IN THE HIGH COURT OF KARNATAKA AT BENGALURU
ANU SIVARAMAN, RAJESH RAI K., JJ.
State Load Dispatch Center, Operated By Karnataka Power Transmission Corporation Limited, Represented By Its Chief Engineer – Appellant
Versus
NSL Sugars Limited, Represented By Its Authorised Signatory – Respondent
Writ Appeal No. 529 Of 2024 (GM-KEB) C/W Writ Appeal No. 526 Of 2024 (GM-KEB) Writ Appeal No. 530 Of 2024 (GM-KEB), Writ Appeal No. 557 Of 2024 (GM-KEB), Writ Appeal No. 623 Of 2024 (GM-KEB)
Decided On : 19-12-2025
| Table of Content |
|---|
| 1. writ appeals allowed; judgment of learned single judge set aside. (Para 1) |
| 2. background facts regarding electricity generation in karnataka. (Para 2 , 3 , 4 , 5) |
| 3. court's observations on jurisdictional implications. (Para 6 , 8 , 20 , 21) |
| 4. arguments concerning the jurisdiction of appropriate government. (Para 7 , 9 , 10 , 11 , 12 , 19) |
| 5. interpretation of statutory provisions regarding emergency powers. (Para 18 , 33 , 34 , 35 , 43) |
| 6. clarification on the applicability of section 11 of the act. (Para 49) |
JUDGMENT :
RAJESH RAI K., J.
1. Writ Appeals No.529/2024, 526/2024 and 530/2024 are by State Load Despatch Centre (SLDC), Writ Appeal No.557/2024 is by the Karnataka Power Transmission Corporation Limited (KPTCL) and Writ Appeal No.623/2024 is by the State of Karnataka, challenging the common order dated 11.03.2024 passed by the learned Single Judge in W.P.No.24998/2023, 24239/2023, 26833/2023 and 26324/2023, whereby the learned Single Judge has allowed the said petitions as under:
"The petitions are allowed quashing the impugned State Government’s Order dated 16.10.2023 in No. ENERGY 82 PPT 2023 insofar as it extends to those engaged in inter-state transmission of electricity and the following consequential withdrawal of approval / No-Objections issued by M/s KPTCL [the State Load Dispatch Centre] to the respective petitioners.
[A] the Communication dated 18.09.2023 [Annexure - B in WP No.24998/2023]
[B] the Communication dated 17.10.2023 [Annexure - B in WP No. 26324/2023]
[C] the Communication dated 18.10.2023 [Annexure - B in WP No. 26833/2023]
Consequentially, M/s KPTCL, the State Load Dispatch Centre, is directed to reinstate the corresponding approvals/No-objection issued to the petitioners in W.P.No.24998/2023 and W.P.No.23624/2023, and insofar as the petitions in W.P.No.24239/2023 and W.P.No.26833/2023, M/s KPTCL is directed to consider the respective requests in the light of this order."
2. The abridged facts for disposal of these collective Writ Appeals are as under:
Electricity generation in the State of Karnataka is primarily dependent on renewable and hydel sources. Owing to depleted reservoir levels in major dams, the State Load Dispatch Centre was compelled to implement load management measures since the August of 2023. As the Electricity Supply Companies’ effort to procure power from exchanges at maximum cap rates proved insufficient, the Government of Karnataka issued the Government Order dated 16.10.2023 under Section 11 (1) of the Electricity Act, 2003 (hereinafter referred to as "the Act") directing all generators within the State to operate and maintain generating stations at maximum exportable capacity and supply all electricity generated to the State Grid at a provisional tariff of Rs.4.86 per unit, subject to final determination by KERC under (2) of the Act, which reads as under:
GOVERNMENT ORDER No. ENERGY 82 PPT 2023, BENGALURU, Dated 16.10.2023
In the circumstances explained in the Preamble and in exercise of the power conferred under Section.11 of Electricity Act, 2003, the State Government in the public interest hereby issues the following Directions, with immediate effect and until further orders.
1. All the Generators in the State of Karnataka shall operate and maintain their generating stations to maximum exportable capacity and supply all the electricity generated to State Grid subject to the following conditions:
[a] ESCOMs shall pay at Rs.4.86/unit provisionally subject to KERC orders thereon.
[b] The balance capacity of UPCL plant, over and above the contracted capacity with the ESCOMs under the PPA shall be supplied to State Grid at PPA rates.
[c] Joint meter readings shall be the basis for raising the monthly invoices.
[d] Rebate of 2% shall be allowed on the bill amount if payment is made within 5 days from the date of presentation of bill or otherwise 1% shall be allowed if the payments are made within 30 days.
[e] Due date for making payment shall be 30 days from the date o


Kunhayammed v. State of Kerala
M/s GMR Energy Limited v. Government of Karnataka
Narendra & Co. (P) Ltd. v. Workmen
The appropriate government under Section 11 of the Electricity Act is the State Government for embedded generators facing state-specific extraordinary circumstances, reaffirming that jurisdiction doe....
The State cannot grant financial incentives like rebates to distribution licensees for prompt payments while compelling generating companies to supply power, as this constitutes an unlawful financial....
The court ruled that challenges to past decisions cannot be re-litigated in separate writ petitions if they are pending appeals, emphasizing principles of res judicata.
State cannot grant rebates to distribution licensees while compelling power supply under public interest directives, as it undermines the interests of generating companies.
The State Government cannot discriminate between similarly situated industrial units in the matter of supply of electricity.
The Central Government lacks the legislative competence to frame rules regarding open access in electricity, which is exclusively regulated by the State Commission under the Electricity Act.
The State Government's directions under Section 108 of the 2003 act are binding on the State Electricity Regulatory Commission, and the principles of promissory estoppel and legitimate expectation ar....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.