Variation Work Completed Without Approved Quotation – Can Contractors Still Claim Payment?

When Variation Works Are Done Without a Quotation Approval, Who Pays the Contractor?

It is a familiar scenario on construction sites: the employer urgently needs extra work done, the contractor submits a quotation, and before the quotation is formally approved, the employer's agent tells the contractor to proceed anyway. Months later, with the works completed and the project certified, the employer refuses to pay — arguing that no variation quotation was ever approved. Can the contractor still recover payment? Generally, the answer may well be yes.

The Core Legal Principle: Employer Conduct Can Bind the Employer

The decisive question in these disputes is whether the employer, through its employee or agent, instructed or assured the contractor to carry out the variation works, and whether the employer's subsequent conduct amounted to acceptance of the completed work. Where both elements are established, the absence of a formally approved quotation does not defeat the contractor's claim.

In one Malaysian decision, the court held that the employer was bound by the act and conduct of the defendant's employee who had assured the plaintiff that payment would be made and instructed the plaintiff to carry on with the work as soon as possible

MALIM RESTU CONSTRUCTION SDN BHD vs PETRONAS DAGANGAN BHD - 2014 MarsdenLR 750

. The assurance induced the contractor to proceed with the variation works even though the quotation was still pending approval.

Acceptance by Conduct After Completion

Courts often look at what the employer did after the works were finished. If the employer allows the contractor to complete the variation works, accepts the completed works, and obtains the certificate of completion, a later rejection of the variation claim may be treated as too late. In the same case, the court found that the employer's rejection, made long after completion, meant that the employer must have or be deemed to have agreed and accepted the contractor's claim for the variation works

MALIM RESTU CONSTRUCTION SDN BHD vs PETRONAS DAGANGAN BHD - 2014 MarsdenLR 750

. This is essentially a doctrine of deemed acceptance by conduct.

This approach is consistent with principles under the Contracts Act 1950, where payment may be recovered for work done lawfully for another's benefit on a quantum meruit basis, supported by evidence of instructions and acceptance

LIM SHU YING vs NBRAND (M) SDN BHD & OTHER CASES

.

Not Every Contract Is Truly a Strict Lump Sum

Employers sometimes resist variation claims by insisting the contract is a lump-sum contract under which all extra items should have been included. But the employer's own conduct can undermine that argument. In the Malaysian case, the employer had approved and paid for two other variation items — constructing a unipole MID footing and supplying a piston air compressor — which led the court to conclude that the project is not a lump sum contract otherwise there will no necessity for the defendant to approve and pay for the aforesaid two items

MALIM RESTU CONSTRUCTION SDN BHD vs PETRONAS DAGANGAN BHD - 2014 MarsdenLR 750

.

The Quotation Procedure Does Not Bar Payment Once Work Is Completed

Requiring a contractor to submit a quotation is a common contract mechanism, but it is generally intended to regulate pricing, not to give the employer a free pass to obtain work without paying. As the court observed, the employer requested the quotation, and while it was still pending approval, due to urgency of completing the project the employer's agent instructed the contractor to proceed and assured payment

MALIM RESTU CONSTRUCTION SDN BHD vs PETRONAS DAGANGAN BHD - 2014 MarsdenLR 750

. Once the employer authorised and accepted the work, the contractor's entitlement to payment follows.

What Happens When There Was No Genuine Authority?

The picture changes when the variation order did not come from a person with actual authority. In adjudication decisions arising from a wastewater project, the variation work order was said to have come from the Indah Water Konsortium Operation Unit rather than the respondent, and the claimant's quotation was merely submitted for consideration — raising doubts about whether the contractual variation machinery was ever engaged

Quantum Hyrdromech Sdn Bhd vs Nine Hundred Builders Sdn Bhd and another

QUANTUM HYRDROMECH SDN BHD vs NINE HUNDRED BUILDERS SDN BHD & ANOTHER CASE

. Similarly, in another dispute, a party argued a quotation was approved by Nbrand but the court found there was simply no evidence of such approval

LIM SHU YING vs NBRAND (M) SDN BHD & OTHER CASES

. Proof of authorisation is therefore the contractor's central burden.

Lessons from Public Sector and Infrastructure Disputes

The same reasoning appears across jurisdictions. In an Indian writ petition, extra works were carried out at the direction of the authorities and payments were made based on completed works; the court held that unilateral recovery of those amounts after payment was arbitrary and could not stand 2025 Supreme(Online)(Ker) 56832. In another matter, respondents admitted in their pleadings that extra work had been executed at their instance, and the petitioner was held entitled to the cost of that extra work notwithstanding an audit objection 2016 0 Supreme(Chh) 546. By contrast, where additional works were carried out beyond the original scope without obtaining the required approval, the employer successfully resisted liability 2020 0 Supreme(Bom) 814. The dividing line in every case is authorisation and acceptance.

Subcontractors Cannot Refuse Variation Works Over Price Uncertainty

The position differs slightly for subcontractors. A subcontractor is generally legally obliged to carry out variation works as instructed by the main contractor and cannot refuse simply because the price has not been agreed. As one decision put it, even if the disputed system constituted variation works, the defendant is legally obliged to carry it out and claim accordingly either under CIPAA or in the Court. Refusing to execute it would be a breach of the contract MYS0000010590. The subcontractor's protection lies in claiming the applicable rates through adjudication under the Construction Industry Payment and Adjudication Act 2012 or in court proceedings — and adjudication decisions under CIPAA are binding unless successfully set aside on jurisdictional or natural justice grounds

QUANTUM HYRDROMECH SDN BHD vs NINE HUNDRED BUILDERS SDN BHD & ANOTHER CASE

.

Practical Steps for Contractors and Subcontractors

  • Document every instruction, assurance, and communication from the employer or its agents concerning variation works, especially where quotation approval is pending.
  • Keep records showing the employer accepted the completed works — certificates of completion, site minutes, and correspondence are critical.
  • Track how the employer treats other variation items, since approving and paying for some variations can defeat a strict lump sum defence.
  • Subcontractors should submit quotations promptly but should not halt instructed variation works merely because the price is unsettled MYS0000010590.
  • Employers should respond to variation claims promptly; silence and continued use of the works may be construed as deemed acceptance

    MALIM RESTU CONSTRUCTION SDN BHD vs PETRONAS DAGANGAN BHD - 2014 MarsdenLR 750

    .

Key Takeaways

Where variation work has been carried out and completed but the quotation was never formally approved, the contractor is not automatically out of pocket. If the employer or its authorised agent instructed the contractor to proceed, assured payment, and subsequently accepted or used the completed works, the employer may be bound by that conduct and deemed to have accepted the variation claim. Conversely, contractors must prove actual authorisation — claims resting on instructions from persons without authority, or on unapproved quotations with no evidential support, may fail. Where the quotation process stalls, escalation through CIPAA adjudication or court proceedings remains available, and subcontractors in particular must continue performing instructed variations while reserving their pricing claims. Every dispute turns on its own facts and contract terms, so parties should seek advice tailored to their specific situation.

#ConstructionLaw #VariationWorks #BuildingDisputes #CIPAA #ContractorRights
Chat Download
Chat Print
Chat R ALL
Landmark
Strategy
Argument
Risk
Chat Voice Bottom Icon
Chat Sent Bottom Icon
SupremeToday Portrait Ad
whatsapp-icon Back to top