SUPREME COURT OF INDIA
PAMIDIGHANTAM SRI NARASIMHA, ALOK ARADHE, JJ.
Sriganesh Chandrasekaran & Others – Appellants
Versus
M/s Unishire Homes LLP & Others – Respondents
Civil Appeal Nos. 10527 - 10528 of 2024
Decided On : 20-02-2026
Consumer Protection Act, 2019 – Section 67 – Real estate – Joint Development Agreement (JDA) – Delay in handing over possession of flats – Developer directed by National Commission to complete construction of flats allotted to appellants, obtain occupancy certificate, and handover possession of flats within three months – Developer further directed to pay 6% interest on amount deposited by appellants from due date of possession – In respect of flats falling in developer’s share, developer has right to enter into sale agreements, undertake construction, receive consideration, transfer possession and convey title – Construction has to be carried out by developer – Delay in delivery of possession is in respect of flats falling to share of developer – It is not the case of appellants that there was delay in construction on account of any act or omission on part of landowners – Liability to pay delay compensation is sought to be fastened only on the ground that there is relationship of principal and agent – Landowners are jointly responsible with developer to ensure transfer of title to appellants – Commission has rightly directed both landowners and developer to transfer title and execute sale deeds in favour of appellants – For lapse on part of developer, landowners, who are in no way concerned with construction, cannot be held liable for deficiency in service, particularly when developer has indemnified them against acts of commission or omission in construction – Appeals dismissed. (Paras 14, 15 and 17)
Facts of the case:
These appeals, filed under Section 67 of Consumer Protection Act, 2019 arise out of impugned judgment and final orders dated 30.07.2024 and 19.10.2023 passed by National Consumer Disputes Redressal Commission (Commission) in Review Petition and consumer case respectively.
Findings of Court:
In order dated 20.09.2024 passed in Civil Appeal @ Diary No.37702/2024 with SLP (C) @ Diary No.33331/2024, the issue with regard to joint and several liability of landowners and the developer has not been adjudicated. Similarly, order dated 25.07.2023 passed in Civil Appeal No.8418 of 2022 directs the developer alone to pay the delay compensation. Challenge in these appeals is confined to the extent, impugned orders hold landowners not jointly and severally not liable along with the developer for payment of compensation for deficiency in service.
Result : Appeals dismissed.
Ratio Decidendi: In a Joint Development Agreement (JDA) coupled with a General Power of Attorney (GPA) authorizing the developer to handle sales, construction, and possession for its share of flats, the landowners are not jointly and severally liable with the developer for deficiency in service or delay compensation arising from the developer's failure to complete construction and hand over possession, as construction obligations rest solely with the developer, who indemnifies the landowners against such lapses, and no delay is attributable to any act or omission by the landowners. (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) Landowners remain jointly responsible with the developer only to ensure transfer of title and execution of sale deeds to buyers. (!) (!)
JUDGMENT
ALOK ARADHE, J.
1. These appeals, filed under Section 67 of the Consumer Protection Act, 2019 arise out of the impugned judgment and final orders dated 30.07.2024 and 19.10.2023 passed by National Consumer Disputes Redressal Commission (Commission) in the Review Petition and consumer case respectively.
2. Facts giving rise to filing of these appeals, briefly stated, are that landowners entered into a Joint Development Agreement (JDA) with the developer on 24.02.2012 and executed General Power of Attorney (GPA) in favor of the developer. On 21.02.2013, the developer obtained the sanctioned plan and a construction licence. Thereafter, from 29.07.2013, onwards the developer executed the Memoranda of Sale Agreements with the flat buyers. Under the Sale Agreements, the developer agreed to handover the possession of flats within 36 months.
3. The initial 36 months period for handing over the possession of the flats expired on 24.08.2016. The grace period of six months also expired on 24.02.2017. However, the project remained incomplete. On 05.06.2017, the appellants issued a notice seeking redressal for delay in handing over the possession of the flats.
