SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2026 Supreme(SC) 113

SUPREME COURT OF INDIA
PAMIDIGHANTAM SRI NARASIMHA, ATUL S. CHANDURKAR, JJ.
M/s Saisudhir Energy Ltd. – Appellant
Versus
M/s NTPC Vidyut Vyapar Nigam Ltd. – Respondent
Civil Appeal Nos. 12892-12893 of 2024
With
M/s NTPC Vidyut Vyapar Nigam Ltd. – Appellant
Versus
M/s Saisudhir Energy Ltd. – Respondent
Civil Appeal Nos. 12894-12895 of 2024
Decided On : 30-01-2026

Important Points

The court clarified that in public utility projects, liquidated damages may be claimed without proof of actual loss, reinforcing the importance of agreed contractual terms.

Subject

Contract Law - Arbitration

Act Referred

Headnote

(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Cross appeals arising from a common judgment regarding liquidated damages due to delays in power plant commissioning under a Power Purchase Agreement (PPA) - The High Court awarded damages of Rs. 20.70 crores after initially setting Rs. 27.06 crores, asserting that the PPA aimed at public utility. (Paras 1, 6, 10, 19)

(B) Liquidated Damages - In accordance with Clause 4.6 of PPA, damages are pre-estimated losses for delays and the courts must respect terms agreed unless proven arbitrary. (Paras 12, 18)

(C) Burden of Proof - The arbitral award determined findings on delay and respective damages, with NVVNL not needing to prove actual loss due to public interest considerations. (Paras 14, 16)

Facts of the case:
Two firms were engaged in a PPA for solar power supply, with delays in commissioning leading to liquidated damage claims. The High Court's modification of damages sparked disputes requiring judicial examination of jurisdiction under Sections 34 and 37.

Findings of Court:
Original award set at Rs. 1.2 crores was insufficient, with courts able to modify awards slightly but not overstep parameters of the award.

Issues: Whether the courts appropriately addressed liquidated damages and the burden of proof regarding actual loss.

Ratio Decidendi: Division Bench overstepped its jurisdiction by modifying the damages without basis; the Liquidated Damages following the PPA's details are enforceable irrespective of the claimed actual loss.

Result: Civil Appeal Nos. 12894-12895 allowed, Civil Appeal Nos. 12892-12893 dismissed.
Judgement Key Points

Key Points: - In public utility projects, liquidated damages may be claimed without proof of actual loss, as agreed in the contract (!) . - Courts must respect pre-estimated losses for delays unless proven arbitrary, and cannot reduce agreed amounts without basis (!) (!) . - The burden of proof shifts to the breaching party to show no loss occurred in public interest projects (!) . - Judicial modification of arbitral awards is permissible only to correct errors within the award’s terms, not to substitute the court’s view (!) (!) . - The Division Bench exceeded its jurisdiction by recalculating damages instead of upholding the arbitral determination (!) (!) .

What is the enforceability of liquidated damages clauses in public utility projects when one party fails to meet commissioning deadlines?

How should courts determine the amount of reasonable compensation for delays in public utility projects under pre-agreed contractual terms?

What is the scope of judicial modification of arbitral awards concerning liquidated damages in power purchase agreement disputes?


Legal Category Hierarchy

  • arbitration and conciliation
    • arbitral awards
      • challenge and modification (Para 1, 5, 14, 15, 18)
    • liquidated damages
      • breach of contract (Para 10, 12, 16, 17)
  • administrative and regulatory law
    • public utility projects (Para 6, 12, 16)

Advocates appeared:
For the Appellant(s) : Mr. Gopal Jain, Sr. Adv. Mr. Adarsh Tripathi, AOR Mr. Vikarm Singh Baid, Adv. Mr. Ajitesh Garg, Adv. Mr. Gowtham Polanki, Adv. Mr. Sahil Raveen, AOR
For the Respondent(s): Mr. Gowtham Polanki, Adv. Mr. Sahil Raveen, AOR Mr. Gopal Jain, Sr. Adv. Mr. Adarsh Tripathi, AOR Mr. Vikram Singh Baid, Adv. Mr. Ajitesh Garg, Adv.

