SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Telangana) 728

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
B. VIJAYSEN REDDY, J.
Sew Infrastructure Limited, Hyd – Appellant
Versus
The Federal Democratic Republic Of Ethiopia, And Others – Respondents
Arbitration Application No.54 of 2016
Decided on : 13-10-2022

Advocates:
Advocate Appeared:
For the Appellant : AVINASH DESAI

Headnote:

Arbitration and Conciliation Act, 1996 - Section 9 - Delay in execution of project - Notice of termination - Application seeking to restrain ERA, its agents, officers, employees etc. by way of injunction from invoking two ABGs and two PBGs - To stay operation of all further actions pursuant to notice of termination including any coercive steps and encashment of BG issued on behalf of SEW by BOA and SBI - Held, No judicial precedent is brought to notice of this Court to substantiate that an order under Section 9 of Act can be continued post-award, even if party having benefit of such order, faced adverse decision in arbitral award - During subsistence of status quo order passed by Court BOA paid monies under ABGs and PBGs to ERA purportedly in compliance of order passed by Federal High Court of Ethiopia - Chances of applicant/SEW succeeding before appellate Tribunal and other grounds urged impugning findings of Arbitral Tribunal, in opinion of this Court, cannot fall for consideration in instant application after award has been passed - Court does not have jurisdiction to continue interim order, as matter has been rendered infructuous, more particularly, in view of decision of Arbitral Tribunal that invocation of BGs is valid - Interim order extended from time to time, shall stand vacated - Application is dismissed.

ORDER :

The applicant herein is SEW Infrastructure Limited (SEW), a company incorporated under the laws of India and having its registered office at Begumpet, Hyderabad; the respondent No.1 is the Ethiopian Roadways Authority (ERA), an entity of the Federal Democratic Republic of Ethiopia; the respondent No.2 is the Bank of Abyssinia (BOA) and the respondent No.3 is the State Bank of India (SBI).

Background facts:

2. In the bidding process floated by ERA, a contract for construction of roads under Mombassa – Nairobi – Addis Ababa Corridor Phase III Project: Hawassa – Ageremarian Section, Lot 1 : Hawassa – Chuko in Ethiopia was awarded to SEW and contract agreement dated 30.11.2012 was entered into by the parties. In terms of the contract BOA has issued four Bank Guarantees (BGs) to ERA on the basis counter BGs issued by SBI on behalf of SEW. Out of four BGs, two BGs are Advance Bank Guarantees (ABG), which are encashable on the condition of SEW applying the funds received for the project to purposes, which are outside the scope of the roads project. The other two BGs are Performance Bank Guarantees (PBG), which are encashable upon declaring the contractor/SEW being in default under the contract.

3. Disputes arose between SEW and ERA, as, admittedly, there was delay in execution of the project. SEW claimed that delay is attributable to ERA, as it did not hand over the project sites without obstructions and encumbrances for execution of the road project. The General Conditions of Contract (GCC) provided for mechanism of forming a Dispute Board to which any dispute arising between the parties has to be referred to. It is the case of SEW that as per Clauses 20.4 and 20.5 without referring the dispute to the Dispute Board and without following any conditions of settlement under GCC, ERA unilaterally issued notice of termination dated 20.05.2016, which was served on SEW on 23.05.2016 giving a notice of 14 days for termination of the contract. SEW issued reply dated 30.05.2016 asserting that delay and slow progress of work was due to various reasons attributable to ERA.

4. SEW approached this Court by way of this Arbitration Application under Section 9 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act’) seeking to restrain ERA, its agents, officers, employees etc. by way of injunction from invoking two ABGs and two PBGs; to restrain BOA from honouring/encashing ABG and PBG on behalf of SEW; to restrain SBI from honouring/encashing counter BG issued to BOA; to stay operation of all further actions pursuant to the notice of termination dated 20.05.2016 including any coercive steps and encashment of BG issued on behalf of SEW by BOA and SBI.

5. Clause 20.06 of the GCC provides for arbitration, which reads as follows:

    “20.6 Arbitration

20.6.1 Any dispute between the Parties arising out of or in connection with the Contract not settled amicably in accordance with GC Clause 20.5 above, and in respect of which the DB’s decision (if any) has not become final and binding, shall be finally settled by arbitration. Arbitration shall be conducted as follows:

(a) for contracts with foreign contractors, international arbitration (i) with proceedings administered by the institution designated in the Particular Conditions, and conducted under the rules of arbitration of such institution; or, if so specified in the Particular Conditions,

(ii) international arbitration in accordance with the arbitration rules of the United Nations Commission on International Trade Law (UNCITRAL); or (iii) if neither an arbitration institution or UNCITRAL arbitration rules is specified in the Particular Conditions, with proceedings administered by the International Chamber of Commerce (ICC), and conducted under the ICC Rules of Arbitration; by one or more arbitrators appointed in accordance with the said arbitration rules.

The place of arbitration shall be the neutral location specified in the Particular Conditions, and the arbitration shall be conducted

                Click Here to Read the rest of this document
                1
                2
                3
                4
                5
                6
                7
                8
                9
                10
                11
                SupremeToday Portrait Ad
                supreme today icon
                logo-black

                An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                Please visit our Training & Support
                Center or Contact Us for assistance

                qr

                Scan Me!

                India’s Legal research and Law Firm App, Download now!

                For Daily Legal Updates, Join us on :

                whatsapp-icon Back to top