THE HIGH COURT OF SIKKIM: GANGTOK
BISWANATH SOMADDER, CJ., BHASKAR RAJ PRADHAN, J.
State of Sikkim - Appellant
Vs.
Chhabil Dass Agarwal S/o Late Deepchand Agarwal - Respondent
ARB. A. No. 9 of 2024
Decided On : 10-12-2025
| Table of Content |
|---|
| 1. factual background and procedural trajectory of the arbitration dispute. (Para 1 , 2 , 3 , 15) |
| 2. contentions regarding contractual interpretation and limitation periods. (Para 4 , 19 , 20 , 21 , 28) |
| 3. commercial court's analysis on patent illegality and public policy foundations. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14) |
| 4. scope of section 37 appellate jurisdiction in arbitration matters. (Para 16 , 17 , 18) |
| 5. court's final assessment on contract breach, escalation, and dismissal of appeal. (Para 22 , 23 , 24 , 25 , 26 , 27 , 29 , 30) |
Judgment :
Bhaskar Raj Pradhan, J.
This is an appeal under section 37 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act).
2. The facts pertinent for disposal of the present appeal can be briefly summarised as under:
(i) The appellants and Chhabil Dass Agarwal (the respondent) had entered into a contract agreement dated 24.02.2004 for construction of 2x5MVA, 66/11KV substation with LILO from Phodong 66KV S/S and Meyong- C-Power House at Mangan. The work had to be completed within four months but due to several factors, it could be done only on 18.02.2008. The work value was initially for Rs.7,79,33,000. Admittedly, on 28.04.2004 and 09.11.2004 mobilization advances for Rs.1,00,00,000/- and Rs. 94,83,250/- respectively, were paid to the respondent. Although, the work was completed on 18.02.2008, the respondent did not receive full and final payment on the said date. According to the respondent, on 16.02.2006, he received Rs.2,76,44,048/- for civil works. Thereafter, for electrical works, he received Rs.1,76,00,000/- on 14.10.2011 and Rs.91,00,000/- on 02.11.2011. According to the respondent, on 31.03.2017 he received final payment of Rs.3,77,67,688/- after entering into a revised agreement dated 30.03.2017. The total amount received therefore was Rs.11,15,94,986/-.
(ii) Dissatisfied with the amount of payment received for the contract work, the respondent invoked the arbitration clause, claimed escalation cost and interest on delayed payment. Consequently, the sole Arbitrator was appointed by this Court vide order dated 08.10.2020 in Arb. P. No. 2 of 2020. After completing the proceedings, the impugned award was passed on 08.11.2021 holding that the respondent is entitled to both escalation cost and interest amounting to Rs.5,88,10,934/- along with 10% interest per annum. Aggrieved with the impugned award, the appellant filed an application under section 34 of the Arbitration Act, which was rejected by the learned Commercial Court.
(iii) The respondent, in their claim before the learned Arbitrator, asserted certain facts which were admitted by the appellant in their statement of defence. The respondent asserted that during the process of execution of the work there was change in specification. The change in alignment of approach road necessitated increase in protective works and other allied works due to site conditions. There was also increase in number of culverts. To protect private properties during monsoon period and because of the instability of the site, additional walls were also constructed. The respondent had to execute all such works. For all such reasons, the revised estimate for said works increased from original approved cost of Rs.9,18,21,591.79p to Rs.11,19,55,284.10p which fact finds support from office notings of the appellants. Token work order dated 09.05.2007 was also issued to complete the work as per the revised estimate. Revised estimate was prepared in view of the excess work done at site. Ultimately, revised agreement dated 30.03.2017 was also executed for additional civil and electrical works. By the end of October 2005, more than 80% of the civil works were completed which fact has been admitted by the appellants in their office notings dated 26.10.2005. The entire work was completed and the sub-station charged on 18.02.2008. All the additional works were executed which fact the appellants also admitted. That, against the entire works
Associate Builders vs. Delhi Development Authority
Delhi Airport Metro Express Pvt. Ltd. vs. Delhi Metro Rail Corporation Ltd.
J.C. Budhraja vs. Chairman, Orissa Mining Corporation Ltd. & Another
Ssangyong Engineering and Construction Company Ltd. vs. National Highways Authority of India (NHAI)
NTPC Ltd. vs. Deconar Services Pvt. Ltd.
Delhi Metro Rail Corporation Limited vs. Delhi Airport Metro Express Private Limited
Pam Developments Private Limited vs. State of West Bengal & Another
State of Rajasthan & Another vs. Nav Bharat Construction Co.
Konkan Railway Corporation vs. Chenab Bridge Project Undertaking
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
The court confirmed that the scope of interference under Section 37 of the Arbitration Act is limited, emphasizing the binding nature of arbitration agreements.
The court upheld the arbitral award, affirming that contractual obligations prevail over departmental instructions, and emphasized the limited scope of appellate review under the Arbitration and Conc....
The main legal point established in the judgment is that the court should not interfere with an arbitral award unless the arbitrator's conclusions are arbitrary, capricious, or perverse. The court's ....
The court upheld the Arbitral Tribunal's award on escalation claims, affirming the limited grounds for judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996.
The court affirmed that the scope of interference in arbitral awards is limited, emphasizing that awards can only be set aside on specific grounds, including patent illegality or violation of public ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.