4. The appellants filed a Complaint before the Commission on 18.08.2017 alleging deficiency in service and unfair trade practices. By judgment and final order dated 19.10.2023, the Commission found deficiency in service due to delay of more than six years in handing over the possession of the flats. The developer was directed to complete the construction of the flats allotted to the appellants, obtain occupancy certificate, if not already obtained and handover the possession of the flats within three months from the date of the order. The developer was further directed to pay interest @ 6% per annum on the amount deposited by the appellants from the due date of possession as per their respective agreements till the date of offer of possession, within six weeks, failing which delay interest would carry interest @ 9% per annum. The landowners were not held liable for delay, as the obligation to complete the construction rested solely with the developer.
5. The appellants filed a review petition seeking to hold the landowners jointly and severally liable and to enhance the compensation awarded, to Rs.5/- per square feet per month, as provided in the agreement, along with interest @ 6% per annum. By an order dated 15.12.2023 passed in Chamber, the Commission partly allowed the Review Petition and held the landowners jointly and severally liable for completion of construction and for payment of delay compensation. However, the relief to award delay compensation @ Rs.5/- per square feet along with 6% interest, on the deposits made by the appellants was declined. The Review Petition was accordingly disposed of.
6. The landowners challenged the aforesaid order dated 15.12.2023 before this Court in SLP (C) No.9470/2024. By an order dated 03.05.2024, this Court held that the order dated 15.12.2023 in the Review Petition was passed without affording any opportunity of hearing to the landowners. Accordingly, the order dated 15.12.2023 was set aside and the Commission was directed to dispose of the Review Petition after giving an opportunity of hearing to the contesting parties, within a period of six weeks.
7. By an order dated 30.07.2024, the Commission inter alia held that in view of JDA and Sale Agreement, the landowners cannot be held jointly and severally liable for the deficiency in service. However, the landowners and the developer were directed to transfer the title of the property in question and proceed with the execution of the sale deed in favour of the appellants. The Review Petition was thus partly allowed.
8. The challenge in these appeals is confined to the extent, the impugned orders hold the landowners not jointly and severally not liable along with the developer for payment of compensation for deficiency in service.
9. Learned counsel for the appellants submitted that the lando
Syed Abdul Khader v. Rami Reddy & Ors.
Bangalore Development Authority v. Syndicate Bank
Santhosh Narasimha Murthy & Ors. v. M/s Mantri Castles Pvt. Ltd. & Anr.
Akshay & Anr. v. Aditya & Ors. (Civil Appeal No.3642 of 2018) – Distinguished [Para 9]
Joint Development Agreement (JDA) – Delay in handing over possession of flats – Landowners are jointly responsible with developer to ensure transfer of title to appellants – For lapse on part of deve....
Deficiency in Service – Deficiency in service is manifest as possession has not been offered by the respondents despite payment of nearly 90% of the consideration agreed upon between the parties.
The execution of a conveyance deed and prior acceptance of compensation settle a builder-buyer dispute, preventing subsequent claims of deficiency despite contractual delays.
(1) Unreasonable and unfair - The Complainant cannot be made bound to the terms of the Agreement, which are unreasonable and unfair.(2) Dotted lines - A terms of a contract will not be final and bind....
Consumers cannot be compelled to accept possession of property without proper approvals; they are entitled to refund and compensation for delays.
Developers are liable to pay delay compensation when possession of flats is not delivered within the agreed timeframe, reinforcing consumer rights against unfair contractual terms.
Delayed Compensation - The complainants are entitled for delayed compensation in the form interest @6% per annum on their deposit from 10.09.2015 to 21.02.2018 – On facts, the complaint is partly all....
Consumer agreements with one-sided clauses are unenforceable; delayed possession incurs compensation at 8% interest.
(i) the Opposite Party Developer shall complete the construction of allotted flats/Apartments in all respect within a period of six months from today and shall offer possession to the Complainants af....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.