SUPREME COURT OF INDIA
DHANANJAYA Y. CHANDRACHUD, B.V. NAGARATHNA, JJ.
Supertech Limited - Appellant
Versus
Emerald Court Owner Resident Welfare Association and Others – Respondents
Miscellaneous Application No 1572 of 2021 In Civil Appeal No 5041 of 2021
Decided on : 04-10-2021
Miscellaneous Application - Modification of Judgment - NBR 2006, NBR 2010, NBC 2005, UP Apartments Act 2010, UP 1975 Act - The judgment affirmed the demolition of Towers 16 and 17 due to violations of minimum distance requirements, green area requirements, fire safety norms, and non-compliance with building regulations. The court also found collusion between NOIDA and the applicant. The court directed the demolition to be carried out by the appellant at its own cost and ordered refunds to existing flat purchasers. The court dismissed the miscellaneous application seeking modification of the judgment, citing the finality and stability of judicial pronouncements and the prohibition on seeking modification through a miscellaneous application.
Fact of the Case:
The Division Bench of the High Court directed the demolition of Towers 16 and 17 in Emerald Court, NOIDA, due to various violations and collusion between NOIDA and the applicant. The appellant filed a miscellaneous application seeking modification of the judgment to retain Tower 16 and slice a portion of Tower 17 to comply with the minimum distance and green area requirements.
Finding of the Court:
The court dismissed the miscellaneous application, affirming the demolition of Towers 16 and 17 and ordering the appellant to carry out the demolition at its own cost. The court emphasized the finality and stability of judicial pronouncements and prohibited seeking modification through a miscellaneous application.
Issues: The issues involved the compliance with minimum distance requirements, green area requirements, fire safety norms, and building regulations, as well as collusion between NOIDA and the appellant. The appellant sought modification of the judgment through a miscellaneous application.
Ratio Decidendi: The court held that seeking substantive modification of a judgment through a miscellaneous application is impermissible and an abuse of the process. The court emphasized the finality and stability of judicial pronouncements and prohibited seeking modification through a miscellaneous application.
Final Decision: The court dismissed the miscellaneous application seeking modification of the judgment, citing the finality and stability of judicial pronouncements and the prohibition on seeking modification through a miscellaneous application.
ORDER :
1. A miscellaneous application has been filed by Supertech Limited seeking modification of the judgment and order of this Court dated 31 August 2021. The reliefs which are sought in the Miscellaneous Application read thus:
(b) Pass an order of status quo in respect of Towers 16 & 17 in Emerald Court, Plot No. 4, Sector 93A, NOIDA till final orders are passed in the present application.”
2. A Division Bench of the High Court of Judicature at Allahabad directed the demolition of Towers 16 and 17 by the third respondent, New Okhla Industrial Development Authority, in Emerald Court constructed by the applicant and situated on Plot No 4, Sector 93A, NOIDA. While affirming the judgment of the Division Bench, this Court has recorded the following conclusions in its judgment, which is reported as Supertech Limited vs Emerald Court Owner Resident Welfare Association and Others, 2021 SCC OnLline SC 648:
(i) The land allotted to appellant under the original lease agreement and the supplementary lease deed constitute one plot;
(ii) The land which was allotted through the supplementary lease deed forms a part of original Plot No 4, and would be governed by the same terms and conditions as the original lease deed;
(iii) The sanction given by NOIDA on 26 November 2009 and 2 March 2012 for the construction of T-16 and T-17 is violative of the minimum distance requirement under the NBR 2006, NBR 2010 and NBC 2005;
(iv) An effort was made to get around the violation of the minimum distance requirement by representing that T-1 together with T-16 and T-17 form one cluster of buildings in the same block. This representation was sought to be bolstered by providing a space frame between T-1 and T- 17. The case that T-1, T-16 and T-17 are part of one block is directly contrary to the appellant's stated position in its representations to the flat buyers as well as in the counter affidavit before the High Court. The suggestion that T-1, T- 16 and T-17 are part of one block is an after-thought and contrary to the record;
(v) After realizing that the building block argument would not pass muster, another false case was sought to be set up with the argument that T-1 and T-17 are dead end sides, thereby obviating the need to comply with the minimum distance requirements. This argument is belied by the comprehensive report submitted by NBCC. The sides of T- 1 and T-17 facing each other are not dead end sides since both the sides have vents/egresses facing the other building;
(vi) By constructing T-16 and T-17 without complying with the Building Regulations, the fire safety norms have also been violated;
(vii) The first revised plan of 29 December 2006 contained a clear provision for a garden area adjacent to T-1. In the second revised plan of 26 November 2009, the provision for garden area was obliterated to make way for the construction of Apex and Ceyane (T-16 and T-17). The common garden area in front of T-1 was eliminated by the construction of T-16 and T-17. This is violative of the UP Apartments Act 2010 since the consent of the flat owners was not sought before modifying the plan promised to the flat owners; and
(viii) T-16 and T-17 are not part of a separate and distinct phase (Phase-II) with separate amenities and infrastructure. The supplementary lease deed stipulates that the they are part of the original project. Hence, the consent of the individual flat owners of the original fifteen towers, individually or through the RWA, was a necessary requirement under the UP Apartments Act 2010 and UP 1975 Act before T-16 and T-17 could have been constructed, since they necessarily reduced the undivided interest of the individual flat owners in the common area by adding new flats and increasing the
Delhi Administration vs Gurdip Singh Uban and Others
Ram Chandra Singh vs Savitri Devi and Others
Sone Lal v. State of U.P. [(1982) 2 SCC 398] [Para 8]
Suthendraraja v. State [(1999) 9 SCC 323 : 2000 SCC (Cri) 463] [Para 9]
Ramdeo Chauhan v. State of Assam [(2001) 5 SCC 714 : 2001 SCC (Cri) 915] [Para 9]
Delhi Admn. v. Gurdip Singh Uban [(2000) 7 SCC 296] [Para 9]
(1) Breach by planning authority of its obligation to ensure compliance with building regulations is actionable at instance of residents whose rights are infringed by violation of law. Their quality ....
Amendments to pleadings should be allowed to determine the real controversy between parties, emphasizing a liberal approach to avoid multiplicity of litigation.
Point of Law : Court find ourselves unable to agree with the submissions made by learned counsel for the review petitioner and Court do not find any error, much less an error apparent on the face of ....
Review petitions must be based on new evidence or errors apparent on the record, not simply rearguments of previous claims.
The court confirmed that identical issues must exist for a stay under Section 10 of CPC, emphasizing the requirement for unequivocal identity across cause of action, subject matter, and relief.
Amendments to plaints should be liberally allowed, provided they do not cause injustice, ensuring precise determination of legal rights in ongoing litigation.
The amendment of pleadings to incorporate subsequent events pending litigation is permissible to avoid multiplicity of suits and seek appropriate relief.
Amendments to pleadings under Order VI Rule 17 of the CPC should not change the nature of the suit or introduce new causes of action, and must be necessary for the proper adjudication of the case wit....
The High Court's jurisdiction under Article 227 does not extend to re-evaluating lower court decisions but ensures they act within their authority; unauthorized constructions cannot be permitted to p....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.