Can a Contractor Claim Rectification Costs Without Starting the Rectification Work?

Rectification Cost Claims in Construction Contracts – Why Contractors Must Perform or Incur the Expense First

A recurring question in construction disputes is this: can the contractor claim for the cost of rectification without starting the work? Contractors facing defective work allegations, or employers withholding payment for anticipated remedial costs, often assume that a claim for rectification is a standalone entitlement that can be asserted prospectively. The case law points firmly in the other direction. A rectification claim is generally not self-executing – it crystallises only when the rectification work has actually been carried out or when the cost of that work has actually been incurred.

The General Rule: No Rectification Work, No Rectification Claim

The authorities consistently establish that a contractor cannot simply assert a claim for rectification costs on the basis of defective work alone. The entitlement arises when:

  • the contractor itself performs the rectification work and incurs the expense; or
  • the employer is put to the expense of engaging another party to remedy the defects.

Until one of these events occurs, a rectification claim is speculative. Courts have repeatedly emphasised that a claimant must prove, on a balance of probabilities, that costs allegedly incurred are genuinely attributable to rectification of defects or rejected works before any deduction or recovery is permitted

NCT BUILDING & CIVIL ENGINEERING SDN BHD vs SINOHYDRO CORPORATION (M) SDN BHD & OTHER CASES - 2020 MarsdenLR 2579

. The same evidential burden applies to a contractor seeking payment: no incurred cost, no recoverable claim.

The Employer's Route: Calling on the Performance Bond

Where the contractor fails or refuses to rectify, the contract typically empowers the employer to act unilaterally. Standard clauses provide that upon breach of contract or termination, the employer may call on the performance bond for the completion of and/or rectification of the Works and reimbursement of loss and expense suffered

MCC Overseas (M) Sdn Bhd vs Malayan Banking Bhd & Ors - 2026 MarsdenLR 265688

.

The mechanics were illustrated in a cladding defects dispute where the employer called on the performance bond to fund rectification work carried out by another contractor, claiming a substantial sum as the cost of rectifying the defects

KEJURUTERAAN BINTAI KINDENKO SDN BHD vs NAM FATT CONSTRUCTION SDN BHD & ANOR - 2011 MarsdenLR 4802

. Once the employer has lawfully made such a call and paid a third party, the contractor's ability to claim the same rectification costs is effectively extinguished – unless the employer's call was itself wrongful or excessive.

Similar contractual provisions allow the employer, where the contractor fails to execute required remedial work, to carry out that work by its own workmen or other contractors and recover the cost from the contractor or deduct it from monies due

VILLAGE GROVE CONDOMINIUM MANAGEMENT CORPORATION vs YUNCO ENTERPRISE SDN BHD - 2021 MarsdenLR 285

. Again, the mechanism protects the employer's incurred expenditure – it does not create an anticipatory claim for either party.

The Clean Hands Principle and Quantum Meruit

Contractors sometimes attempt to frame rectification claims restitutionary – as quantum meruit claims for the value of remedial work. Equity, however, imposes a significant limit. A party seeking restitutionary relief must come with clean hands. A contractor who caused the very defect necessitating the remedial work cannot invoke equity to profit from its own non-performance, a principle applied where a plaintiff sought payment for rectifying defects arising from its own breach

REAGAL ELITE LETRIK SDN BHD vs COUNTRY GARDEN DANGA BAY SDN BHD - 2025 MarsdenLR 5005

.

This means that even where a contractor has actually performed rectification, it may still be barred from recovering the cost if the defects originated from its own defective workmanship or breach.

Procedural Fairness: The Opportunity to Rectify

Employers are not entirely unrestricted either. In a Smart Home System defect case decided under the Contracts Act 1950, the court held that a plaintiff must provide the defendant an opportunity to rectify breach-related defects before engaging a third party and claiming the cost. Because that opportunity was not given, the plaintiff recovered only nominal damages instead of the full RM423,137.38 claimed

CHU KOK WEI vs PCOM PACIFIC SDN BHD

.

The lesson cuts both ways:

  1. Contractors must be given notice and a chance to cure before the employer engages others at the contractor's expense.
  2. Employers who bypass this step may find their rectification counterclaims reduced or dismissed.

Set-Off and Substantiation

Employers frequently respond to defect allegations by set-off – deducting anticipated or actual rectification costs from progress payments. Such set-off is valid only where the employer proves both the defects and the costs actually incurred. In one subcontract dispute over aluminium works, the employer successfully counterclaimed for rectification costs after proving the subcontractor's failure to fulfil its rectification obligations, and the court upheld the right of set-off for costs incurred due to that failure

LUCKSOON METAL WORKS SDN BHD vs ESAMEGAH SDN BHD & ANOR

.

Conversely, where the evidential foundation is missing, deductions fail. Adjudication and court decisions have set aside deductions where the responding party failed to prove on a balance of probabilities that the costs allegedly incurred are for rectification of defects or rejected works

NCT BUILDING & CIVIL ENGINEERING SDN BHD vs SINOHYDRO CORPORATION (M) SDN BHD & OTHER CASES - 2020 MarsdenLR 2579

. Other counterclaims for rectification costs have been dismissed entirely where the termination was mutual, the final account had become conclusive, or the claimant simply failed to discharge its burden of proof

EASTMONT SDN BHD vs MEGA PLANNER JAYA SDN BHD

EASTMONT SDN BHD vs MEGA PLANNER JAYA SDN BHD

.

Practical Takeaways for Contractors and Employers

For contractors:

  • Do not lodge a rectification claim before performing the work or incurring genuine cost – it will likely fail.
  • Preserve invoices, quotations, and third-party contracts evidencing actual remedial expenditure.
  • If the employer has called on the performance bond, challenge the lawfulness or quantum of that call rather than claiming the same costs in parallel.
  • Insist on notice and an opportunity to cure before the employer engages others.

For employers:

  • Rectification deductions must be backed by proof of actual cost, not estimates alone.
  • Follow contractual notice requirements and give the contractor the chance to rectify first.
  • Be aware that mutual termination or a conclusive final account may extinguish later rectification claims

    EASTMONT SDN BHD vs MEGA PLANNER JAYA SDN BHD

    .

Conclusion and Key Takeaways

The short answer to whether a contractor can claim rectification costs without starting the work is, generally, no. The claim crystallises only upon performance of the rectification or actual incurrence of cost, and even then it may be defeated by the clean hands principle where the contractor caused the defects. Employers, for their part, must substantiate any deductions or bond calls with evidence of real expenditure and must afford the contractor an opportunity to cure. This article is intended as general information on construction contract principles and should not be treated as advice on any particular dispute.

#ConstructionLaw #RectificationCosts #PerformanceBond #ContractorClaims #BuildingDisputes