SUPREME COURT OF INDIA
Pamidighantam Sri Narasimha, Atul S. Chandurkar, JJ.
The State of Jharkhand – Appellant
Versus
The Indian Builders Jamshedpur – Respondent
Civil Appeal Nos. 8261-8262 of 2012
Decided On : 05-12-2025
Arbitration and Conciliation Act, 1996 – Section 31(7) – Arbitration – Applicability of excepted clause or a prohibited claim in a contract – Contractual clauses that limit claims are founded on freedom to contract – They are agreements that crystalise informed choices of parties – Applicability of excepted or prohibitory clauses would primarily depend upon the agreement between the parties, which alone is the guiding principle for Arbitral Tribunal – Issues relating to payment of interest arising under Section 31(7) of Act stand on a different footing from that of contractual clauses excepting or prohibiting certain claims – In order to ensure clarity and consistency, ratio of Bharat Drilling, (2009) 16 SCC 705 requires to be reconsidered – Matter referred to larger Bench. (Paras 8, 9, 11 and 12)
Facts of the case:
State of Jharkhand is in appeal against the judgment of the High Court of Jharkhand allowing Section 372 appeal under Arbitration and Conciliation Act, 19963. The appeal was filed by the respondent-claimant against the judgment of the Civil Court4 setting aside the arbitral award allowing the objections filed by State under Section 34. By its award dated 19.04.2007, the Arbitral Tribunal allowed certain claims but the Civil Court set aside the claims 3, 4 and 6 on the ground that they were specifically prohibited under the contract between the parties.
Findings of Court:
High Court has not examined the contractual clauses extracted hereinabove and has proceeded to dispose of the appeal under the impression that the issue is conclusively covered by the decision of this Court in Bharat Drilling.
Result : Matter referred to larger Bench.
| Table of Content |
|---|
| 1. need for re-evaluation of bharat drilling case (Para 1) |
| 2. appeal against high court judgment under arbitration act (Para 2) |
| 3. counsel's argument on high court error (Para 3) |
| 4. examination of contractual clauses controlling claims (Para 4 , 5) |
| 5. high court reliance on bharat drilling without detailed analysis (Para 6 , 7 , 8) |
| 6. appropriateness of bharat drilling with respect to claims and interest (Para 9 , 10 , 11) |
| 7. referral to larger bench for clarity (Para 12) |
JUDGMENT :
1. In view of our opinion that Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors., (2009) 16 SCC 705. is not an authority for the proposition that an excepted clause or a prohibited claim in a contract applies only to the employer and not to the Arbitral Tribunal, for the reasons to follow, in order to obviate uncertainty and for clear declaration of law, we are referring Bharat Drilling (supra) to a larger bench for reconsideration and authoritative decision. The context in which we have referred the matter to a larger bench is as follows.
2. State of Jharkhand is in appeal against the judgment of the High Court of Jharkhand allowing Section 3 72[In Arbitration Appeal No. 17 of 2007 dated 11.05.2012] appeal under Arbitration and Conciliation Act, 19963[Hereinafter referred to as the ‘Act’]. The appeal was filed by the respondent-claimant against the judgment of the Civil Court4[Sub-Judge-1, Jamshedpur in Misc. Arbitration Case No. 01/2004 dated 19.04.2007.] setting aside the arbitral award allowing the objections filed by State under Section 3 4 . By its award dated 19.04.2007, the Arbitral Tribunal allowed certain claims but the Civil Court set aside the claims 3, 4 and 6 on the ground that they were specifically prohibited under the contract between the parties.
3. Mr. Rajiv Shankar Dwivedi, learned counsel appearing for the State of Jharkhand has made a short submission that the High Court committed a serious error in allowing the appeal on the ground that the issue arising for consideration is covered by decision of this Court in Bharat Drilling (supra). Mr. Dwivedi has expressed a serious concern that the decision in Bharat Drilling (supra) is being applied, regularly and wrongly, to interpret prohibitory claim clauses in all Government contracts. He would therefore submit that even if the Court may not interfere in the facts of this case, there is a compelling necessity to clarify the position of law. On the other hand, Mr. Manoj C. Mishra, learned counsel appearing for the respondent, supported the decision of the High Court.
4. In view of the concern expressed by Mr. Dwivedi, we agreed to examine the question of law and the principle in Bharat Drilling (supra). Before we proceed any further, it is necessary to examine the relevant clauses under the agreement, which are extracted hereinbelow for ready reference;
4.20.2: No claim for idle labour, idle machinery, etc. on any account will be entertained…
4.20.4: No claim shall be entertained for business loss or any such loss.”
5. It is submitted that the Arbitral Tribunal committed a serious error in allowing claim no. 3 (relating to underutilised overheads) when that claim is barred under clause 4.20.2, claim no. 4 (relating to loss due to underutilised tools, plants and machinery) when such claim is clearly barred under contractual clause 4.20.2. Further, it is also contended that claim no. 6 (relating to loss of profit) could not have been granted in the teeth of clause 4.20.4, which specifically declares that “no claim shall be entertained for business loss or any such loss”.
6. This submission, however, found favour with the Civil Court accepting Section 3 4 objections of the State and setting aside the award on claim nos. 3, 4 and 6. When we peruse the judgment of the High Court under Section 3 7 , we find that there is no discussion whatsoever as regards to claim nos. 3, 4 and 6, except for reference and reliance on the order of this Co
Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors.
Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age
Pam Developments Private Limited v. State of West Bengal
State of Orissa v. N.C. Budharaj
Union of India v. Krafters Engg. & Leasing (P) Ltd.
Port of Calcutta v. Engineers-De-Space-Age
Madnani Construction Corpn. (P) Ltd. v. Union of India
Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd.
Union of India v. Ambica Construction
Ambica Construction v. Union of India
Raveechee & Co. v. Union of India
Reliance Cellulose Products Ltd. v. ONGC Ltd.
State of U.P. v. Harish Chandra
Sayeed Ahmed & Co. v. State of U.P., (2009) 12 SCC 26, paras 14, 23
Union of India v. Saraswat Trading Agency
Sree Kamatchi Amman Constructions v. Railways
Union of India v. Bright Power Projects (India) (P) Ltd., (2015) 9 SCC 695
Jaiprakash Associates Ltd. v. Tehri Hydro Development Corpn. (India) Ltd.
Delhi Airport Metro Express (P) Ltd. v. DMRC
Oriental Structural Engineers (P) Ltd. v. State of Kerala
Central Bank of India v. Ravindra
AI
Arbitration – Applicability of excepted or prohibitory clauses would primarily depend upon the agreement between the parties, which alone is the guiding principle for Arbitral Tribunal.
(1) Appeal against Arbitral Award – Grant of post-award interest is conditional in nature and operates as a deterrent against delayed payment, rather than as an automatic or punitive imposition of po....
An arbitral award can only be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 if the appellant establishes that the award is in conflict with the public policy of India, is p....
Arbitrability of claims hinges on adherence to procedural agreements; claimants can seek interest despite contractual prohibitions, reflecting arbitral authority.
(1) Arbitrator in arbitration proceedings being creature of contract has no power to award interest, contrary to terms of agreement/contract between parties.(2) There cannot be estoppel against law.
(1) If contract contains a specific clause which expressly bars payment of interest, then it is not open for Arbitrator to grant pendente lite interest.(2) Lawful agreement to refer the matter to arb....
The arbitral tribunal can award pendente lite interest unless expressly prohibited by the contractual agreement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.