SUPREME COURT OF INDIA
MANOJ MISRA, JOYMALYA BAGCHI, JJ.
Rattanindia Power Limited – Appellant
Versus
Maharashtra State Electricity Distribution Company Limited And Another – Respondents
Civil Appeal No. 8232 of 2023
Decided On : 10-12-2025
JUDGMENT :
MANOJ MISRA, J.
1. This appeal under Section 125 of the ELECTRICITY ACT , 20031[2003 Act] impugns the order dated 06.10.2023 passed by the Appellate Tribunal For Electricity2[APTEL] in Appeal No.341 of 2023 to the extent it disallows Carrying Cost to RattanIndia Power Limited3[RPL] (the appellant) on compounding interest basis.
FACTS
2. RPL is supplying power to Maharashtra State Electricity Distribution Co. Ltd.4[MSEDCL] (first respondent) under two long term Power Purchase Agreements5[PPA] (i.e., dated 22.04.2010 and 05.06.2010 for supply of 450 MW and 750 MW, respectively) with MSEDCL.
3. In connection therewith, RPL filed a petition (i.e., Case No.84 of 2016) under Section 86 of the 2003 Act before the Maharashtra Electricity Regularity Commission6[MERC] seeking compensation on account of various Change in Law events affecting the project from the date of commencement of supply of power by RPL along with the Carrying Cost, and requested MERC to allow the compensation with effect from the date of commencement of supply.
4. MERC vide order dated 05.04.2018 had allowed certain Change in Law claims. However, it held: (i) increase in rates of Chhattisgarh Paryavaran Upkar Cess and Chhattisgarh Vikas Upkar Cess do not qualify as Change in Law events; (ii) PPAs executed between MSEDCL and RPL do not provide compensation for Carrying Cost and therefore, RPL is not entitled to claim Carrying Cost on its approved Change in Law events; (iii) compensation for approved Change in Law events would be payable from Scheduled Delivery Date (for short SSD) and not for the period prior to SDD, even though supply of power commenced prior to SDD.
5. Aggrieved therewith, RPL filed Appeal No.263 of 2018 before APTEL, which was allowed vide its order dated 18.10.2022. The operative portion of the order dated 18.10.2022 is reproduced below:
(Emphasis supplied)
6. Key observations/ findings in the remand order of APTEL dated 18.10.2022 are as follows:
(ii) Carrying Cost is payable as per the provisions of PPA to compensate the affected party for time value of funds deployed on account of Change in Law events (paragraphs 7 to 11 of the order).
(iii) Liability to compensate for Change in Law events will arise from the date of actual supply of power rather than SDD, particularly, in a case where supply has commenced prior to SDD (paragraphs 13 and 14 of the order).
7. Pursuant to the remand order dated 18.10.2022 requiring MERC to compute the amounts payable by MSEDCL to RPL for restoring it to the same economic position as if the Change in Law event had not occurred, RPL filed an application (i.e., M.A. in Diary No.257 of 2022) before MERC with the following prayer:
Jasraj Inder Singh v. Hemraj Multanchand
Uttar Haryana Bijli Vitran Nigam Ltd. & Another v. Adani Power (Mundra) Ltd. & Another
Jaipur Vidyut Vitran Nigam Ltd. v. Adani Power Rajasthan Ltd.
Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Ltd. and another
Dhakeshwari Cotton Mills Ltd. v. Commissioner of Income Tax, West Bengal
Laliteshwar Prasad Sahi v. Bateshwar Prasad
A. Subash Babu v. State of A.P., (2011) 7 SCC 616
Carrying Cost is compensable for Change in Law events, and the affected party must be restored to its original economic position, supporting claims for compound interest.
The central legal point established in the judgment is the entitlement to compound interest on carrying cost under the restitutionary principle of the PPAs, emphasizing the aim of restituting the aff....
The term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decis....
The Notification imposing Evacuation Facility Charges constitutes a change in law, entitling the affected party to compensation from that date.
(1) Condition precedent for entertaining appeal under Section 125 of Electricity Act, 2003 is existence of a substantial question – A question of law which arises incidentally or collaterally and has....
Any change resulting in a cost impact on selling electricity constitutes a Change in Law event, entitling affected parties to compensation under PPAs.
Increases in GST and Basic Custom Duty on solar project inputs post-PUA signing qualify as Change in Law events entitling compensation via annuity payments at normative loan rates, with carrying cost....
GST increase from 5% to 12% on renewable devices post-bid is Change in Law under PPA Article 12, entitling annuity compensation at 9.12% over 15 years plus carrying cost, reconciled to commissioned c....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.