IN THE HIGH COURT OF KARNATAKA AT BENGALURU
KRISHNA S. DIXIT, J.
Karnataka EMTA Coal Mines Limited – Petitioner
Versus
Karnataka Power Corporation Limited – Respondent
Writ Petition No. 1517 of 2012
Decided On : 19-09-2023
The court examines Article 10 of the Fuel Supply Agreement (FSA) and concludes that the penalty mentioned in the agreement is in the nature of liquidated damages. The court also discusses the provisions of the Indian Contract Act, 1872, including sections 73 and 74, which deal with the recovery of damages for breach of contract. The court refers to various legal principles and precedents to interpret and apply these provisions in the context of the case. The court also considers the role of the Comptroller and Auditor General (CAG) and the Advocate General (AG) in the audit process and the basis for the impugned demand.
Fact of the Case:
Petitioners, companies incorporated under the Companies Act, are complaining against a letter from KPCL demanding penalties. The impugned letter demands penalties for non-commencement of coal supply, recovery of difference in cost for arranging supply of coal, and short supply of coal. The petitioners argue that the clauses of the Fuel Supply Agreement do not authorize KPCL to quantify damages and levy penalty without judicial determination. KPCL argues that the clauses authorize it to assess damages and determine compensation/penalty for breach. The court frames questions for determination, including whether contractual disputes can be examined in writ jurisdiction, whether principles of natural justice apply to private contracts, and whether the penalty mentioned in the agreement is in the nature of liquidated damages. The court discusses these questions and concludes that writ jurisdiction can be invoked in contractual matters involving public law elements, principles of natural justice apply to contracts with public law elements, and the penalty mentioned in the agreement is in the nature of liquidated damages. The court also examines the basis of the impugned demand, including the CAG/AG audit report and the opinion of the Advocate General. The court finds that the report and opinion cannot be the sole basis for the demand and that the petitioners were not given an opportunity to participate in the audit proceedings. The court quashes the impugned order to the extent it levies penalties and remands the matter to KPCL for de novo determination of the amount payable by the petitioners for the actual cost of procurement of coal from alternative source.
Finding of the Court:
The court examines the questions framed for determination, including whether contractual disputes can be examined in writ jurisdiction, whether principles of natural justice apply to private contracts, and whether the penalty mentioned in the agreement is in the nature of liquidated damages. The court concludes that writ jurisdiction can be invoked in contractual matters involving public law elements, principles of natural justice apply to contracts with public law elements, and the penalty mentioned in the agreement is in the nature of liquidated damages. The court also examines the basis of the impugned demand, including the CAG/AG audit report and the opinion of the Advocate General. The court finds that the report and opinion cannot be the sole basis for the demand and that the petitioners were not given an opportunity to participate in the audit proceedings.
Ratio Decidendi: Writ jurisdiction can be invoked in contractual matters involving public law elements. Principles of natural justice apply to contracts with public law elements. The penalty mentioned in the agreement is in the nature of liquidated damages. The report of CAG/AG and the opinion of the Advocate General cannot be the sole basis for a demand without giving the affected party an opportunity to participate in the proceedings.
Result: The court quashes the impugned order to the extent it levies penalties and remands the matter to KPCL for de novo determination of the amount payable by the petitioners for the actual cost of procurement of coal from alternative source.
ORDER:
1. Petitioners being the companies incorporated under the provisions of erstwhile Companies Act, 1956, are complaining before the Writ Court against the letter dated 12.12.2011 issued by the first respondent-KPCL demanding from them a sum of Rs. 52,63,00,000/- by way of penalties.
2. The relevant part of the impugned letter reads as under:
(a) ‘Non-commencement of supply of coal to BTPS’ - amounting to 33 crores as per clause 10.2 of the Article 10 of Fuel Supply Agreement executed on 09.05.2007. As discussed in the 38th Board Meeting held on 19.11.2010 of KECML, the issue of recovery of penalty amounting to 33 crores, was referred to the Advocate General, Karnataka, who has opined for imposition of the penalty as per the terms and conditions of the Fuel Supply Agreement, which was informed vide our letter cited at ref (1) above.
(b) ‘Recovery of difference in cost for arranging supply of coal from alternate sources’ - amounting to 16.44 crores as per clause 10.5 of the Article 10 of Fuel Supply Agreement executed on 09.05.2007. As informed vide our letter cited at ref (2) above, the Technical Committee of KPCL had recommended for recovery of the penalty amounting to 16.91 crores as per clause 10.5 of the FSA. Further, the Advocate General, Karnataka, has also opined for recovery of difference in cost in respect of the entire supply of coal arranged by KPCL from alternate source.
(c) ‘Short supply after commencement of supply of coal to BTPS from the captive coal mines’ - amounting to 5.72 crores as per clause 10.4 of the Article 10 of Fuel Supply Agreement executed on 09.05.2007. Out of the total recovery of 5.72 crores, an amount of 3.00 crores has already been recovered. The AG Auditors have objected for the non-recovery of the amount as per the clause 10.4 of the FSA.
In this regard, KECML is requested to remit an amount of 52.63 crores immediately, in respect of the above issues, or else, KPCL will be left with no other alternative but to recover the amount from the payments released to KECML, since our Auditors are objecting for the non-recovery of penalty as per the clauses of the Fuel Supply Agreement executed on 09.05.2007...”
3. After service of notice, the first respondent (hereafter ‘KPCL’) has entered appearance through its Panel Counsel; the second respondent-Government is represented by the learned AGA. The KPCL has filed its Statement of Objections on 20.07.2013 resisting the petition. Learned Sr. Advocate appearing for the KPCL made submission in justification of the impugned demand and the reasons on which it has been structured. This court hastens to mention that its suggestion to explore the possibility of arbitration, absence of such a clause in the subject Agreement notwithstanding, was acceded to by the petitioners; however, the KPCL being a State Government Company, its learned Sr. Advocate expressed the constraints of his client in that regard.
4. CASE OF THE PETITIONERS:
(b) The Coal Ministry of Central Government vide letter dated 10.11.2003 allocated cert
Writ jurisdiction can be invoked in contractual matters involving public law elements. Principles of natural justice apply to contracts with public law elements. The penalty mentioned in the agreemen....
Retrospective termination of Fuel Supply Agreements is lawful under the Indian Contract Act, provided it follows the terms of the agreement, and contractual disputes are generally not suitable for wr....
The demand for compensation for short lifting of coal was impermissible as no loss was incurred by the respondent. The court restrained the respondent from encashing the bank guarantee, as it would r....
An authority must adhere to contract terms, including timely communication of penalties and an opportunity to rectify, or face quashing of arbitrary demands.
A writ petition can be dismissed for lack of maintainability if an arbitration clause exists; however, constitutional violations may warrant judicial review.
Writ jurisdiction under Article 226 cannot adjudicate disputes arising from contracts or address complex questions of fact needing evidence.
The obligation of the state to act fairly and reasonably in contractual disputes, and the importance of respecting the specific terms of a contract.
The respondent-CCL must satisfy itself regarding the authenticity of the end use of coal by calling for/inspecting the documents and by physical verification as per Clause 4.4 of the FSA. The princip....
Unilateral deductions from contractual payments without notice violate principles of natural justice and are illegal under Article 14 of the Constitution.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.