for the respondent contends that if the prayer sought by the appellants is granted, it will create more serious complications. Further there is no recognition of possession in favour of the appellants and by means of filing the application, they are trying to gain back possession, which is otherwise, vested in the respondent. If what is contended by the appellants is true that they are in possession and in violation of status-quo order, if the respondent is interfering
Manindra Land & Building Corpn. v. Bhutnath Banerjee
Maniben Devraj Shah v. Municipal Corpn. of Brihan Mumbai
Parimal v. Veena [Parimal v. Veena
Hon’ble Supreme Court was dealing with three civil appeals. In the civil appeal arising from Bombay and Delhi High Courts, both Courts refused to condone delay in filing appeals beyond 120 days.
The main legal point established in the judgment is that the delay in filing an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 must be considered in the context of the need for....
Point of Law : Merely because the appellant is Government organization, lenience cannot be shown to condone such a long delay.
The court emphasized that delay in filing appeals under the Arbitration Act must be justified by sufficient cause, with negligence being insufficient for condonation.
The main legal point established in the judgment is that the doctrine of condonation of delay should be applied judiciously, taking into account the circumstances and the impact of external factors s....
The law of limitation applies equally to all parties, including the Government, and a lack of diligence in filing appeals can result in rejection of delay condonation applications.
The court may condone delays in filing appeals where sufficient cause is shown, including circumstances beyond a party's control, advocated particularly in light of unprecedented events like a pandem....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.