SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 2118

SUPREME COURT OF INDIA
MANOJ MISRA, JOYMALYA BAGCHI, JJ.
Rattanindia Power Limited – Appellant
Versus
Maharashtra State Electricity Distribution Company Limited And Another – Respondents
Civil Appeal No. 8232 of 2023
Decided On : 10-12-2025

Advocates appeared:
For the Appellant(s) : Mr. Syed Jafar Alam, AOR Mr. Vishrov Mukerjee, Adv. Mr. Pratyush Singh, Adv. Ms. Juhi Senguttuvan, Adv.
For the Respondent(s): M/S. Udit Kishan And Associates, AOR Mr. B.p. Patil, Sr. Adv. Mr. Udit Gupta, Adv. Mr. Vyom Chaturvedi, Adv. Ms. Pragya Gupta, Adv. Ms. Sneha Singh, Adv. Ms. Prachi Gupta, Adv. Ms. Shaily Gupta, Adv. Mr. Geet Ahuja, Adv. Ms. Purnima Chanana, Adv.

Carrying Cost is compensable for Change in Law events, and the affected party must be restored to its original economic position, supporting claims for compound interest.

Headnote:(A) Electricity Act, 2003 - Section 125 - Appeal against APTEL's order regarding Carrying Cost - Appellant's claim for Carrying Cost on a compounding basis was denied by APTEL, which upheld earlier rulings and required MERC to compute Carrying Cost based on LPS rates - Compounding of interest was contested by RatanIndia Power Limited. (Paras 1, 3, 11, 53)

(B) Carrying Cost - Definition and relevance in compensating the affected party for time value of funds due to Change in Law - The court noted, 'Carrying Cost is payable as per the provisions of PPA to compensate the affected party for time value of funds.' (Paras 13, 15)

(C) Jurisdiction and Binding Nature of Remand Orders - The court held, 'When a Court or Appellate Tribunal remands a matter...the issue remanded is alive and has to be decided as per law applicable on the date of the decision.' (Paras 40, 42)

Facts of the case:
RattanIndia Power Limited appealed against the denial of Carrying Cost on a compounding basis for Change in Law events affecting power supply contracts, following a remand from the Appellate Tribunal for Electricity.

Findings of Court:
It was determined that the earlier APTEL orders constrained MERC's computations; however, the claim for compounding interest is to be decided fresh.

Issues: Whether LPS on Carrying Cost is applicable, and if the decision for compounding interest should be granted.

Ratio Decidendi: The appellate court reinforced the notion that compensation should restore the affected party's original economic position while affirming the applicability of Change in Law events and the computation of Carrying Cost.

Result: Appeal allowed with directions to remand the matter for the issue of compounding interest to be decided.

JUDGMENT :

MANOJ MISRA, J.

1. This appeal under Section 125 of the ELECTRICITY ACT , 20031[2003 Act] impugns the order dated 06.10.2023 passed by the Appellate Tribunal For Electricity2[APTEL] in Appeal No.341 of 2023 to the extent it disallows Carrying Cost to RattanIndia Power Limited3[RPL] (the appellant) on compounding interest basis.

FACTS

2. RPL is supplying power to Maharashtra State Electricity Distribution Co. Ltd.4[MSEDCL] (first respondent) under two long term Power Purchase Agreements5[PPA] (i.e., dated 22.04.2010 and 05.06.2010 for supply of 450 MW and 750 MW, respectively) with MSEDCL.

3. In connection therewith, RPL filed a petition (i.e., Case No.84 of 2016) under Section 86 of the 2003 Act before the Maharashtra Electricity Regularity Commission6[MERC] seeking compensation on account of various Change in Law events affecting the project from the date of commencement of supply of power by RPL along with the Carrying Cost, and requested MERC to allow the compensation with effect from the date of commencement of supply.

4. MERC vide order dated 05.04.2018 had allowed certain Change in Law claims. However, it held: (i) increase in rates of Chhattisgarh Paryavaran Upkar Cess and Chhattisgarh Vikas Upkar Cess do not qualify as Change in Law events; (ii) PPAs executed between MSEDCL and RPL do not provide compensation for Carrying Cost and therefore, RPL is not entitled to claim Carrying Cost on its approved Change in Law events; (iii) compensation for approved Change in Law events would be payable from Scheduled Delivery Date (for short SSD) and not for the period prior to SDD, even though supply of power commenced prior to SDD.

5. Aggrieved therewith, RPL filed Appeal No.263 of 2018 before APTEL, which was allowed vide its order dated 18.10.2022. The operative portion of the order dated 18.10.2022 is reproduced below:

    “The impugned order to the extent it ruled against the appellant on the three above mentioned subjects is set aside. The matter to that extent is remitted to the State Commission for fresh decision bearing in mind the observations recorded as above. We shall also expect the State Commission to pass all consequential orders including quantification of the amounts payable by the licensee unto the appellant. Of course, for such purposes the Commission will ascertain the calculations from the appellant and then take the views of the licensee before determining the actual liability. We direct that the Commission shall pass all necessary orders in the wake of such determination including by taking appropriate measures such that the claims are duly satisfied in a time bound manner, expeditiously and at an early date, not later than three months from the date of this judgment.”

    (Emphasis supplied)

6. Key observations/ findings in the remand order of APTEL dated 18.10.2022 are as follows:

    (i) Impact of levy of Environment Cess and Development Cess by the State of Chhattisgarh adds to the burden of RPL inasmuch as it is passed through against the procurement of fuel from sources in the State of Chhattisgarh (paragraph 5 of the order).

    (ii) Carrying Cost is payable as per the provisions of PPA to compensate the affected party for time value of funds deployed on account of Change in Law events (paragraphs 7 to 11 of the order).

    (iii) Liability to compensate for Change in Law events will arise from the date of actual supply of power rather than SDD, particularly, in a case where supply has commenced prior to SDD (paragraphs 13 and 14 of the order).

7. Pursuant to the remand order dated 18.10.2022 requiring MERC to compute the amounts payable by MSEDCL to RPL for restoring it to the same economic position as if the Change in Law event had not occurred, RPL filed an application (i.e., M.A. in Diary No.257 of 2022) before MERC with the following prayer:

    (a) Direct MSEDCL to make payment of Rs.98.79 Cr. (including Carrying Cost of Rs.54.13 Cr.) in accordance with the order dated 18.10.2022 passed by APTEL in Appeal No.263 of 2

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top