Table of Contents

1. Parties dispute liquidated damages claims arising from delays in commissioning a power plant project under a long-term power purchase agreement. (Para 1 , 2 , 3 )

2. Employer asserts entitlement to liquidated damages without proving actual loss in public utility contracts, while the developer challenges the lack of proof of loss and the scope of judicial modifications. (Para 7 , 8 )

3. The court found the project involved public interest, justifying liquidated damages even without proof of actual loss, but held the appellate court exceeded its scope by recalculating damages. (Para 16 , 18 )

4. In public utility contracts, liquidated damages for breach are recoverable without explicit proof of actual loss, and appellate courts cannot modify awards beyond the permissible scope of judicial review. (Para 14 , 15 , 18 )

5. The High Court division bench's modification of liquidated damages is set aside, restoring the judgment of the single judge. (Para 19 )

6. Is proof of actual loss required for claiming liquidated damages in a public utility project?

No. In projects involving public utility or interest, the party complaining of a breach is entitled to reasonable compensation per the contract without needing to prove actual damage or loss. (Para 12 , 16 )

7. Can a court under Section 34 of the Arbitration and Conciliation Act modify an arbitral award?

Yes, consistent with the limited power of modification, a court can modify or vary an arbitral award provided it remains within the statutory guardrails and does not involve re-evaluating the merits of the dispute. (Para 14 , 15 )

8. What is the permissible scope of interference by an appellate court under Section 37 in arbitral proceedings?

An appellate court must restrict its review to determining whether the Section 34 court exercised its jurisdiction properly. It cannot substitute its own findings or re-calculate damages unless the original determination was fundamentally arbitrary or perverse. (Para 18 )

JUDGMENT :

ATUL S. CHANDURKAR, J.

1. These cross appeals arise out of the common judgment passed by the Division Bench of the Delhi High Court dated 18.01.2018 in proceedings filed under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, “the Act of 1996”). Broadly, the dispute between the parties relates to the claim for liquidated damages raised by the employer against the Solar Power Developer on account of delay caused in commissioning a power plant. A three-member Arbitral Tribunal while holding that there was a delay in commissioning the power plant, by majority, awarded an amount of Rs.1.2 crores towards the claim made by the employer. Both parties raised objections under Section 34 of the Act of 1996. A learned Single Judge of the Delhi High Court proceeded to grant an amount of Rs. 27.06 crores to the employer on account of delay on the part of the Solar Power Developer in commissioning the power plant. Both parties further took recourse to of the Act of 1996. By the impugned judgment, the Division Bench modified the order passed under of the Act of 1996 in the matter of grant of liquidated damages and reduced the amount to Rs. 20.70 crores.

2. The facts relevant for considering the challenge as raised by the parties to the aforesaid common judgment are that, in 2010 the Ministry of Power, Government of India, launched the Jawaharlal Nehru National Solar Mission (for short, “the JNNSM”) with the objective of deploying 20000 Mega Watt (MW) of grid connected solar power in three phases by 2022 at a reasonable cost. The JNNSM postulated bundling of solar power alongwith cheaper power from and out of the unallocated quota of central stations and thereafter selling the said bundled power to the State distribution utilities at a regulated price.

3. The Ministry of Power designated NTPC Vidyut Vyapar Nigam Limited (for short, “NVVNL”) as the nodal agency. NVVNL was required to enter into Power Purchase agreements with Solar Power Developers at a fixed rate for twenty-five years. The bundled-up power was to be sold by NVVNL to various distribution utilities at prices determined by the Regulatory Commission. Accordingly, on 24.01.2012, a Power Purchase Agreement (for short, “PPA”) was entered into between M/s Saisudhir Energy Limited (for short, “SEL”) and NVVNL. Under the said agreement, SEL agreed to set up and thereafter supply 20 MW solar power at the rate of Rs. 8.22 per unit, which was a discounted price from the tariff approved by the Regulatory Commission of Rs. 15.39 per unit. Under the said agreement, the date of commissioning supply of 20 MW solar power was 26.02.2013. Clause 4.6 of the PPA provided for liquidated damages in case there was a delay in commencement of supply of solar power to NVVNL. On 30.01.2013, SEL sought extension of time by two months from NVVNL citing various exigencies and invoked the force majeure clause. This request was, however, rejected by NVVNL on 31.01.2013 as notice of seven days as required under Clause 11.5.1 of the PPA was not given. SEL failed to commission its project by 26.02.2013. It commissioned supply of 10 MW power from 26.04.2013, which was after a delay of two months. Thereafter, it commissioned supply for the balance 10 MW power from 24.07.2013, which was after a delay of about five months. SEL, thereafter, moved an application under Section 9 of the Act of 1996 before the Delhi High Court seeking to restrain NVVNL from encashing the bank guarantees furnished by it. The High Court granted interim relief in favour of SEL till the consideration of its prayer for interim relief by the Arbitral Tribunal under Section 17 of the Act of 1996.

4. On invocation of the arbitration clause, a three-member Arbitral Tribunal was constituted. SEL as claimant submitted its claim and sought to restrain NVVNL from encashing the bank guarantees. It also claimed charges for maintenance of the bank guarantees. On the other hand, NVVNL claimed encashment of the bank guarante

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top