VIBHU BAKHRU, AMIT MAHAJAN
Delhi State Industrial & Infrastructure – Appellant
Versus
Sukumar Chand Jain – Respondent
JUDGMENT
Vibhu Bakhru, J. Delhi State Industrial & Infrastructure Development Corporation Ltd. (hereafter `DSIIDC') has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an order dated 03.05.2019 (hereafter `the impugned order') passed by the learned Commercial Court, whereby DSIIDC's application under Section 34 of the A&C Act, seeking to set aside an arbitral award dated 13.11.2014 (hereafter `the impugned award'), was rejected.
Factual Context
2. By a work order dated 18.07.2003 (hereafter `the agreement'), DSIIDC awarded the work of "Construction of Pucca School Bldg..at Dwarka, Sector-22, Delhi (Composite Work)" (hereafter `the Dwarka Project') to the respondent. The stipulated date of commencement of the Dwarka Project was on 27.03.2003. The Dwarka Project was to be completed within a period of eighteen months, that is, by 26.01.2005.
3. Thereafter, by a memo dated 02.09.2004, the Directorate (Works) Central Public Work Department (CPWD) added Clause 10CA to the agreement. The relevant extract of Clause 10CA reads as under:
"If after submission of the tender, the price of cement and/or steel reinfo
The main legal point established is that the issuance of a No Claim Certificate (NCC) under economic duress can invalidate its validity and preclude the claimant from raising any claim in connection ....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Arbitration - Application for setting aside of arbitral Award - Award of interest at rate of 18% per annum from date of award is not in consonance with observations made by Arbitral Tribunal, which r....
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
The Court upheld the AT's findings regarding the attribution of delay, enforcement of NOC, and the allowance of the claim for escalation cost without a specific clause in the Contract, based on the n....
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
Failure to raise claims for escalation in a timely manner and acceptance of payments in full and final settlement preclude further claims.
The Arbitral Tribunal's jurisdiction to consider claim amounts and reject specific claims under the Arbitration and Conciliation Act, 1996.
Execution of the works was delayed and the respondent sought Extension of Time for completion of the works on successive occasions, which were approved by NHAI.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.